USS IWO JIMA_QA 3.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Amendment 0009 - USS IWO JIMA (LHD 7) and USS MITSCHER (DDG 57) Docking Selected Restricted Availability (DSRA)
Solicitation number
N00024-21-R-4490
Issued by

About this file

This file contains questions and answers related to a solicitation for docking selected restricted availability for USS Iwo Jima (LHD 7) and USS Mitscher (DDG 57).

The solicitation issued by Naval Sea Systems Command seeks maintenance, modernization, and repair services for the two ships, requiring capable contractors with substantial facilities including a pier and human resources. Work includes hundreds of option items for USS Iwo Jima with an exercise date of December 3, 2021 providing less than 60 days prior to ship arrival on January 17, 2022. The government intends to exercise options as soon as feasible based on funding availability but no later than A-45. The document provides responses to contractor questions seeking clarification on work specifications and references.

View the file

Other files

File Type Posted
USS IWO JIMA_QA 7.xlsx XLSX spreadsheet
USS MITSCHER_QA 5.xlsx XLSX spreadsheet
USS IWO JIMA_QA 6.xlsx XLSX spreadsheet
N00024-21-R-4490-A0009.pdf PDF
N00024-21-R-4490-A0009 Conformed.pdf PDF
(USS IWO) Attachment J-4A Pricing Workbook (E5) - 6Aug21.xlsx XLSX spreadsheet
21-R-4490 Amendment 0008 Conformed.pdf PDF
21-R-4490 Amendment 0008.pdf PDF
21-R-4490 Amendment 0007 Conformed.pdf PDF
21-R-4490 Amendment 0007.pdf PDF
USS IWO JIMA_QA 5.xlsx XLSX spreadsheet
USS MITSCHER_QA 4.xlsx XLSX spreadsheet
USS IWO JIMA_QA 4.xlsx XLSX spreadsheet
USS MITSCHER_QA 3.xlsx XLSX spreadsheet
N00024-21-R-4490 Amendment 0006 Conformed.pdf PDF
N00024-21-R-4490 Amendment 0006.pdf PDF
N00024-21-R-4490 Amendment 0005.pdf PDF
N00024-21-R-4490 Amendment 0005 Conformed.pdf PDF
N00024-21-R-4490_Amendment 0004_Conformed.pdf PDF
N00024-21-R-4490_Amendment 0004.pdf PDF
USS IWO JIMA_QA 2.xlsx XLSX spreadsheet
N00024-21-R-4490_Amendment 0003_Conformed.pdf PDF
N00024-21-R-4490_Amendment 0003.pdf PDF
USS MITSCHER_QA 2.xlsx XLSX spreadsheet
N00024-21-R-4490_Amendment 0002_Conformed.pdf PDF
USS IWO JIMA_QA 1.xlsx XLSX spreadsheet
N00024-21-R-4490_Amendment 0002.pdf PDF
USS MITSCHER_QA 1.xlsx XLSX spreadsheet
N00024-21-R-4490 Amendment 0001.pdf PDF
N00024-21-R-4490 Amendment 0001 Conformed.pdf PDF
N00024-21-R-4490.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PPI FORM

USS IWO JIMA (LHD 7) FY22 DSRA N00024-21-R-4490Contracting Officer: Elizabeth Feliciano(202)781-1049
Attachment S-3A Pre-Proposal Information (PPI) FormContract Specialist: Danielle Bences(202)781-3732
Contract Specialist: Katie DanielsTBD
Master #Date of Request:SectionWork Items/CSWT #Para. #Page #:Attach. #Contractor QuestionGovernment Response
1326/11/21SolicitationRevised solicitation converts all work items to Options with the exception of CLINs 0001 and 0002 for availability preparation and procurement of some LLTM.

CLINs 0003, 0005, 0008. 0009, and 0045 include hundreds of Option Items that now have an exercise date of NLT 3-DEC-21.

This is a formula for failure as it provides less than 60 days prior to ship arrival to prepare for execution of an enormous amount of work when the ship arrives on 17-JAN-22 We see no reason that Options cannot be exercised NLT 10/15/21 which might provide enough time to hire all subcontractors, order LLTM, and schedule resources to coordinate for an extremely complex availability.

Please confirm that this is the intent.

The Government intends to exercise options as soon as feasible in the new FY based on funding availability but NLT A-45.
1396/21/21123-11-0013.2Paragraph 3.2 calls out preservation in accordance with Table 4, Line 11. This table and line identifies Note 65 as applicable. Will the Government allow preservation of the Fuel Service Tanks to be done in accordance with Note 65?No. Note 65 is not applicable. Preservation of the tanks is required. Note 65 states “Fuel oil storage, fuel oil service, fuel oil gravity head tanks, and diesel service tanks are not required to be painted unless specifically addressed in the tables. The WI invokes entire table: 009-32 Table 4, Line 11 and requires SSPC-SP-10 and single coat ofvultra high solids coating system.
1596/30/21763-90-0013.1Drawing 8831186 piece #11 shows tagging and retaining this piece but then shows a source of IAF. Please clarify whether piece #11 is retained for reinstallation or furnished by the IAF.Piece 11 is a remove/retain item. 8831186 incorrectly notes the source as IAF, it should be noted as "R". For reference, the removal drawing (8831185) directs removal of 2 5-drawer file cabinets and requires the better of the two be retained for installation as LOM item 11 in 8831186. A LAR is being submitted to correct dwg 8831186.
1606/30/21160-90-0012.18, 3.1Installation Note 11, on page 2 of drawing 184-8830872 directs treatment of the "Platform Weldment" per Mil-H-6088E. This is a Mil-Spec is for aluminum assemblies. All the welding on this drawing is carbon steel and stainless steel. The only aluminum is P/N 2, which is retained and reinstalled without welding. Please clarify if this Mil-Spec is applicable and required.Correction of reference for BQ 160; should be, 2.18 (184-8830872), page 2, Note 12; PER “quicksearch.dla.com” MIL-SPEC Mil-H-6088E(Latest REV listed “G”) is canceled, will need a LAR to correct note, follow requirements of NSI 009-12, which reference “MIL-STD-1689, Fabrication, Welding, and Inspection of Ships Structure” for welding requirements.
1777/1/21251-31-0012.9The Contractor contacted the POC for the reference 2.9 , 2607.001 Rev E, to obtain the drawing that was added in errata 5. We were issued Rev D and told this was the latest available revision. Please confirm the contractor is to use Rev D providedRev E is the proper revision. As this is a restricted document. Requests for limited distribution Drawings/References can be submitted at the following link: http://www.coretl.com/help/shell.php. The Technical POC is: Timothy Russell. Mr. Russell can be reached at timothy.russell1@navy.mil.
1787/1/21251-32-0012.9The Contractor contacted the POC for the reference 2.9 , 2607.002 Rev C, to obtain the drawing that was added in errata 5. We were issued Rev B and told this was the latest available revision. Please confirm the contractor is to use Rev B providedRev C is the proper revision. As this is a restricted document. Requests for limited distribution Drawings/References can be submitted at the following link: http://www.coretl.com/help/shell.php. The Technical POC is: Timothy Russell. Mr. Russell can be reached at timothy.russell1@navy.mil.
1797/2/21Attachment J-1182-10-0013.1.4Para 3.1.4 calls for fasteners to be coated with Polysulfide sealant conforming to MIL-PRF-85285. The issue is, MIL-PRF-85285 is not a spec for polysulfide, but polyurethane spec. Please clarify if the Governemnt wants MIL-PRF-85285 and what type and classThe correct spec is MIL-PRF-81733. WI will be corrected via Errata 7. Errata forthcoming.