USS LASSEN_QA4.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- N00024-22-R-4486
About this file
This solicitation seeks proposals for the USS LASSEN (DDG 82) FY23 Depot Modernization Period. The Naval Sea Systems Command is soliciting proposals under solicitation number N00024-22-R-4486 to complete maintenance, modernization, and repair availability for the USS LASSEN beginning in December 2022 and concluding in August 2024. The availability requires extensive facilities and personnel capable of coordinating multiple areas of ship maintenance and modernization. A single award is expected to be made to one contractor by September 2022. Interested parties must register in SAM and PIEE to receive the full solicitation and submit proposals through PIEE. Requests for restricted attachments should be directed to the Contract Specialist and Contracting Officer.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPI FORM
| USS LASSEN (DDG 82) DMP N00024-22-R-4486 | RFP | ||||||
| Attachment S-3 Pre-Proposal Information (PPI) Form | Attachment J-1 | ||||||
| NAVSEA POC: | Liz Feliciano, elizabeth.feliciano-hernandez.civ@us.navy.mil, (202) 781-1049 | Attachment J-2 | |||||
| Daniel Breedlove, daniel.j.breedlove.civ@us.navy.mil, (202) 781-0615 | Attachment J-3 | ||||||
| Attachment J-4 | |||||||
| Question # | Date of Request: | Question Area | Work Iem (if applicable) | Section/Para | Contractor Question | Government Response | Attachment J-5 |
| 152 | 4/19/22 | RFP | N/A | Section L, II.A.1 | The government has extended the proposal due date by 2 weeks to 9 May 22, which is helpful in developing a more complete and accurate proposal. However, as previously submitted, the LASSEN DMP solicitation is a sizable and complex work package that requires considerable estimating, subcontracting, and resources planning. This same level of complexity has been noted by the subcontractors, many of which have requested significant extensions to develop their proposals. Shortened timelines result in less accuracy and greater risk Considering the volume and complexity of the work scope, the delays encountered with obtaining references, and the benefit of allowing key subcontractors to participate in this work, the contractor requests the proposal due date be extended to June 3, 2022, or further if the government anticipates any significant amendments to the solicitation. | Proposal due date remains unchanged. |