L-4_Sample_Task_1-CLIN_0002_Lot_I_Only_Technical_v2.docx
DOCX document 27 KB Posted
- Attached to
- Aircraft Prototype Systems Division (APSD) Research, Development, Test & Evaluation Prototyping and Production Contract Federal contract opportunity
- Solicitation number
- N00421-16-R-0040
About this file
Attachment L-4 V.2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Final_RFP_QAs_85-90.pdf | ||
| N00421-16-R-0040-0002_Conformed.pdf | ||
| N00421-16-R-0040-0002_SF30.pdf | ||
| N00421-16-R-0040-0001_SF30.pdf | ||
| L-7_Vol_3_T-1_SB_Goals_v1.xlsx | XLSX spreadsheet | |
| L-3a_Vol_2_PP-1_PP_Cont_Data_v1.xlsx | XLSX spreadsheet | |
| L-8_Vol_4_CE_Tables_v1.xlsx | XLSX spreadsheet | |
| L-4_Sample_Task_1-CLIN_0002_Lot_I_Only_Technical_v1.docx | DOCX document | |
| L-3b_Vol_2_PP-1_PP_Cont_Data_v1.xlsx | XLSX spreadsheet | |
| Final_RFP_QAs_1-84.pdf | ||
| L-5_Sample_Task_2-CLIN_0002_Lot_II_Only_Technical_v1.docx | DOCX document | |
| Final_J_Attachments.zip | ZIP file | |
| N00421-16-R-0040_APF_APSD_Prototyping_and_Limited_Production_Final_RFP.pdf | ||
| Final_L_Attachments.zip | ZIP file |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N00421-16-R-0040 Sample Task 1: CLIN 0002 Lot I Only Sample Task 1: CLIN 0002 Prototype, Validation and Verification Systems (Lot I Only)
Sample Task 1 is for Lot I evaluation purposes only. This sample task will not result in an award of an actual delivery order. This sample task is for technical and cost evaluation purposes only.
This sample task is representative of a Lot I requirement. Tasks performed under this effort would be representative of requirements from the following SOW sections from solicitation N00421-16-R-0040:
· Section 4.0 Overall Requirements
· Section 4.1 Lot I Requirements
· Section 4.4 CLIN 0X02 Prototype, Validation and Verification Systems
· Section 4.7 CLIN 0X05 Travel in Support of CLIN 0X01, 0X02, and 0X03
· Section 4.8 CLIN 0X06 Contract Data Requirements List (CDRLS)
This task would be a non-severable supply completion Cost Plus Fixed Fee contract.
Overview The following scenario is representative of a complex program to missionize a legacy fixed wing aircraft to support an Other Government Agency. In this scenario, the Other Government Agency has provided a mission system specification and identified three legacy medium cargo lift mission fixed wing assets (approximately size of CN-235) for the modification. NAVAIR will be responsible for providing the OGA a flight clearance recommendation. The AIRWorks office, supported by APSD and other NAVAIR technical experts, will provide programmatic and technical oversight, define airworthiness EDRAP requirements, and conduct Government Acceptance Testing. The Contractor shall be required to execute the system architecture development, mission suite component procurements, hardware and software integration design, analysis for airworthiness, fabrication, installation, functional system testing and provisioning of technical and logistics data. The Contractor shall produce one prototype aircraft. The mission system will include:
· Required Navigation Performance for Area Navigation (RNP/RNAV)
· Mode Select (Mode S) – Enhanced Surveillance (EHS)
· Mode 5 Identification Friend or Foe (IFF)
· Automatic Dependent Surveillance – Broadcast (ADS-B) Out
· 8.33 kHz VHF Channel Spacing
· Traffic Collision Avoidance System (TCAS)
· Enhanced Terrain Awareness Warning (Predictive)
· Automatic Flight Control
· Multifunction Display System
· Flight Management System
· Air Traffic Management (ATM) and Command and Control (C2) Data Link
· Digital Maps
The mission system shall include software to allow the command and control of the sensors through a graphical user interface.
Assumptions
· Contract award 1 Dec 2017
· Aircraft are in flight worthy condition
· OGA will perform maintenance actions post modification to return to flight ready condition
· Aircraft baseline electrical loads analysis is not available.
· Aircraft baseline electrical system schematics and wiring diagrams are available.
· Aircraft baseline structural drawings are available.
· Aircraft baseline 3D models of exterior outer mold line and inner mold line are not available.
· Aircraft baseline critical flight conditions data is available
· Aircraft baseline aerodynamic CFD model is not available
· Aircraft baseline structural loads FEA model is not available
· GFE:
· 1 aircraft
· OTHER CONDITIONS:
· The aircraft shall be available for delivery to the contractor site no later than thirty days from contract award.
Place of Performance All activities prior to Government Acceptance Testing will occur at the Contractors facilities inclusive of air vehicle modification activities.
Notional Delivery Requirement Schedule:
24 months from contract award to prototype installation complete and ready for ground test with the Level III Technical Data Package to be delivered 60 days after completion of installation.
Requirements:
Based on the information above, the Contractor shall design, document, analyze for airworthiness, procure materials for, fabricate, install the aircraft modification kit and perform contractor system functional ground testing. The Contractor shall also develop technical publications that support the operational use of the system.
Reference the 10310 data package. Use this data package to assess the scope and complexity of the finished A-Kit data package. The Government will authorize the Contractor to modify the aircraft after completing CDR and IRR. The installation period shall begin after the Government grants authority to modify and ends prior to contractor flight test. The contractor shall have 6 months to complete the installation phase of the project.
Expected Deliverables:
One prototype aircraft with functional mission systems ready for Government Acceptance Testing and supporting publications.
Contract Data Requirements List:
These CDRLs are listed for reference only and are not required to be delivered as part of the sample task response. The offeror may reference these CDRLs as necessary when responding to this sample task.
· CDRL A001 Contractor Progress Report (Monthly)
· CDRL A002 Contractor Financial Report (Monthly)
· CDRL A003 Contract Data Accession List (DAL)
· CDRL A004 Certificate of Conformance (per aircraft)
· CDRL A005 Quality Assurance Inspection Documents (QA record for each installation and manufactured item)
· CDRL A006 Level III Technical Data Package inclusive of all native files and Master Bill of Materials
· CDRL A007 Structural Analysis Report
· CDRL A008 Weight and Balance Report
· CDRL A009 Electrical Loads Analysis Report
· CDRL A010 Power Check Report
· CDRL A011 Contractor Test and Evaluation Master Plan
· CDRL A012 Aircraft Baseline Electrical Loads Report
· CDRL A013 Aircraft Baseline Structural 3D model
· CDRL A013 Aircraft Structural Finite Element Analysis model
· CDRL A014 Interface Control Documents (ICDs)
· CDRL A015 Interface Design Documents (IDDs)
· CDRL A016 Installation Control Drawings (ICDs)
· CDRL A017 Operator Manual
· CDRL A018 Failure Modes, Effects and Criticality Analysis (FMECA)
· CDRL A019 Failure Reporting, Analysis and Corrective Action System Report (FRACAS)
· CDRL A020 Supportability Analysis Plan
· CDRL A021 Logistics Product Data
· CDRL A022 Level of Repair Analysis (LORA)
· CDRL A023 Interim Spares Item List (ISIL)
· CDRL A024 Source Data for Technical Manuals
· CDRL A025 Support Equipment Candidate List (SECL)
· CDRL A026 Operator and Maintainer Training Manuals
· CDRL A027 Mission System Software Source Code
· CDRL A028 Software Description Document
· CDRL A029 System Requirements Review Slide Presentation for A-Kit integration Requirements
· CDRL A030 Preliminary Design Review Slide Presentation
· CDRL A031 Critical Design Review Slide Presentation
· CDRL A032 Integration Readiness Review Slide Presentation
· CDRL A033 Test Readiness Review Slide Presentation
· CDRL A034 Contractor Test Results Report
· CDRL A035 Principles of Operation Publications
· CDRL A036 Testing & Troubleshooting Publications
· CDRL A037 Maintenance Procedures Publications
· CDRL A038 Illustrated Parts Breakdown Publications Technical Narrative Instructions The offerors shall provide a narrative to define the technical approach to the execution of the sample task.
The narrative shall describe the following:
1. Offerors assumptions
2. Technical and management approach to achieve the required deliverable state covering at a minimum:
2.1. Overall management approach
2.2. Systems Engineering and development approach
2.3. Integration Engineering and TDP development
2.4. Airworthiness baseline development and modification substantiation approach
2.5. Technical Interchange meetings and Approval points
2.6. Procurement, handling, and kitting
2.7. Aircraft kit fabrication and installations
2.8. Functional system testing
2.9. Technical Publication Development IAW CDRLS A017-A038
2.10. Notional high level schedule that includes:
2.10.1. Overall milestone and SETR events
2.10.2. Deliveries from Subcontractors
2.10.3. Required by dates for GFI/GFE or OEM Data based on assumptions
3. How the offerors AS9100 processes align with those work flow tasks
4. The offerors overall staffing and teaming approach including:
4.1. Identify those areas of the contract or task to be performed by the Prime or passed to subcontractors and vendor team mates
4.2. How the Prime will monitor the subcontractor performance, quality of work and will be managed to ensure integration into the overall team and management approach
Sample Task 1: Unrestricted