Attachment 2 First Article and Factory Acceptance Testing Requirements N00024-15-R-6401
First Article
Requirements
Component/
Assembly
Part/ Drawing
Number
Applicable C2-b/
CIPS
Factory Acceptance
Tests Performed by
Contractor
FAT Details Required Test Equipment/Solutions for FAT First Article
Requirements Verified by the GOV During the POM
Phase
Afterbody and
Tailcone Unit
8243663 6935288 6935288: Figure 1
To be completed only after successful FAT of lower level assemblies.
Figure 1 details:
4.2 Dimensional and Material Inspection
4.2.4.3.1 Insulation Resistance
4.2.4.3.2 Electrical Isolation
4.2.4.3.3 Fin Deflection
4.2.4.3.4.1 External Pressure Test by Contractor
4.2.4.3.5 Hydraulic System Leakage
4.2.4.3.6 Operational Test (air spin)
4.2.4.3.7 VSS Test
4.2 COTS
4.2.4.3.1 CTR
4.2.4.3.2 CTR
4.2.4.3.3 CTR
4.2.4.3.4.1 CTR Pressure Test & GFE Vacuum
Test Stand (MK5 Hydraulic Filling Unit)
4.2.4.3.5 CTR
4.2.4.3.6 GFE Air Spin Test Tools and Vacuum
Test Stand
4.2.4.3.7 GFE VSS Testing Tools
6935288: Figure 3
Engine Assembly 7052739 6935289 SW-513-EO-PRO-050
Job Sheet 3-81 Engine assembly verification tests
3-81-6 Engine shaft Displacement Test
3-81-8 Piston Head Clearance test
3-81-6 GFE: Engine Assembly Cart (P/N
7052521)
3-81-8 GFE Engine Cart and Tools
6935289: Figure 4
Lube Oil Pump
Assembly
2074259 5893761 5893761: Figure 1 Figure 1:
4.2 Dimensional and Material Inspection
4.2.4.1 Self Priming Test
4.2.4.2 Flow and Pressure Low Speed
4.2 COTS
4.2.4.1 CTR Test Stand*
4.2.4.2 CTR Test Stand*
(*GFF Test Stand available)
5893761: Figure 3
Coolant Pump
Assembly
6935010 6935197 6935197: Figure 2 Figure 2:
4.2 Dimensional and Material Inspection
4.2.4.3.3.1 Valve cycle test
4.2.4.3.3.2 Valve Leak Test
4.2.4.3.3.3 Valve Operational Test
4.2.4.3.2 External Leakage
4.2.4.3.1 Flow and Pressure
4.2 COTS
4.2.4.3.3.1 CTR Test
4.2.4.3.3.2 CTR Test
4.2.4.3.3.3 CTR Test
4.2.4.3.2 CTR Test Stand
4.2.4.3.1 CTR Test Stand
6935197: Figure 4
Hydraulic Pump
Assembly
6558186 5893762 5893762: Source
Controlled Drawing, FAT Verified by Source
Contractor before delivery to Prime
FAT level test performed during top level FAT N/A: Source already has required equipment N/A
Speed Control Valve 5905689 5894150 ST890-BM-MMD-020
J/S 4-2
Must meet all testing requirements per J/S 4-2 GFE: MK 707 Speed Control Valve Test Set 5894150: Figure 5
Factory Acceptance Test Requirements
For Official Use Only
SOURCE SELECTION SENSITIVE INFORMATION – SEE FAR 2.101 and 3.104 Page 1 of 3
Deployable Water
Inlet Valve (DWIV)
6935142 6935196 5893750: Figure 1 Figure 1:
4.2 Physical Inspection
4.2.4.2.1 Cycling Test
4.2.4.2.2.1 Outlet Port Test
4.2.4.2.2.2 Inlet Port Test
4.2.4.2.3 Operating Pressure Test
4.2.4.2.4 Pilot Proof-Pressure Test
4.2.4.2.5 Opening Time Test
4.2.4.2.6 Closing Time Test
4.2 COTS
4.2.4.2.1 CTR
4.2.4.2.2.1 CTR
4.2.4.2.2.2 CTR
4.2.4.2.3 CTR
4.2.4.2.4 CTR
4.2.4.2.5 CTR
4.2.4.2.6 CTR
5893750: Figure 3
Velocity Sensor
Switch
6935175 6935194 6935194: Figure 4 and
SW-513-EO-PRO-040
Job Sheet 3-41
Velocity Sensor Switch test
Figure 4:
4.2 Performance Verification
4.2.4.1 Hydrostatic Pressure (one cycle)
4.2.4.2 Electrical Performance
4.2.4.3 Maximum Force
3-41 Velocity Sensor Switch Test
4.2 COTS
4.2.4.1 CTR
4.2.4.2 CTR*
4.2.4.3 CTR
3-41 CTR*
(*GFE VSS tester provided can be utilized for these tests)
6935194: Figure 6
Type II Cables: 5W1 (5893725)
5W2 (5893727)
5W2 (5893729)
5W7 (5893731)
5W8 (5893733)
5W9 (5893735)
5W13
(5893737)
5W14
(5893739)
5W15
(6105293)
5W16
(6105298)
5894148 5894148: Figure 1 Figure 1:
4.2 & 4.2.4.4 Dimensional, Material, Weight and
Workmanship Inspection only*
4.2.4.1 Pressure/Temp Operating
4.2.4.2 Electrical Performance
4.2.4.3 Cable Transition
(*Sub paragraphs of 4.2 not specifically called out are not part of FAT requirement)
4.2&4.2.4.4 COTS
4.2.4.1 CTR
4.2.4.2 CTR
4.2.4.3 CTR
5894148: Figure 3
Slide Valve 2507318 6724953 6724953: Figure 1 Figure 1:
4.2 Dimensional and Material Inspection
4.2.4.2.1 Connector Mating
4.2.4.2.2 Coil Resistance
4.2.4.2.3 Insulation Resistance
4.2.4.2.4 Continuity Loop
4.2.4.3 Operational Performance
4.2 COTS
4.2.4.2.1 CTR
4.2.4.2.2 CTR
4.2.4.2.3 CTR
4.2.4.2.4 CTR
4.2.4.3 CTR
6724953: Figure 3
SOURCE SELECTION SENSITIVE INFORMATION – SEE FAR 2.101 and 3.104 Page 2 of 3
Tailcone Assembly, Shock Hardened
8243661 N/A SW-513-EO-PRO-050
Job Sheet 3-104
Pass all testing required per job sheet 3-104. GFE: MK 659 Factory Steering Assembly Test
Set (FSATS)
N/A
Fuel Delivery
Assembly (FDA)
6935014 6935190 SW-513-EO-PRO-040
Job Sheet 3-42
Pass all testing required per job sheet 3-42. GFE: MK 658 Fuel Delivery Assembly Test Set
(FDATS)
6935190: Figure 2
Fuel Pump Valve 6935093 6935193 N/A All 6935193 FAT tests satisfied at FDA level N/A 6935193: Figure 5
Fuel Pump 6935015 6935195 N/A All 5894152 FAT tests satisfied at FDA level N/A N/A
EPS Regulator
Assembly
5894200 5893756 AEPS test per
Attachment 3
5893756: Figure 13
AEPS: All tests Passed
Perform only these tests from Figure 13:
4.2.4.1.1 Vacuum
AEPS: Contractor Designed Auto Electrical
Power System (AEPS) Test Equipment (CLIN
0x03)
4.2.4.1.1 GFE Vacuum Test Stand
5893756: Figures 11 & 15
Alternator Assembly 6935009 6935199 AEPS test per
Attachment 3
6935199: Figure 14
AEPS: All tests Passed
Perform only these tests from Figure 13:
4.2 Dimensional and Material inspection
4.1.2.1 Run-In
4.2.4.17 Vacuum
AEPS: Contractor Designed Auto Electrical
Power System (AEPS) Test Equipment (CLIN
0x03)
4.2 COTS
4.1.2.1 CTR
4.2.4.17 GFE Vacuum Test Stand
6935199 Figures 11 & 12
Isolated Rotor
Assembly
7053477 7053456 7053456: 4.2.1 4.2.1 Axial Load Testing 4.2.1 CTR 7053456: 3.5
Performance per 6934934 requirements
SOURCE SELECTION SENSITIVE INFORMATION – SEE FAR 2.101 and 3.104 Page 3 of 3