J-7_Schedule_Model_Review.docx

DOCX document 16 KB Posted

Attached to
FY19 Depot Modernization Period (DMP) Availability For USS SHOUP (DDG 86)
Solicitation number
N00024-18-R-4407
Issued by

About this file

J-7 Schedule Model Review

View the file

Other files

File Type Posted
N00024-18-R-4407_A0008_conformed.pdf PDF
N00024-18-R-4407_A0008.pdf PDF
N00024-18-R-4407-0007.pdf PDF
USS_SHOUP_FY19_DMP__BQ6.xlsx XLSX spreadsheet
USS_SHOUP_FY19_DMP__BQ5.xlsx XLSX spreadsheet
N00024-18-R-4407-0006.pdf PDF
N00024-18-R-4407-0005.pdf PDF
N00024-18-R-4407_0004.pdf PDF
J-4_Pricing_Workbook_-_SHOUP_rev_8.xlsm XLSM spreadsheet
USS_SHOUP_FY19_DMP__BQ_4.xlsx XLSX spreadsheet
J-4_Pricing_Workbook_-_SHOUP_rev_7.xlsm XLSM spreadsheet
J-5_QASP_SHP_FY19_DMP_rev_2.docx DOCX document
USS_SHOUP_FY19_DMP__BQ_3.xlsx XLSX spreadsheet
N00024-18-R-4407_0003.pdf PDF
J-4_Pricing_Workbook_-_SHOUP_rev_6.xlsm XLSM spreadsheet
USS_SHOUP_FY19_DMP__BQ_2.xlsx XLSX spreadsheet
N00024-18-R-4407_0002.pdf PDF
N00024-18-R-4407_0001.pdf PDF
USS_SHOUP_FY19_DMP__BQ1.xlsx XLSX spreadsheet
J-4_Pricing_Workbook_-_SHOUP_rev_5.xlsm XLSM spreadsheet
J-5_QASP_SHP_FY19_DMP_rev_1.docx DOCX document
N00024-18-R-4407_USS_SHOUP.pdf PDF
S-4_PP_Reference_List_SHP.docx DOCX document
S-3_PPI_Form_SHP.docx DOCX document
J-5_QASP_SHP_FY19_DMP.docx DOCX document
S-2_Past_Performance_Questionnaire_SHP.docx DOCX document
S-5_Eligibility_Criteria_Data_Sheet_SHP.docx DOCX document
J-4_Pricing_Workbook_-_SHOUP_-_12Jun18_rev4.xlsm XLSM spreadsheet
USS_SHOUP_Synopsis.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J-7 Schedule Model Review USS SHOUP Purpose: At A-30 the LMA shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day2 and following is 0800-1130.

1. Required Attendees:

a. LMA management team

b. Government Project Management Team (NSA)

c. Turnkey Subcontractors

d. AIT On Site Installation Coordinators (OSIC)

e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable

f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)

2. Agenda:

Day 1 WPER (Government Facilitated)

a. Early Start Candidates (LMA)

b. WAF/Tag Out coordination (LMA)

c. Pier Laydown Plan (LMA)

d. First 100 Hour Plan (NSA)

e. Communications Plan (NSA)

f. Process Control Procedures (PCP) (LMA)

g. Access Cuts (LMA)

h. Fire Prevention and Fire Drill (8010) requirements (NSA)

i. Memorandum of Agreement (MOA) – AIT’s only (NSA)

Day 2 - 7

j. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the Lead Maintenance Activity (LMA), subcontractors, Alteration Installation Teams (AIT), Ship’s Force, and Intermediate Maintenance Activity (IMA).

3. Deliverables:

a. Updated IPS with all maintenance activities fully integrated. (LMA)

b. Early start candidates submitted and approved by the NSA. (LMA)

c. WAF/Tag Out coordination plan established. (LMA)

d. First 100 Hour Plan established. (NSA)

e. Set schedule for all required meetings. (NSA)

f. Pier Laydown Plan submitted for approval by Naval Station Everett. (LMA)

g. List of Process Control Procedures with projected due dates. (LMA)

h. List of access cuts (if required). (LMA)

i. Fire drill execution date set. (NSA)

j. Detailed review of critical path and top three controlling path items. (LMA)