This solicitation seeks proposals for the USS LASSEN (DDG 82) FY23 Depot Modernization Period. The Naval Sea Systems Command will execute maintenance, modernization, and repair of the USS LASSEN from December 2022 through August 2024. Interested parties must register in the System for Award Management and Procurement Integrated Enterprise Environment in order to receive solicitation attachments and submit proposals through the latter system by the anticipated award date of September 2022. The Government will make a single award and does not set aside this procurement for small businesses due to its complexity, magnitude, and duration.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPI FORM
| USS LASSEN (DDG 82) DMP N00024-22-R-4486 | RFP | ||||||
| Attachment S-3 Pre-Proposal Information (PPI) Form | Attachment J-1 | ||||||
| NAVSEA POC: | Liz Feliciano, elizabeth.feliciano-hernandez.civ@us.navy.mil, (202) 781-1049 | Attachment J-2 | |||||
| Daniel Breedlove, daniel.j.breedlove.civ@us.navy.mil, (202) 781-0615 | Attachment J-3 | ||||||
| Attachment J-4 | |||||||
| Question # | Date of Request: | Question Area | Work Iem (if applicable) | Section/Para | Contractor Question | Government Response | Attachment J-5 |
| 206 | 4/22/22 | Attachment J-3 | N/A | Execution Milestones and Key Event Dates | Please confirm Attachment J-3 Execution Milestones and Key Event Dates - Rev 3 Availability Start Date: 12/05/22 – Availability Completion Date: 03/01/2024 is still accurate and should be used for Contractors to develop its proposal. |
The Contractor has been made aware of a communication from COMNAVSURFLANT Norfolk, VA that the LASSEM DMP performance performance has shifted to the right. New Availability Start Date: 01/23/23 New Availability Completion Date is 08/16/24.
If the comminication is accurate and the communicated performance period supersedes Attachment J-3 Rev 3 dated 4/21/22, please provide Solicitation Amendment with the updated Attachment J-3 (Rev 4) to reflect accurate Availability Start, Completion and ERL dates.
Attachment J-3 Execution Milestones and Ket Event Dates - Rev 4, provided in Amendment 0007, reflect accurate Availability Start, Completion, and ERL dates.