N00024-22-R-4486 A002.pdf

PDF 693 KB Posted

Attached to
Amendment 0008 - USS LASSEN (DDG 82) FY23 Depot Modernization Period (DMP)
Solicitation number
N00024-22-R-4486
Issued by

About this file

This is a solicitation for the USS LASSEN (DDG 82) FY23 Depot Modernization Period (DMP) issued by the Naval Sea Systems Command. The solicitation seeks a contractor to complete a combination of maintenance, modernization, and repair for the USS LASSEN from December 2022 through August 2024. Interested parties must register in SAM and PIEE in order to receive the full solicitation and submit a proposal. Proposals are due in September 2022 and a single award is expected to be made. The requirement is not set aside for small businesses as market research found no two or more capable small businesses. The solicitation includes restricted attachments containing key milestones, pricing workbooks, and compartment closeout lists. Interested parties must request access to these attachments from the Contract Specialist.

View the file

Other files

File Type Posted
N00024-22-R-4486 A008.pdf PDF
N00024-22-R-4486 A008 conformed.pdf PDF
USS LASSEN_QA6.xlsx XLSX spreadsheet
N00024-22-R-4486 A007 conformed.pdf PDF
N00024-22-R-4486 A007.pdf PDF
USS LASSEN_QA5.xlsx XLSX spreadsheet
N00024-22-R-4486 A006 conformed.pdf PDF
N00024-22-R-4486 A006.pdf PDF
N00024-22-R-4486 A0005 conformed.pdf PDF
USS LASSEN_QA4.xlsx XLSX spreadsheet
N00024-22-R-4486 A0005.pdf PDF
N00024-22-R-4486 A004 conformed.pdf PDF
N00024-22-R-4486 A004.pdf PDF
N00024-22-R-4486 A003.pdf PDF
USS LASSEN_QA3.xlsx XLSX spreadsheet
N00024-22-R-4486 A003 conformed.pdf PDF
N00024-22-R-4486 A002 conformed.pdf PDF
USS LASSEN_QA2.xlsx XLSX spreadsheet
N00024-22-R-4486 A001.pdf PDF
USS LASSEN_QA1.xlsx XLSX spreadsheet
N00024-22-R-4486 A001 CONFORMED.pdf PDF
(USS LASSEN) Attachment S-5 Eligibility Criteria Data Sheet.docx DOCX document
(USS LASSEN) Attachment S-8 Pier and Drydock Graphical Representation.xlsx XLSX spreadsheet
(USS LASSEN) Attachment J-7 IPTD Events SMR.docx DOCX document
(USS LASSEN) Attachment S-3 Pre-Proposal Information (PPI) Form.xlsx XLSX spreadsheet
(USS LASSEN) Attachment J-8 Government Furnished Material (GFM) List.xlsx XLSX spreadsheet
(USS LASSEN) CDRL Exhibit A.pdf PDF
(USS LASSEN) CDRL Exhibit B.pdf PDF
(USS LASSEN) Attachment J-10 20 Percent Open Inspect Milestone Reports Due.xlsx XLSX spreadsheet
(USS LASSEN) Attachment S-9 Past Performance Questionnaire.docx DOCX document
(USS LASSEN) Attachment S-4 Manpower Performance Data Sheet.xlsx XLSX spreadsheet
N00024-22-R-4486_USS LASSEN FY23 DMP.pdf PDF
(USS LASSEN) Attachment J-5 Quality Assurance Surveillance Plan.docx DOCX document
(USS LASSEN) Attachment S-7 Proposal Assessment.xlsx XLSX spreadsheet
(USS LASSEN) CDRL Exhibit C.pdf PDF
(USS LASSEN) Attachment S-2 Past Performance CPARS References.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N0002421FR62098C

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to:

1.Revise Sections B, C, F, I, and J

2. Deleted paragraphs 9.1.7 through 9.1.12 in Section C

3. Revise Attachments J-3 and J-4

4. Incorporate Erratas 2 and 3

5. Provide Bidders' questions answ ers

1. CONTRACT ID CODE PAGE OF PAGES

J 1 27

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Mar-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N0002422R4486

X 9B. DATED (SEE ITEM 11)

24-Feb-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Mar-2022

CODE

NAVAL SEA SYSTEMS COMMAND

1333 ISAAC HULL AVENUE

WASHINGTON NAVY YARD DC 20376

N00024 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0002422R4486

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0003

The CLIN description has changed from TYCOM BASE to TYCOM.

CLIN 0004

The CLIN description has changed from PMS 407 OPN BASE to PMS 407 OPN.

CLIN 0005

The CLIN description has changed from PMS 407 OMN BASE to PMS 407 OMN.

The following have been modified:

NOTE B: FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR GROWTH AND

NEW WORK

SCHEDULE OF PRICES / RATES: SHIP REPAIR LABOR RATE (FULLY BURDENED)

1. The Contractor’s fully burdened ship repair growth labor rate and fully burdened ship repair new work labor rate will be used for negotiating growth and new work, respectively, to be performed under this contract. The contractor agrees that the number of hours included in its price proposal submitted in response to Requests for Contract Changes (RCCs), Growth Management Requests (GMRs) and Reservation Task Requests (RTRs) for either Growth or New Work shall include only direct production hours. For these purposes, direct production hours are for skilled labor at the journeyman level expended in direct production including but not limited to the following functions:

Abrasive cleaning/blasting Fire Watch Welding Burning Brazing Carpentry Machinists (inside and outside) Electrical Work Electronic Work Engineering Design Support Lagging Ship-fitting Boiler-making Painting Sheet-metal Work

Pipefitting Rigging General Labor Staging/Scaffolding Diesel Mechanics

2. The fully burdened ship repair labor rate proposed by the contractor listed in paragraph 7 below shall include all costs associated with support functions (whether charged directly or indirectly by the offeror’s accounting systems) provided in support of the direct production functions listed in paragraph 1 above. Support functions shall be considered to be included in the offeror’s fully burdened ship repair labor rate for direct production hours. Labor hours for the below support functions shall not be separately proposed for either growth or new work, including in support of subcontractors. Support functions include, and are not limited to, those types listed below:

Testing Quality Assurance Execution Planning Cleaning (except tank cleaning) Supervision (all types, including, but not limited to supervision of trades, support personnel and subcontractors) Security Surveying Administration Transportation Purchasing Staff Lofting Other indirect support Handling & Warehousing Safety/Environmental Program Management

3. The fully burdened ship repair labor rate is a fixed hourly rate that includes all wages, (i.e. straight time, overtime, shift differential, holiday time, etc.), overhead, all other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit. The fully burdened ship repair labor rate represents a blended rate including labor transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

4. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc., that are consumed/used in the process of repair and do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor’s fully burdened ship repair labor rate and not separately priced.

5. Physical materials are goods that become incorporated into the repaired vessel in the course of the repair, such as replacement steel, pipes, paint, and fasteners. The material burden rate applies to physical materials but not to consumable materials. The material burden rate will be applied to the actual cost of the physical material. Actual cost does not include handling charges, general and administrative cost, overhead, profit, or any other indirect cost.

6. For growth and new work contract changes involving subcontractors, subcontractor quotes will be treated as

Other Direct Costs (ODCs) and will be subject to the applicable contract material burden rate shown in paragraph (7) below. Subcontractor must be submitted with the contractor’s COPA in response to RCCs, GMRs and RTRs issued by the Contracting Officer. For new work only, these subcontractor quotes must be competitively acquired. At no time will the proposed total to be performed by the prime contractor combined with subcontractor quote, material quote, and applicable burdens be allowed to cost more than it would have, had the prime contractor directly provided all material and labor. The proposed total pricing restriction addressed in the preceding sentence does not apply in any case where the work is required to be performed by Original Equipment Manufacturers (OEMs), Government directed subcontractors, and/or Government authorized vendors. RCCs and RTRs that are subcontracted for material only (no associated labor required within the RCC) shall not be subject to the Material Burden Rate. Any material burden rate applied to new work shall be approved at the discretion of the ACO, upon receipt of supporting documentation in accordance with FAR 15.404-3 ‘Subcontract Pricing Considerations.

7. The contract fixed fully burdened ship repair labor rate and material burden rate are shown below. These fixed rates shall be used for negotiating growth and new work during the availability and up to three (3) months after the Attachment J-3 ‘Contract Complete’ date:

USS LASSEN FY23 DMP

Fully Burdened Ship Repair Growth Labor Rate TBD Fully Burdened Ship Repair New Work Labor Rate TBD Material Burden Growth Rate TBD Material Burden New Work Rate TBD

8. In the event of a one-bid or directed availability, the Contracting Officer may negotiate the Fully Burdened

Ship Repair Labor Rate and Material Burden Rate (not to exceed the ceiling rate(s) identified above) with the offeror in accordance with FAR 15.4, Contract Pricing. The rates herein are not considered a Forward Pricing Rate Agreement (FPRA) and are identified solely for the purpose of establishing a ceiling.

9. In the event of an extension due to excusable delay to the delivery date for the USS LASSEN FY23 DMP, the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.59 % commencing 3 months after the Attachment J-3 “Contract Complete” date. Following the “Contract Complete” date identified in Attachment J- 3 (Milestones), this rate shall be escalated quarterly through the 24th month, if necessary, and shall be used to negotiate all growth and new work. Note, in the event of an excusable delay, this escalation rate shall be applied only to growth and new work not previously identified in Attachment J-4 (Pricing Worksheet). The material burden rate shall not increase.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been added by full text:

C-217-H005

C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)

(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within five (5) working days of discovery:

(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,

(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.

(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and Above Work and it provides the process for adjudication.

(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.

(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.

(End of Text)

SCOPE OF WORK

1. GENERAL REQUIREMENTS

1.1 The Contractor, under the direction of the Regional Maintenance Center (RMC) as an independent

Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities (except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repairs and alterations required to complete the USS LASSEN (DDG 82) FY23 DMP in accordance with the requirements stated in this Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract.

1.2 The Contractor shall lead or participate in periodic meetings, as required, to facilitate status reporting related to USS LASSEN FY23 DMP. Forums will be conducted at a time mutually agreed to by primary participants. These meetings include, but are not limited to, the following from Availability Start through Contract Complete:

1.2.1 Project Management Reviews such as the 25%, 50%, 75%, and other meetings required to manage the overall availability to completion.

1.2.2 Daily Production meetings.

1.2.3 Weekly Progress meetings.

1.2.4 Weekly Commanding Officer briefs.

1.2.5 IPTD Completion Event (formerly known as “IPTD C+21 Post-Completion Meeting”).

1.2.6 Provide all reports, required in accordance with NSI 009-01.

1.3 Category I NSIs identified under Attachment J-1 are applicable to all items without further reference.

Category II NSIs are applicable when invoked and/or referenced in individual work items specified in Attachment J-1. NSIs may be found at:

http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx. The contractor is obligated to submit all required reporting in accordance with applicable NSIs (See Contract Data Requirements List, DD 1423, Exhibit A003).

1.4 In addition to the Work Item Specifications and Work Item Plans, Drawings, and Other References and applicable NSIs, additional work item references not already in the possession of the Offerors, commercially available, listed under 52.211-2, are available through the following websites:

a) https://jedmics.net/

b) https://mfom.sscno.nmci.navy.mil/MFOM/DoDStatement.aspx

c) https://nsedr.nnsy.navy.mil//

1.5 The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair and alterations required to complete the USS LASSEN (DDG

82) FY23 DMP within the availability dates herein.

1.6 INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS:

1.6.1 The Contractor shall formally present its IPS for the USS LASSEN FY23 DMP to the NSA at the

SMR, Start of the Availability, 25% complete conference, 50% complete conference, 75% complete conference, production completion meetings, and for pre Sea Trials requirements. At each meeting, the contractor shall present and explain, at minimum, the following information:

1.6.1.1 The Contractor's latest, Government approved, IPS created in full compliance with FY23 NSI

009-60

1.6.1.2 The Contractor's current progress in preparing for and/or executing the Availability in accordance with their IPS. The Contractor shall provide an explanation and mitigation plan in the event of any preparation or execution delays in comparison to their IPS.

1.6.1.2.1 The Contractor's plan shall describe opportunities for schedule acceleration, associated costs, and potential risks and mitigations to remaining schedule attainment.

1.7 LOGISTICS: The contractor shall develop and submit all logistics and technical data required, including but not limited to provisioning parts lists, engineering data for provisioning, design change notices, interim support items lists, provisioning technical documentation, demand only transaction reports, commercial off the shelf (COTS) equipment manual revisions, technical manual revisions, and purchase orders. (See CDRLs A005, B001 – B009 and C001 – C002).

1.8 SMALL BUSINESS SUBCONTRACTING REPORT: The Contractor shall execute a Small Business

Subcontracting Report in accordance with FAR Part 19 and the subcontracting goals identified in the RFP (See CDRL A001).

1.9 SITE INSPECTION: The Government may send a site inspection team to perform an inspection of the contractor's facility prior to arrival of the vessel.

1.10 GOVERNMENT FURNISHED MATERIAL from Availability Start through Contract Complete: The contractor is to coordinate the delivery and/or pick-up of all Government Furnished Material (GFM) as cited in work specification(s), supporting drawings, references and/or Statement of Work (SOW) with the Project Manager (See CDRL A011).

1.10.1 Turnover of GFM:

1.10.1.1 NAVSEA GFM for Modernization Work Items: All NAVSEA GFM for Modernization

Work Items will be available at A-30 unless otherwise noted in Attachment J-8. The Contractor is required to coordinate turnover of NAVSEA GFM with the Project Manager following contract award.

1.10.1.2 TYCOM GFM for Repair Work Items: All TYCOM GFM will be available at A-30, unless otherwise noted in Attachment J-8. The Contractor is required to coordinate turnover of TYCOM GFM with the Project Manager following award.

1.10.2 In the event of a claim and/or request for equitable adjustment arising out of a late or adjusted turnover of GFM, the Contractor bears the burden of proving both delay and resulting impact to critical and/or controlling path work items.

1.10.3 GFM transportation costs shall be included in the contract. Change order will only be issued if there is a Government caused change to pick-up date(s). Government property permanently removed from a vessel that requires a Property Administrator's disposition instructions shall be properly prepared for shipment and be delivered as directed by the Property Administrator. GFM is listed in paragraph 5 of the Work Item(s) and in Attachment J-8.

1.10.4 The Contractor is required to manage all GFM and CFM which includes purchasing, monitoring, receiving, inspecting, segregating, issuing, determining nonconformance, and disposing of material.

This also includes providing an inventory system for both Government Furnished Material and Contractor Furnished Material, including ordering, tagging and warehousing of material. All materials selected for installation must meet the specified standard military performance specifications, Federal performance standards, and may require to be listed on a Qualified Products List (QPL) for shipboard installations.

1.11 QUALITY ASSURANCE

1.11.1 QUALITY ASSURANCE PROGRAM: The Contractor shall provide and maintain a quality assurance program acceptable to the Government, and shall perform or have performed the inspections and tests pursuant to that program to substantiate that the material and workmanship provided pursuant to the job order conform to the drawings, specifications, job orders, and contract requirements listed herein.

The Contractor's quality assurance program shall be in accordance with that set forth in NSI 009-04.

In addition to its rights under DFARS 252.217-7005 “Inspection and Manner of Doing Work”, the Government shall have the right to deem work or material furnished by the Contractor to be incomplete and not in accordance with the requirements of the job order by reason of the Contractor's failure to comply with the requirements of its quality assurance program and, as such, the Contractor shall not be entitled to progress payments for said work and material (See CDRL A006).

1.11.2 Quality Assurance – Specific Reporting Requirements: The Contractor shall submit all required reporting in accordance with Category I and invoked category II NSIs, including, but not limited to:

1.11.2.1 The Contractor shall submit all required reports associated with NSI 009-07, regarding opening and certification of tanks and spaces, in accordance with

CDRL A007.

1.11.2.2 The Contractor shall meet all Process Control Procedure (PCP) reporting requirements in accordance with NSI 009-09 and CDRL A008.

1.11.2.3 The contractor shall meet all technical reporting requirements including those set forth in NSI 009-12 (See CDRL A009).

1.11.2.4 The Contractor shall meet all requirements relating to weight and stability reports for in-service surface ships in accordance with NSI 009-103 and CDRL A014.

1.11.3 Quality Assurance Surveillance Plan (QASP): The Contractor shall meet the Performance/Acceptable Quality Level Requirements for each Deliverable/Assessment Area in the QASP, Attachment J-5.

There will be monetary deductions based on unfavorable Contractor performance as stated in the

QASP.

1.12 IDENTIFICATION OF CONDITION FOUND: In accordance with the requirements of NSI 009-01, the

Contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions to impact the critical path(s) /controlling item(s), the Contractor shall notify the Government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a Condition Found Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below. Recommended repairs and corrective actions shall be submitted to the Government in the form of a CFR (intended to represent the "Work Request" described in DFARS 252.217-7028 “Over and Above Work”) per CDRL A002.

1.12.1 CONDITION FOUND NOTIFICATION TO GOVERNMENT: CFRs shall be submitted through the Navy Maintenance Database Re-platform (NMDR) within five (5) working days of discovery of the condition. At a minimum, the CFR will include the following:

(1) Identify contract, ship, and hull number

(2) Serialized by CFR number

(3) Identification of the applicable Work Item number

(4) Date requirement was discovered

(5) Description of the work requirement

(6) Specific location of the work

(7) Recommendation for corrective action

(8) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.

(9) Identification of related changes, if any, to the internal milestones and production and contract completion dates.

1.12.2 GOVERNMENT REVIEW AND RESPONSE TO CFR: The Maintenance Team will review the

CFR. If the CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five (5) working day requirement). As appropriate, the Government and contractor will need to meet, conduct ship checks and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. Accuracy of CFR submissions may be evaluated in CPARS and utilized for past performance ratings on future requirements. Additionally, deductions may be assessed in accordance with Attachment J-5,

1.13 DATA REQUIRED FOR RCC AND LOE TO COMPLETION REQUESTS: In the event a growth requirement is validated and fully scoped, the Government may generate a RCC or GMR (in support of an LOE to Completion Request) which the ACO may request a firm fixed price proposal from the Contractor.

For all generated RCCs and GMRs, the Contractor shall provide a COPA proposal to the ACO within three

(3) business days (See CDRL A002). A Contractor’s COPA shall remain valid for a minimum of 14 calendar days, unless otherwise specified by the ACO; if another timeline is specified by the Government, the Contractor’s COPA shall remain valid for that amount of time. The COPA provided shall include at a minimum:

a. Labor hours to be performed by the Prime Contractor __________

b. Subcontractor Quote (If applicable) $__________

c. Material Quote (If applicable) $__________

d. Mark-up (If applicable) $__________

Note 1 – Labor Hours: Proposed labor hours to be performed by the Prime Contractor shall be provided broken down by paragraph, trade and labor hour mix.

Note 2 – Material: Material pricing shall include a list detailing the source, part number, description, unit cost, quantities, total cost and underlying vendor quotes for each line item.

Note 3 – Subcontractor Quotes: Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable). Proposed subcontractor labor hours shall be broken down by paragraph and task.

Note 4 – Supporting Documentation: The requirements for complete submission of a COPA stated above represents the minimum and does not limit the Government from requesting additional information. In the event the ACO is unable to make a fair and reasonable determination based on the original COPA submission, the Contractor shall comply with FAR 15.402(a)(2) which requires the Contractor provide whatever data the ACO needs in order to determine a fair and reasonable price.

Note 5 – Late Submissions: The above documentation must accompany the COPA for the COPA to be considered submitted to the ACO. The number of days a Contractor’s COPA remains valid does not begin until the COPA is considered submitted by the ACO. See Attachment J-5, QASP, for deductions associated with late or invalid COPA submittals.

If circumstances arise where the Contractor is unable to submit a COPA within three (3) business days, the Contractor shall notify the ACO in writing of the specific circumstances and provide a revised date in which a COPA proposal will be submitted. Additional time needed to complete a COPA may be granted solely at the discretion of the ACO. The new timeframe granted solely at the discretion of the ACO and which may differ from the Contractor’s request, shall be met by the Contractor. Notification of a late COPA does not exempt the Contractor from meeting its requirement, but will be considered by the Government when conducting a CPARS evaluation and utilized for past performance ratings on future contracts. Late submission of COPAs may result in deductions assessed in accordance with Attachment J-5,

1.14 DESCOPING OF REQUIREMENTS: The Government reserves the right to descope any requirement under this contract at any time and for any reason. Descopes are incorporated into the contract via deletion RCCs and can either be a partial deletion of paragraph(s) from the work specification or deletion of a work item in its entirety. The Government will rely on the labor rates and prices entered in Attachment J-4 Pricing Workbook for negotiating and settling RCCs.

1.14.1 Pricing of Deletion RCCs: The Contractor agrees to price deletion RCCs at the same labor rate proposed in Attachment J-4 Pricing Workbook, as follows:

1.14.1.1 Partial or full work item deletion RCCs from the basic work package will be deleted at the basic labor rate and material burden rates as entered in the Work Item Index Tab of Attachment J-4;

1.14.1.2 Partial or full work item deletion RCCs from settled growth work or new work will be deleted at the labor rate and material burden rate as entered in the Labor & Material Burden Rate Tab of Attachment J-4.

1.14.2 Settled Deleted Price:

1.14.2.1 Full Work Item Deletion: For the purposes of pricing a RCC that deletes a work item in its entirety, the Government considers each individual work item to be separately priced. The starting point for negotiations will be the Contractor’s work item price entered in the Work Item Index Tab of Attachment J-4. The burden is on the Contractor to demonstrate production costs incurred. Program management and other indirect costs will not be considered.

1.14.2.2 Partial Deletion: The Contractor agrees to propose RCCs that delete a portion of a work item at the hours, material and subcontractor cost it would have required to accomplish the work. The proposed price shall include only the paragraphs affected by the partial deletion. At no time may the Contractor amend its pricing on the remaining paragraphs not being deleted from the work item.

1.15 MODIFICATION NEGOTIATION: Once the Government receives the Contractor’s COPA, it will evaluate and negotiate it in accordance with applicable Agency regulations and policies. If necessary, the Government may issue unilateral modifications to accomplish required work using the pre-priced labor and material rates, outlined in Section B of this contract.

1.16 NAVY MAINTENANCE DATABASE (NMD): The Contractor shall use NMD for the submission of Condition Found Reports throughout the administration of this contract. In addition to the submission of reports, the contractor shall also utilize NMD to enter in data fields for check points (scheduling, inspection data, and inspection results), entering test and inspection plan (TIP) data, entering and adjudicating Corrective Action Requests (CAR) information, and CFR and Required Report submittal and management inside the program. NMD is located at https://mfom.sscno.nmci.navy.mil/MFOM/DodStatement.aspx.

When required, the Contractor shall have access to and use Naval Ships Engineering Drawing Repository (NSEDR), Electronic Departures from Specifications (EDFS), and other logistic support required throughout the administration of this contract per the CDRLs and standard items invoked at the time of contract award.

1.17 ORGANIZATION CHART AND EMPLOYEE ROSTER:

1.17.1 ORGANIZATION CHART: Within 30 days of contract award, the Contractor shall submit a chart detailing each management, technical, engineering and production position from the highest company level to the lowest supervisory level. Include descriptions of each position describing the duties, responsibilities, authority and names of the individuals filling the positions, as well as identification of whether each individual is assigned to the contract full time. The organizational chart must represent the facility that will perform the work.

1.17.2 EMPLOYEE ROSTER: After receipt of award and prior to starting work aboard the vessel, the

Contractor must submit a list of employees who will work aboard ship to the Commanding Officer of the ship via the NSA Security Office. The list should be on company letterhead, include each employee's name and security clearance when required, and bear the signature of a company official.

1.18 AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER: No order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicates with Contractor personnel during the performance of this contract shall constitute a change under the "Changes" clause of this contract. The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and, notwithstanding provisions contained elsewhere in this contract, the said authority remains solely the Contracting Officer's.

In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof. The only exception to this is if the Contractor is ordered to stop for a safety reason.

If the Contractor believes it has been directed to perform work outside the scope of the contract, it must notify the Contracting Officer immediately.

2 LOCATION

2.1 Government provided pier space will be provided at Naval Base Mayport for this requirement. Government provided pier space will NOT be provided at Naval Base Norfolk. All other work shall be completed at the contractor’s facilities.

2.2 DRY-DOCK CERTIFICATION: The dry-docking of all vessels shall be accomplished in dry-docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009.

3 COST, SCHEDULE AND FINANCIAL DATA

3.1 USS LASSEN FY23 DMP must be delivered, mission-ready, no later than the “Contract Complete – Mission Ready Vessel Delivered to Fleet” (“Contract Complete”) date included in Attachment J-3.

3.2 MILESTONES: In addition to the “Contract Complete” date included in the Attachment J-3, the Government has established execution dates for the milestones identified in Attachment J-3. If any milestone event is not accomplished by the date provided, and the failure to accomplish is due to the fault or negligence of the Contractor, such failure may constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled

"DEFAULT” (DFARS 252.217-7009).

3.3 DELAYS / DISRUPTIONS: The Contractor shall coordinate the work effort with the NSA Project

Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as eight clock (8) hours or less in duration (and is not the cumulative effect of labor hour impact). Minor delays and/or disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under these resulting contracts. The Government will not provide any schedule relief for minor delays/disruptions.

The burden is on the Contractor to establish a delay/disruption is not minor in nature, by immediate verbal notification to the Project Manager and Contracting Officer, followed by a written statement within 24 hours after occurrence of delay, stating time of impact, reason for delay, duration of impact, number of people affected, action taken to properly schedule the work, action taken to minimize impact, and the names of the Government person(s) contacted, and impact to the critical path and/or controlling work items.

The ACO, in coordination with the Project Manager, will issue a written determination as to whether the contractor has met its burden and schedule relief will be granted.

3.4 SCHEDULE AND ASSOCIATED REPORTS: The scheduling of work, resources, key events and milestones submitted by the Contractor shall be in accordance with FY23 NSI 009-60 and associated CDRLs during the course of contract performance.

3.5 MILESTONES FOR CERTAIN REPORTS: The Contractor shall complete the necessary work associated with the reports due on or before the first 20% of the docking duration as well as the reports due on or before the first 20% of the availability duration and submit to the Government the required reports in the necessary format and containing the required information as specified in the Work Item in accordance with their prescribed due dates or be subject to the deductions provided in Attachment J-5 (QASP).

3.6 END COST DATA: In accordance with the reporting requirements in CDRL A016, the Contractor shall provide final actual prime and subcontractor hours, material cost and duration for each Work Item, inclusive of all definitized Request for Contract Changes (RCC) incorporated in the work package:

3.6.1 Subcontractor hours and material cost may be estimated based on the actual Prime Contractor outlay to subcontractors.

3.6.2 The Contractor is not required to provide final actual prime or subcontractor labor costs, or final total actual prime or subcontractor work item costs.

3.7 MONTHLY MANPOWER REPORT: Monthly manpower management information shall be provided in accordance with the requirements of CDRL A017.

4 SAFETY

4.1 SAFETY INSPECTOR / FIRE MARSHAL: In addition to the safety standards provided in the specifications, the Contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshal shall not be one of the

Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the Contractor’s approved Safety Plan.

4.2 PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:

(a) Protective hard hats that meet the following specifications:

(1) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers- Requirements," or shall be demonstrated to be equally effective.

(2) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]

(b) Approved type Plano or prescription glasses meeting the following specifications:

(1) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.

(2) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]

(c) Safety toe shoes, with built-in protective toe box that meet the following specifications:

(1) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.

(2) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]

4.3 BLACK OXIDE COATED THREADED FASTENERS (BOCTFs): Due to safety concerns, use of

BOCTFs is not authorized when installing or replacing threaded fasteners in the accomplishment of any work required by any Work Item in this contract.

4.4 FORCE PROTECTION CONDITION: The Government is currently in force protection condition BRAVO. Any costs associated with delays, disruptions, or security precautions associated with this force protection condition level shall be included in your proposal. Contractors will not receive additional compensation for delays, disruptions, or security precautions associated with this force protection condition level.

4.5 FIRE DRILL: The Contractor shall coordinate the execution of a full scale fire drill with the NSA within the first 30 days after the ship's arrival at the Contractor's facility. The drill will include at a minimum the requirements of the drill specified in FY23 NSIs 009-08 (Shipboard Fire Protection and Fire Prevention;

accomplish), 009-07 (Confined Space Entry, Certification, Fire Prevention and Housekeeping;

accomplish), and 009-74 (Occupational, Safety and Health Plan; accomplish). For the Contractor, this drill will require all production work to stop for a minimum of 4 hours during day shift on the selected day. As part of the drill, the Contractor is required to evacuate the ship, provide a muster report of all personnel safely off ship, support the drill with any firefighting personnel/company emergency procedures, and support the disconnection of temporary services at the drill site. Temporary services at the drill site will be disconnected in the process of the drill, and the Contractor will be responsible for restoring them after the drill. This drill will require involvement with the local fire department. An additional fire drill may be required if the availability exceeds 180 days. All costs associated with drill and production time losses shall be included in proposal. For awareness, the Government will be conducting the drill and using the evaluation criteria found in CH-12, 13, and Appendix A, of S0570-AC-CCM-010/8010. The Contractor will account for required fire drills in the proposed work schedule.

5 OTHER REQUIREMENTS

5.1 USE/POSSESSION OF PERSONAL ELECTRONIC DEVICES (PED'S): The possession and use of portable electronic devices (PED's) within the confines of any naval vessel, or in the Contractor's facility where equipment removed from the vessel is being worked, is strictly controlled. Cellular phones with digital imaging capabilities are strictly prohibited. PED's may not be connected to any Government-owned or controlled network. PED's may not be used to store or process any digital information associated with the conduct of the contract without written authorization from the Naval Supervising Activity (NSA).

PED's include:

mobile computing devices such as personal digital assistants (PDA's);

hand-held or laptop computers;

mobile telephone devices such as data-enabled cellular telephones;

two-way pagers, including those with e-mail capability;

analog and digital sound recorders; and digital cameras, including cellular phones with digital imaging capabilities.

5.2 NON SMOKING POLICY: For bidding purposes, Contractors are advised that in light of the

Government’s policy regarding smoke-free facilities, the entire vessel, topside and below decks, is to be considered a "No Smoking Area" unless otherwise indicated by shipboard policy. Local installation policies shall also apply.

5.3 CITIZENSHIP REQUIREMENTS: The Contractor shall comply with the Department of Defense Industrial Security Manual (DoD 5220.22), and any revisions to that manual as of the Proposal Due Date prescribed, for verification of all U. S. Citizens. Prospective offerors shall refer all questions pertaining to the above to NSA, Security Manager. The DoD Industrial Security Manual can be found at:

http://www.dtic.mil/whs/directives/corres/pdf/522022_vol3_2014.pdf .

5.4 PAINT ABATEMENT: Abatement work will be conducted in accordance with FY23 NSI 009-32. Paint abatement will be included as part of offerors proposed pricing and is not subject to additional growth.

5.5 FIRE PREVENTION: The Contractor will meet requirements of the NAVSEA Industrial Ship Safety Manual, for fire prevention and response (8010 Manual) and NSIs 009-01, 009-07, 009-08, and 009-74.

The Contractor will account for required fire drills in the proposed work schedule. Availability of ship fire main will be determined by the Project Manager.

5.6 RESERVED.

5.7 CRITICAL WORK AUTHORIZATION DURING AND BEYOND NORMAL BUSINESS HOURS: The Contractor shall accept any form of electronic media or verbal Authorizations to Proceed (ATP), Not-to- Exceed (NTE) obligations and Undefinitized Contract Actions (UCAs) from the Contracting Officer during and after normal hours, including weekends and holidays. Any verbal authorization will be followed up by written confirmation by the ACO within 24 hours.

5.7.1 The Government may determine that new work or growth work discovered during execution of an availability may have to begin at the time the work is identified but before receiving a proposal.

The Government reserves the right to issue an unpriced change order (UCO), unpriced GMR, or a UCA to direct the contractor to begin the work. The Government will provide the Contractor a ceiling amount, not to exceed amount, and a definitization schedule. The Contractor’s growth/new work rate established in Note B, shall be utilized when establishing the NTE amount. The contractor shall promptly begin work after receiving verbal or written direction by the Contracting Officer. The Contractor shall then submit a qualifying proposal in accordance with the definitization schedule. The ceiling amount will be adjusted after evaluation of the Contractor’s qualifying proposal. The contractor will be held responsible for any delay in completing work due to failure to comply with the Contracting Officer’s direction

6 ACCOUNTABILITY OF LEVEL OF EFFORT TO COMPLETION GROWTH

6.1 In addition to the specific requirements of the job order or contract, the Contractor shall accomplish the following:

6.2 Following receipt of a RCC, provide a COPA to the ACO (which meets the requirements of Section C, paragraph 1.13 above) and a signed Growth Management Request (GMR). The Contractor must provide the COPA and sign and deliver the GMR and supporting documentation to the SUPERVISOR and ACO.

6.3 The SUPERVISOR and ACO shall review the estimate submitted and if in agreement, shall sign the GMR authorizing the work at the labor hour and material dollars quoted. No work will be authorized prior to the Contracting Officer’s signature.

6.3.1 In the event the Contractor’s estimate differs from that of the RMC, the labor hours and material dollars shall be negotiated immediately to reach a labor hour/price agreement. The negotiated labor hour and material dollars shall then be entered into the “Negotiated Price” blocks with the required signatures. If a labor hour/price agreement cannot be reached, then the ACO may direct the Contractor to accomplish the work at a unilaterally directed labor hour/price position. Any disagreement with this direction shall be addressed in accordance with FAR 52.233-1(Alt. 1), Disputes. Additionally, if the cost of performing the disputed direction exceeds $100,000, the Contractor is required to comply with FAR 52.243-6, Change Order Accounting.

6.4 Submit one legible copy, in approved transferrable media, of a weekly report listing all LOE to Completion items to the SUPERVISOR.

6.4.1 The report shall contain the following: Work Item number, GMR number, the labor hours and material dollars negotiated for each authorized LOE to Completion work, and the total labor hours and material dollars negotiated to date, and the remaining balances allocated by CLIN.

6.5 A TDL will be issued on a weekly basis to adjudicate all authorized LOE to Completion tasking in order to permit the Contractor to invoice progress against the total cost of the authorized labor hours and material dollars under each CLIN.

6.6 Submit one legible copy, in approved transferrable media, of a final report no later than five days after completion of the availability to the SUPERVISOR.

6.6.1 The report shall contain the same information specified in 6.4.1.

6.7 The labor hours and material dollar requirements listed in the LOE to Completion CLINs are a part of this contract under the original solicitation and award. Therefore, they are subject to the provisions, terms, conditions and clauses of this contract job order and the Master Ship Repair Agreement (MSRA)/The Agreement for Boat Repair (ABR).

6.8 The reservation shall include Prime Contractor efforts under the labor hours portion of the reservation and subcontractor efforts under the material reservation.

6.9 NAVSEA text C-217-H005 GROWTH AND NEW WORK (NAVSEA JAN 2019) is not applicable to the following CLINs: 0044 – 0089.

7 ACCOUNTABILITY OF SMALL DOLLAR VALUE GROWTH ITEMS

7.1 For accountability of the Small Dollar Value Growth (SDVG) items, in addition to the specific requirements of the job order or contract, the Contractor shall accomplish the following:

7.2 Once parties have agreed the value of the work identified is $25,000, or less, the Contractor, SUPERVISOR and Contracting Officer shall sign the GMR authorizing the work at the price identified in Section B, Note E. The Contractor shall provide the estimated start date. No work will be authorized prior to the Contracting Officer’s signature.

7.3 Submit one legible copy, in approved transferrable media, of a weekly report listing all SDVG items tasked to the SUPERVISOR.

7.3.1 The report shall contain the following: Work Item number; GMR number; total original quantities of SDVG occurrences obligated under each CLIN; the quantities and occurrences tasked; and the remaining balances allocated by CLIN.

7.4 A TDL will be issued on a weekly basis to adjudicate all authorized SDVG occurrences in order to permit the Contractor to invoice progress against the total amount allocated under each CLIN.

7.5 The Contractor shall submit one legible copy, in approved transferrable media, of a final report no later than five (5) days after completion of the availability to the SUPERVISOR.

7.5.1 The report shall contain the same information specified in Section C, paragraph 7.3.1.

7.6 The requirements listed in the SDVG CLINs are hereby included as part of this contract. Therefore, they are subject to the provisions, terms, conditions and clauses of this contract and the MSRA/ABR.

7.7 In the event the quantity of occurrences for SDVG items is depleted, the SDVG process shall revert to the LOE to Completion process for remaining growth.

7.8 Once the scope of work for a task has been listed and agreed to, neither party will be entitled to an adjustment based on actual labor hours or material dollars required.

8 ACCOUNTABILITY OF RESERVE GROWTH

8.1 The LOE to Completion CLINS will be administered separately than the reserve growth embedded in the individual work items in the work package.

8.2 The Contractor shall provide an estimate of labor hours and material dollars on Reservation Task Request/Control Form (RTR Control Form), entering the date and estimate of labor and material, and deliver the estimate to the SUPERVISOR, with all applicable documentation identified in Section C, paragraph 1.11.

8.2.1 All work to be accomplished must be within the scope of the specific Work Item identifying the RTR.

8.3 The SUPERVISOR shall review the estimate submitted and, if in agreement, shall sign the signature line designated as “RMC/NSA Authorization Agreement to Quote.” The Contractor shall then sign the signature line designated as “Contractor Obligation/Agreement to…