This document announces a solicitation for the USS LASSEN (DDG 82) FY23 Depot Modernization Period (DMP). The solicitation seeks a contractor to execute maintenance, modernization, and repair of the USS LASSEN from December 2022 through August 2024 at a highly capable East Coast facility. The Naval Sea Systems Command will make a single award by September 2022. Interested offerors must register in SAM and PIEE to receive the full solicitation and restricted attachments, including the statement of work, pricing workbook, and technical references, after requesting access from the contract specialist and technical librarian. The solicitation is not set aside for small businesses due to complexity, magnitude, and duration of requirements.

View the file

Other files

File Type Posted
N00024-22-R-4486 A008.pdf PDF
N00024-22-R-4486 A008 conformed.pdf PDF
USS LASSEN_QA6.xlsx XLSX spreadsheet
N00024-22-R-4486 A007 conformed.pdf PDF
N00024-22-R-4486 A007.pdf PDF
USS LASSEN_QA5.xlsx XLSX spreadsheet
N00024-22-R-4486 A006 conformed.pdf PDF
N00024-22-R-4486 A006.pdf PDF
N00024-22-R-4486 A0005 conformed.pdf PDF
USS LASSEN_QA4.xlsx XLSX spreadsheet
N00024-22-R-4486 A0005.pdf PDF
N00024-22-R-4486 A004 conformed.pdf PDF
N00024-22-R-4486 A004.pdf PDF
N00024-22-R-4486 A003.pdf PDF
USS LASSEN_QA3.xlsx XLSX spreadsheet
N00024-22-R-4486 A003 conformed.pdf PDF
N00024-22-R-4486 A002.pdf PDF
N00024-22-R-4486 A002 conformed.pdf PDF
USS LASSEN_QA2.xlsx XLSX spreadsheet
N00024-22-R-4486 A001.pdf PDF
USS LASSEN_QA1.xlsx XLSX spreadsheet
(USS LASSEN) Attachment S-5 Eligibility Criteria Data Sheet.docx DOCX document
(USS LASSEN) Attachment S-8 Pier and Drydock Graphical Representation.xlsx XLSX spreadsheet
(USS LASSEN) Attachment J-7 IPTD Events SMR.docx DOCX document
(USS LASSEN) Attachment S-3 Pre-Proposal Information (PPI) Form.xlsx XLSX spreadsheet
(USS LASSEN) Attachment J-8 Government Furnished Material (GFM) List.xlsx XLSX spreadsheet
(USS LASSEN) CDRL Exhibit A.pdf PDF
(USS LASSEN) CDRL Exhibit B.pdf PDF
(USS LASSEN) Attachment J-10 20 Percent Open Inspect Milestone Reports Due.xlsx XLSX spreadsheet
(USS LASSEN) Attachment S-9 Past Performance Questionnaire.docx DOCX document
(USS LASSEN) Attachment S-4 Manpower Performance Data Sheet.xlsx XLSX spreadsheet
N00024-22-R-4486_USS LASSEN FY23 DMP.pdf PDF
(USS LASSEN) Attachment J-5 Quality Assurance Surveillance Plan.docx DOCX document
(USS LASSEN) Attachment S-7 Proposal Assessment.xlsx XLSX spreadsheet
(USS LASSEN) CDRL Exhibit C.pdf PDF
(USS LASSEN) Attachment S-2 Past Performance CPARS References.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until local time

X

A X B X C X D

EX

X

G F 188 - 199

200 - 216 X H 217 - 226 daniel.j.breedlove@navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 226

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N00024 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

DANIEL J BREEDLOVE 2027810615

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 99

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

100 - 136 137 - 138

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

139 - 142 143 - 149

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 150 - 160 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 161 - 162 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

163 - 186

PART II - CONTRACT CLAUSES

NAVAL SEA SYSTEMS COMMAND (HQ)

1333 ISAAC HULL AVE SE

WASHINGTON NAVY YARD DC 20376-2030

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

N0002421FR62098C

5. DATE ISSUED

24 Feb 2022

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N0002422R4486

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

1 Lot

AVAILABILITY PREPARATION - USS LASSEN

FFP

The Contractor shall provide all labor, materials, facilities, supervision and equipment to meet the requirements outlined in Section C – Statement of Work, paragraph 9. All work shall be completed in accordance with all applicable local, State, Federal and Navy rules and regulations; whether they are explicitly written/referenced in this SF33 or not.

FOB: Destination

PSC CD: J998

NET AMT

ADVANCED MATERIAL PROCUREMENT

FFP

The Contractor shall provide all labor, materials, facilities, supervision and equipment to meet the requirements outlined in Section C – Statement of Work, paragraph 10. All work shall be completed in accordance with all applicable local, State, Federal and Navy rules and regulations; whether they are explicitly written/referenced in this SF33 or not.

OPTION TYCOM BASE

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

PURCHASE REQUEST NUMBER: N0002421FR62098C

OPTION PMS 407 OPN BASE

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION PMS 407 OMN BASE

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

Reserved (CDRLs)

FFP

Reserved FOB: Destination

OPTION Temporary Service; provide

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION GFM Equipment Warehouse Storage Space

FFP

Government Furnished Material and Equipment Warehouse Storage Space;

provide (Option Item)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Underwater Hull Preservation

FFP

Underwater Hull Preservation with Paint Company Original Equipment Manufacturers' (OEM) Technical Representative; accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Underwater Hull; preserve (OPTION ITEM)

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Messing and Berthing Barge Electric

FFP

Messing and Berthing Barge Electric Temporary Service in Contractor Plant;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION TYCOM OPTION

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION TYCOM OPTION

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Berthing Habitability Project

FFP

Berthing Habitability Project (BOFF-S1055) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (BCPO-S9606) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (BENL-S9608) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (BOFF-S9802) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (HOFF-S1056) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (HCPO-S9607) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (HENL-S9609) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

FFP

Berthing Habitability Project (HOFF-S9803) Installation; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-88260K ERM Hardware installation

FFP

ShipAlt DDG51-88260K, Enterprise Remote Monitoring (ERM) Hardware Installation; accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-94451K, Removal of Alfa Laval (AIT)

FFP

Shipalt DDG51-94451K, Removal of Alfa Laval Pure Bilge Oil/Water Separator, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION ORDALT 80831, BMD-MK99 KAS DDG

FFP

ORDALT 80831, BMD-MK99 KAS DDG Illuminator RAM Material Installation;

accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-91580K, AN/SQQ-89A(V)15 Tech Refresh

FFP

ShipAlt DDG51-91580K, AN/SQQ-89A(V)15 Tech Refresh; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-86222K and 91580K, AN/SQQ-89A(V)15

FFP

ShipAlt DDG51-86222K and 91580K, AN/SQQ-89A(V)15 (TI-18/17) and AN/UQN-10 NGF (Fathometer), Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-80156K, AN/SLQ-32(V)6 (SEWIP)

FFP

ShipAlt DDG51-80156K, AN/SLQ-32(V)6 Surface Electronic Warfare Improvement Program (SEWIP) Block 2 Upgrade; accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION OrdAlt 79353K, Ablative Upgrade (AIT)

FFP

DDG-51 OrdAlt 79353K, Ablative Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION OrdAlt 74588K, Topside KAS Installation

FFP

DDG-51 Class OrdAlt 74588K, Topside KAS Installation, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-93584K, AIS Cyber Hardening, (AIT)

FFP

ShipAlt DDG51-93584K, AIS Cyber Hardening, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-87785K, AS-4775 Link 16 Antenna (AIT)

FFP

ShipAlt DDG-51 87785K, AS-4775 Link 16 Antenna, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-91027K, GPNTS(V)4, (AIT) Service

FFP

ShipAlt DDG51-91027K, GPNTS(V)4, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-86033K, MOS Mod, (AIT) Support

FFP

ShipAlt DDG51-86033K, MOS Mod, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-95946K, C2P Tech Refresh, (AIT)

FFP

ShipAlt DDG51-95946K, C2P Tech Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-75874K, SSEE Inc F, (AIT) Support

FFP

ShipAlt DDG51-75874K, SSEE Inc F, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-94294K, CANES HW2 Tech Refresh, (AIT)

FFP

ShipAlt DDG51-94294K, CANES HW2 Tech Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-79686K and 88635K, Closed-In Weapon

FFP

ShipAlt 79686K and 88635K, Closed-In Weapon System (CIWS) Nex Gen and Blk 1B Overhaul, Alteration Installation Team (AIT) Support Service; provide

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-81961K and 85114K, TTWCS v5.6.0 SA

FFP

ShipAlt DDG51-81961K and 85114K, TTWCS v5.6.0 SA and TMPC 6.0.0 HW SA, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-95676K, Enhanced Collection System

FFP

ShipAlt DDG51-95676K, Enhanced Collection System Hardware, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-94692K, AN/SPS-73(V)18 Installation

FFP

ShipAlt DDG51-94692K, AN/SPS-73(V)18 Installation, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-95861K, A/USQ-52A Training Interface

FFP

ShipAlt DDG51-95861K, A/USQ-52A Training Interface Unit, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION SA-93982K, AN/WSN-12 Install, (AIT)

FFP

ShipAlt DDG51-93982K, AN/WSN-12 Install, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Messing and Berthing Barge Electric

FFP

Messing and Berthing Barge Electric Temporary Service in Contractor Plant;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS LASSEN (DDG 82) DURING FY23 DEPOT

MODERNIZATION PERIOD (DMP) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Depot Modernization Period (DMP) onboard USS Lassen (DDG 82) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, C, D, E, and F.

FOB: Destination

OPTION Growth Reservation for CLIN 0003

FFP

Growth Reservation Associated with CLIN 0003. See attachment J-4

See Notes A, B, C, D, E and F.

OPTION Growth Reservation for CLIN 0004

Growth Reservation Associated with CLIN 0004. See attachment J-4

OPTION Growth Reservation for CLIN 0005

Growth Reservation Associated with CLIN 0005. See attachment J-4

OPTION Growth Reservation for CLIN 0007

Growth Reservation Associated with CLIN 0007. See attachment J-4

OPTION Growth Reservation for CLIN 0008

Growth Reservation Associated with CLIN 0008. See attachment J-4

OPTION Growth Reservation for CLIN 0009

Growth Reservation Associated with CLIN 0009. See attachment J-4

OPTION Growth Reservation for CLIN 0010

Growth Reservation Associated with CLIN 0010. See attachment J-4

OPTION Growth Reservation for CLIN 0011

Growth Reservation Associated with CLIN 0011. See attachment J-4

OPTION Growth Reservation for CLIN 0012

Growth Reservation Associated with CLIN 0012. See attachment J-4

OPTION Growth Reservation for CLIN 0013

Growth Reservation Associated with CLIN 0013. See attachment J-4

OPTION Growth Reservation for CLIN 0014

Growth Reservation Associated with CLIN 0014. See attachment J-4

OPTION Growth Reservation for CLIN 0015

Growth Reservation Associated with CLIN 0015. See attachment J-4

OPTION Growth Reservation for CLIN 0016

Growth Reservation Associated with CLIN 0016. See attachment J-4

OPTION Growth Reservation for CLIN 0017

Growth Reservation Associated with CLIN 0017. See attachment J-4

OPTION Growth Reservation for CLIN 0018

Growth Reservation Associated with CLIN 0018. See attachment J-4

OPTION Growth Reservation for CLIN 0019

Growth Reservation Associated with CLIN 0019. See attachment J-4

OPTION Growth Reservation for CLIN 0020

Growth Reservation Associated with CLIN 0020. See attachment J-4

OPTION Growth Reservation for CLIN 0021

Growth Reservation Associated with CLIN 0021. See attachment J-4

OPTION Growth Reservation for CLIN 0022

Growth Reservation Associated with CLIN 0022. See attachment J-4

OPTION Growth Reservation for CLIN 0023

Growth Reservation Associated with CLIN 0023. See attachment J-4

OPTION Growth Reservation for CLIN 0024

Growth Reservation Associated with CLIN 0024. See attachment J-4

OPTION Growth Reservation for CLIN 0025

Growth Reservation Associated with CLIN 0025. See attachment J-4

OPTION Growth Reservation for CLIN 0026

Growth Reservation Associated with CLIN 0026. See attachment J-4

OPTION Growth Reservation for CLIN 0027

Growth Reservation Associated with CLIN 0027. See attachment J-4

OPTION Growth Reservation for CLIN 0028

Growth Reservation Associated with CLIN 0028. See attachment J-4

OPTION Growth Reservation for CLIN 0029

Growth Reservation Associated with CLIN 0029. See attachment J-4

OPTION Growth Reservation for CLIN 0030

Growth Reservation Associated with CLIN 0030. See attachment J-4

OPTION Growth Reservation for CLIN 0031

Growth Reservation Associated with CLIN 0031. See attachment J-4

OPTION Growth Reservation for CLIN 0032

Growth Reservation Associated with CLIN 0032. See attachment J-4

OPTION Growth Reservation for CLIN 0033

Growth Reservation Associated with CLIN 0033. See attachment J-4

OPTION Growth Reservation for CLIN 0034

Growth Reservation Associated with CLIN 0034. See attachment J-4

OPTION Growth Reservation for CLIN 0035

Growth Reservation Associated with CLIN 0035. See attachment J-4

OPTION Growth Reservation for CLIN 0036

Growth Reservation Associated with CLIN 0036. See attachment J-4

OPTION Growth Reservation for CLIN 0037

Growth Reservation Associated with CLIN 0037. See attachment J-4

OPTION Growth Reservation for CLIN 0038

Growth Reservation Associated with CLIN 0038. See attachment J-4

OPTION Growth Reservation for CLIN 0039

Growth Reservation Associated with CLIN 0039. See attachment J-4

OPTION Growth Reservation for CLIN 0040

Growth Reservation Associated with CLIN 0040. See attachment J-4

OPTION Growth Reservation for CLIN 0041

Growth Reservation Associated with CLIN 0041. See attachment J-4

OPTION Growth Reservation for CLIN 0042

Growth Reservation Associated with CLIN 0042. See attachment J-4

OPTION Growth Reservation for CLIN 0043

Growth Reservation Associated with CLIN 0043. See attachment J-4

NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR

1. The Contractor agrees to provide the level of effort to completion (LOE to Completion) in the performance of growth CLINs in the execution of the USS LASSEN DMP:

a. 119,326 direct labor hours (labor hours) and $3,832,325 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS LASSEN DMP work package under

CLINS 0044 – 0089.

2. The total LOE to Completion for the performance of the above growth CLINs shall be comprised of labor hours and the associated material required to support the expected, within scope growth. The mix of labor hours and material may be adjusted. Adjustments to the labor hour and material mix will be documented via weekly Technical Direction Letter (TDL) and subsequently unilaterally adjusted via contract modification. The Government reserves the right to reconcile the weekly TDLs via unilateral modification at the Administrative Contracting Officer’s (ACO) discretion.

3. LOE to completion obligations specified above shall only include effort performed in direct support of this contract and shall not include time and effort expended on such things as (local travel to and from an employee's usual work location), uncompensated effort while on travel status, truncated lunch periods, work (actual or inferred) at an employee's residence or other non-work locations.

4. LOE to Completion labor hours and material are within the scope and pricing of this contract and are not subject to an equitable adjustment under FAR 52.243-1 ‘Changes – Fixed Price’. The utilization of LOE to Completion is at the discretion of the Contracting Officer and subject to the schedule phasing identified in Note F.

5. If, in the opinion of the Contractor, any effort directed in the Growth Management Request Form (GMR) calls for effort outside the scope of the contract, the Contractor shall notify the Administrative Contracting Officer (ACO) in writing within two (2) working days after the receipt of any such direction. In the event of a cost dispute, the ACO may unilaterally authorize hours and material against LOE work. The Contractor shall not proceed with the work directed by the GMR unless and until the Contractor is notified by the ACO to proceed with the directed work. The Contractor is required to proceed with the directed work as directed by the ACO.

Thereafter, any remaining disagreement shall be addressed in accordance with FAR 52.233-1(Alt. 1) ‘Disputes.’

Additionally, if the cost of performing the disputed direction exceeds $100,000, the Contractor is required to comply with FAR 52.243-6 ‘Change Order Accounting.’

6. The labor hours and material requirements listed in Section B, Note A, paragraph 1 above are part of this contract. Prime contractor efforts shall be deducted from the labor hours allocated. Subcontractor efforts and materials shall be deducted from the materials allocated. The balance of labor hours and materials remaining in the LOE to Completion CLINs will be recouped by the Government via final contract modification at the end of the availability.

7. Only authorized direct production labor hours shall be deducted from the LOE to Completion direct labor hour ceiling set forth in Section B, Note A, paragraph 1 above. Per Note B paragraph 2 below, all non-production labor shall be included in the Contractor’s fully burdened labor rate. Non-production hours shall not be included in pricing submitted in support of growth issued under the LOE to Completion CLINs. Additionally, Contractor LOE to Completion pricing shall not include any allowance for technical representatives or for any other Government directed source unless specifically directed by the Contracting Officer.

8. Only authorized material dollars shall be deducted from LOE to Completion material reservation set forth in

Section B, Note A, paragraph 1 above. This material reservation consists of the total cost of materials and subcontractor efforts proposed. All subcontractor quotes shall be included in the Change Order Price Analysis (COPA) as per Section C, paragraph 1.13. Material dollars may include freight or duties if specifically itemized on the invoice for the material. The Contractor shall not be allowed to add material handling charges, overhead (including G&A), or profit into the settled cost of materials deducted from the material reservation.

9. The information received in the consolidated final report required by Section C paragraph 6.6 will be used by the ACO in the issuance of one contract modification based on the information received in the final report identified in Section C below, which will be a final settlement for all LOE to Completion labor hours and material dollars. Once the number of labor hours and materials for directed work has been settled, neither party shall be entitled to an adjustment because the expended labor hours and materials differ from the settled price.

This shall not preclude an adjustment otherwise permitted by law and regulation; e.g. fraud, product substitution, defective workmanship or materials. Each directed work shall receive approval by the SUPERVISOR and the ACO. (“SUPERVISOR” as defined in NAVSEA Standard Item (NSI) 009-01, paragraph 4.3, refers to the local Government activity responsible for the execution and contract administration of Navy maintenance and modernization work.)

NOTE B: FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR GROWTH AND

NEW WORK

SCHEDULE OF PRICES / RATES: SHIP REPAIR LABOR RATE (FULLY BURDENED)

1. The Contractor’s fully burdened ship repair growth labor rate and fully burdened ship repair new work labor rate will be used for negotiating growth and new work, respectively, to be performed under this contract. The contractor agrees that the number of hours included in its price proposal submitted in response to Requests for Contract Changes (RCCs), Growth Management Requests (GMRs) and Reservation Task Requests (RTRs) for either Growth or New Work shall include only direct production hours. For these purposes, direct production hours are for skilled labor at the journeyman level expended in direct production including but not limited to the following functions:

Abrasive cleaning/blasting Fire Watch Welding Burning Brazing Carpentry Machinists (inside and outside) Electrical Work Electronic Work Engineering Design Support Lagging Ship-fitting Boiler-making Painting Sheet-metal Work Pipefitting Rigging General Labor Staging/Scaffolding Diesel Mechanics

2. The fully burdened ship repair labor rate proposed by the contractor listed in paragraph 7 below shall include all costs associated with support functions (whether charged directly or indirectly by the offeror’s accounting systems) provided in support of the direct production functions listed in paragraph 1 above. Support functions shall be considered to be included in the offeror’s fully burdened ship repair labor rate for direct production hours. Labor hours for the below support functions shall not be separately proposed for either growth or new work, including in support of subcontractors. Support functions include, and are not limited to, those types listed below:

Testing Quality Assurance Execution Planning Cleaning (except tank cleaning) Supervision (all types, including, but not limited to supervision of trades, support personnel and subcontractors) Security Surveying Administration Transportation Purchasing Staff Lofting Other indirect support

Handling & Warehousing Safety/Environmental Program Management

3. The fully burdened ship repair labor rate is a fixed hourly rate that includes all wages, (i.e. straight time, overtime, shift differential, holiday time, etc.), overhead, all other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit. The fully burdened ship repair labor rate represents a blended rate including labor transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

4. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc., that are consumed/used in the process of repair and do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor’s fully burdened ship repair labor rate and not separately priced.

5. Physical materials are goods that become incorporated into the repaired vessel in the course of the repair, such as replacement steel, pipes, paint, and fasteners. The material burden rate applies to physical materials but not to consumable materials. The material burden rate will be applied to the actual cost of the physical material. Actual cost does not include handling charges, general and administrative cost, overhead, profit, or any other indirect cost.

6. For growth and new work contract changes involving subcontractors, subcontractor quotes will be treated as

Other Direct Costs (ODCs) and will be subject to the contract material burden rate shown in paragraph (7) below. Subcontractor quotes must be competitively acquired and submitted with the contractor’s COPA in response to RCCs, GMRs and RTRs issued by the Contracting Officer. At no time will the proposed total to be performed by the prime contractor combined with subcontractor quote, material quote, and applicable burdens be allowed to cost more than it would have, had the prime contractor directly provided all material and labor. The proposed total pricing restriction addressed in the preceding sentence does not apply in any case where the work is required to be performed by Original Equipment Manufacturers (OEMs), Government directed subcontractors, and/or Government authorized vendors. RCCs and RTRs that are subcontracted for material only (no associated labor required within the RCC) shall not be subject to the Material Burden Rate. Any material burden rate applied to new work shall be approved by the ACO, upon receipt of supporting documentation in accordance with FAR 15.404-3, Subcontract Pricing Considerations.

7. The contract fixed fully burdened ship repair labor rate and material burden rate are shown below. These fixed rates shall be used for negotiating growth and new work during the availability and up to three (3) months after the Attachment J-3 ‘Contract Complete’ date:

USS LASSEN FY23 DMP

Fully Burdened Ship Repair Labor Rate TBD Material Burden Rate TBD

8. In the event of a one-bid or directed availability, the Contracting Officer may negotiate the Fully Burdened

Ship Repair Labor Rate and Material Burden Rate (not to exceed the ceiling rate(s) identified above) with the offeror in accordance with FAR 15.4, Contract Pricing. The rates herein are not considered a Forward Pricing Rate Agreement (FPRA) and are identified solely for the purpose of establishing a ceiling.

9. In the event of an extension due to excusable delay to the delivery date for the USS LASSEN FY23 DMP, the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.59 % commencing 3 months after the

Attachment J-3 “Contract Complete” date. Following the “Contract Complete” date identified in Attachment J- 3 (Milestones), this rate shall be escalated quarterly through the 24th month, if necessary, and shall be used to negotiate all growth and new work. Note, in the event of an excusable delay, this escalation rate shall be applied only to growth and new work not previously identified in Attachment J-4 (Pricing Worksheet). The material burden rate shall not increase.

NOTE C: Option item to which the option clause FAR 52.217-7 (NAVSEA Variation II) applies and which is to be supplied only if and to the extent said option is exercised.

NOTE D: SCHEDULE OF DAILY RATES FOR PIERSIDE AND DRY-DOCKING (FULLY BURDENED)

FOR PURPOSES OF A COMPENSABLE EXTENSION TO THE DRY-DOCKING OR DELIVERY DATE

1. In the event of a compensable extension to the dry-docking or delivery date, the Contractor’s fully burdened daily rates for additional dry-dock and/or pierside performance period at the Contractor’s facility will be evaluated by the ACO upon receipt of the Contractor’s certified or other than certified cost or pricing data (certification requirements are subject to FAR 15.403).

2. The Contractor agrees that the daily rates shall include all costs that run with time associated with additional performance days in accordance with the work package specification requirements of this availability. The daily rates shall include all costs associated with additional performance days (whether charged directly or indirectly by the offeror’s accounting systems) including but not limited to:

Temporary Services, including but not limited to:

o Decking services o Pumping services o Electricity

Internet Connectivity Air Conditioning Support Services for the Navy, its agents and Contractors Facilities, including but not limited to:

o Piers o Dry-docks o Office spaces o…