This document provides details on a federal solicitation for docking selected restricted availability for two Navy vessels. The solicitation seeks maintenance, modernization, and repair services for the USS Mitscher (DDG 57) and USS Iwo Jima (LHD 7) with a start date of January 2022. Offerors must be registered in SAM and submit proposals through beta.SAM.gov by the applicable due dates. The work packages and attachments are not posted to beta.SAM.gov but are available upon request from the identified contracting officers. The solicitation is not set aside for small businesses based on the complexity, magnitude, and duration of the requirement. The Navy anticipates making two separate awards by October 2021 and place of performance will be at contractor facilities on the East Coast of the United States. The solicitation is issued by the Naval Sea Systems Command on behalf of the Department of the Navy.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPI FORM
| USS MITSCHER (DDG 57) FY22 DSRA N00024-21-R-4490 |
| Attachment S-3 Pre-Proposal Information (PPI) Form |
| Contracting Officer: Elizabeth Feliciano | (202)781-1049 | |||||||
| Contract Specialist: Danielle Bences | (202)781-3732 | |||||||
| Contract Specialist: Katie Daniels | TBD | |||||||
| Master # | Date of Request: | Section | Work Items/CSWT # | Para. # | Page #: | Attach. # | Contractor Question | Government Response |
| 23 | 7/23/21 | In light of the amount of undefined scope in the solicitation and the Government’s responses to recent Q&As, respectfully request, and strongly urge, the Government to reconsider and amend the solicitation by reducing the undefined work to a more reasonable volume and/or adjusting the terms and conditions to a more balanced approach that provides an equitable adjustment of cost and schedule to perform such a large volume of undefined work. | The Government re-examined the hours of growth and new work, completed its assessment and determined that no changes to the growth and new work are required at this time. |