QA 71-73.pdf
PDF 101 KB Posted
- Attached to
- Machine Shop Rapid Prototyping Solicitation Federal contract opportunity
- Solicitation number
- N0017822R4305
About this file
This document contains questions and answers related to a federal solicitation for machine shop rapid prototyping services. The solicitation seeks proposals for indefinite-delivery, indefinite-quantity contracts with firm-fixed-pricing and five-year ordering periods to manufacture, assemble, inspect, and deliver machined prototypes and assemblies. The combined value of all delivery orders under all awarded contracts shall not exceed $50 million. This opportunity is set aside for small businesses and represents the government's requirements, superseding information from any previous postings. The Naval Surface Warfare Center, Dahlgren Division is the contracting agency within the Department of the Navy Naval Sea Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA 82.pdf | ||
| N0017822R4305 AMENDMENT 0002.pdf | ||
| QA 80 - 81.pdf | ||
| QA 76-79.pdf | ||
| QA 74-75.pdf | ||
| QA 69-70.pdf | ||
| N0017822R4305 Amend 0001.pdf | ||
| QA 38-51.pdf | ||
| QA 52-68.pdf | ||
| Q10-Q37.pdf | ||
| Q4-Q9.pdf | ||
| QA 2-3.pdf | ||
| QA 1.pdf | ||
| MSMAIDIQ - CDRL A003.pdf | ||
| MSMAIDIQ - CDRL A001.pdf | ||
| MSMAIDIQ - CDRL A002.pdf | ||
| N0017822R4305.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0017822R4305 Machine Shop Rapid Prototyping Solicitation
Questions and Answers
PLEASE NOTE that the Technical Data Package is provided only to those Offerors that successfully complete the Solicitation instructions at L.4.3.
Q71: The artwork provided via the model does not match the artwork shown on drawing SK101949. Please confirm that we should use the artwork provided in the model.
A71: The artwork in the model should be utilized.
Q72: Is there a way to request the RFP response date (sample shipment) be extended?
A72: No, the proposal due date (including bid sample) remains as stated in Amendment 0001.
Q73: Our primary concern is that the Q&A conflicts with the drawing package/models. The RFP states that if the unit doesn’t match the requirements, it will be found unacceptable. Does the Q&A override the drawings/models, or do the drawings/models take precedence over the Q&A? Or, will a new drawing package be released, along with adequate time to build the unit?
A73: A new drawing package will not be released. The questions that were answered should be sufficient to build this package successfully.