USS_SHOUP_FY19_DMP__BQ6.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
FY19 Depot Modernization Period (DMP) Availability For USS SHOUP (DDG 86)
Solicitation number
N00024-18-R-4407
Issued by

About this file

Bidder Questions

View the file

Other files

File Type Posted
N00024-18-R-4407_A0008_conformed.pdf PDF
N00024-18-R-4407_A0008.pdf PDF
N00024-18-R-4407-0007.pdf PDF
USS_SHOUP_FY19_DMP__BQ5.xlsx XLSX spreadsheet
N00024-18-R-4407-0006.pdf PDF
N00024-18-R-4407-0005.pdf PDF
N00024-18-R-4407_0004.pdf PDF
J-4_Pricing_Workbook_-_SHOUP_rev_8.xlsm XLSM spreadsheet
USS_SHOUP_FY19_DMP__BQ_4.xlsx XLSX spreadsheet
J-4_Pricing_Workbook_-_SHOUP_rev_7.xlsm XLSM spreadsheet
J-5_QASP_SHP_FY19_DMP_rev_2.docx DOCX document
USS_SHOUP_FY19_DMP__BQ_3.xlsx XLSX spreadsheet
N00024-18-R-4407_0003.pdf PDF
J-4_Pricing_Workbook_-_SHOUP_rev_6.xlsm XLSM spreadsheet
USS_SHOUP_FY19_DMP__BQ_2.xlsx XLSX spreadsheet
N00024-18-R-4407_0002.pdf PDF
N00024-18-R-4407_0001.pdf PDF
USS_SHOUP_FY19_DMP__BQ1.xlsx XLSX spreadsheet
J-4_Pricing_Workbook_-_SHOUP_rev_5.xlsm XLSM spreadsheet
J-5_QASP_SHP_FY19_DMP_rev_1.docx DOCX document
N00024-18-R-4407_USS_SHOUP.pdf PDF
S-4_PP_Reference_List_SHP.docx DOCX document
S-3_PPI_Form_SHP.docx DOCX document
J-5_QASP_SHP_FY19_DMP.docx DOCX document
S-2_Past_Performance_Questionnaire_SHP.docx DOCX document
J-7_Schedule_Model_Review.docx DOCX document
S-5_Eligibility_Criteria_Data_Sheet_SHP.docx DOCX document
J-4_Pricing_Workbook_-_SHOUP_-_12Jun18_rev4.xlsm XLSM spreadsheet
USS_SHOUP_Synopsis.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Attachment S-3

Pre-Proposal Information (PPI) Form
DATE OF REQUEST: 28 August 2018SOLICITATION NO: N00024-18-R-4407
TITLE: USS SHOUP (DDG 86) FY19 DMPNAVSEA POC: Martha.Bello@navy.mil; kurt.boyles@navy.mil

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

FORWARD ALL REQUESTS TO: Martha Bello, Martha.Bello@navy.mil; and Kurt Boyles, kurt.boyles@navy.mil

ITEM NO: : 624-11-001 CONTRACTOR QUESTION 103:

Paragraph 3.5 states to ‘Install new each balanced joiner door and associated equipment…’. Parts listed in paragraph 3.5 show NAME OF PART and PIECE NO. for a door manufactured by Ellison Bronze Inc. but PART NO. for a door manufactured by Bennett Industries.

Contractor requests clarification of which door Government wants purchased and installed

GOVERNMENT RESPONSE:

Per reference 2.2 of the work item, both part numbers listed are equivalent. Errata #6 issued to remove any confusion.

Please contact Kurt Boyles, Kurt.Boyles@navy.mil and Martha Bello, Martha.Bello@navy.mil to request the Errata.

TITLE:
PARA. NO: 3.5
PAGE NO:

ITEM NO: : 582-11-001 CONTRACTOR QUESTION 104:

Paragraph 3.3.3 states to ‘Restore pump mating surfaces exposed by disassembly.’ Paragraph 1.3 and reference drawings do not indicate any pump.

Contractor requests clarification of which pump the Government wants disassembled?

GOVERNMENT RESPONSE:

Errata #6 issued to delete the work "Pump."

Please contact Kurt Boyles, Kurt.Boyles@navy.mil and Martha Bello, Martha.Bello@navy.mil to request the Errata.

TITLE:
PARA. NO: 3.3.3
PAGE NO:

ITEM NO: : 624-11-001 CONTRACTOR QUESTION 105:

Paragraph 3.2.2 states to ‘Plug Weld a total of 40 holes.’. Contractor requests clarification on if these holes are from previous door and will not affect new door bolt pattern or if drilling of new holes will be required to accommodate new doors installed in paragraph 3.5? GOVERNMENT RESPONSE:

Yes, the holes are from previous door installations and they will affect new door installation.

Yes, drilling of new holes will be required to accommodate installation of new doors.

TITLE:
PARA. NO: 3.2.2
PAGE NO:

ITEM NO: : 167-11-005 CONTRACTOR QUESTION 106:

Paragraph 3.2 states to ‘Remove existing and install new each the equipment located in 1.2, identified in 1.3, and provided in 5.1…’. Reference 2.5 indicates single hatch(s) with side deck ramps surrounding hatch but existing hatches have longer side ramps and elevated deck spacer to connect them. Contractor requests clarification on if these hatches will be supplied together as one piece with connecting side ramps and deck spacer already installed, will new side ramps and deck spacer to connect new hatches be supplied as part of GFM, or will new hatches require modification and reuse of existing side deck ramps and deck spacer prior to install? GOVERNMENT RESPONSE:

The GFM to be provided consists of two hatches and insert plate assembly, and separately the ramps and center plate as an assembly. These will both require welding during installation.

TITLE:
PARA. NO: 3.2.2
PAGE NO:

image1.jpg