AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The Request for Proposal is hereby amended in accordance w ith the changes incorporated.
1. CONTRACT ID CODE PAGE OF PAGES
S 1 37
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-May-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N00019-15-R-0090
X 9B. DATED (SEE ITEM 11)
16-Apr-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-May-2015
CODE
NAVAL AIR SYSTEMS COMMAND
AIR-2.2.3.1 SUITE 453 BLDG
47123 BUSE RD UNIT IPT
PATUXENT RIVER MD 20670
N00019 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N00019-15-R-0090
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The depository location has changed from bldg 2272 room 453 to Bldg 2455, Room 103.
SECTION F - DELIVERIES OR PERFORMANCE
The following have been modified:
52.242-15 STOP-WORK ORDER (AUG 1989)
(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 60 days after the order is delivered to the
Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 60 days after a stop-work is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either--
(1) Cancel the stop-work order; or
(2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.
(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if--
(1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract; and
(2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim submitted at any time before final payment under this contract.
(c) If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the
Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement.
(d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the
Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.
Applicable CLINs: 0001, 0002, 0003, 0004, 0007, 0009, 0012, 0101, 0102, 0103, 0104, 0106, 0107, 0109, 0110, 0201, 0202, 0203, 0204, 0206, 0207, 0209, 0210
52.242-15 STOP-WORK ORDER (AUG 1989) - ALT I (APR 1984)
(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 60 days after the order is delivered to the
Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 60 days after a stop-work is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either--
(1) Cancel the stop-work order; or
(2) Terminate the work covered by the order as provided in the Termination clause of this contract.
(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected, and the contract shall be modified, in writing, accordingly, if--
(1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract; and
(2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim submitted at any time before final payment under this contract.
(c) If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the
Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement.
(d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the
Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.
Applicable CLINs: 0005, 0008, 0010, 0105, 0108, 0205, 0208
5252.216-9506 MINIMUM AND MAXIMUM QUANTITIES (NAVAIR) (MAR 1999)
As referred to in paragraph (b) of FAR 52.216-22 "Indefinite Quantity" of this contract, the contract minimum quantity and the maximum quantity is
Item Description Min Qty
(FY16)
Max Qty
(FY16)
0001 A-D High Flight Hour
Inspections
1 Aircraft 2 Aircraft
0002 A-D Modifications 1 Aircraft 4 Aircraft
0003 Engineering Services (A-D) 0 LH 2,950 LH
0004 Artisan Labor (A-D) 0 LH 2,700 LH
0005 Parts and Materials A-D $0 $185,000
0006 A-D Validation and/or
Verification
0 LH 0 LH
0007 A-D Repair Incident to
Modification
0 LH 3,200 LH
OPTION
NMCI Seats $0 $23,000
0009 DATA NSP NSP
OPTION
OOMA/FAME Server $0 $45,000
0011 Transition In 1 Lot 1 Lot
0012 Artisan Labor (A-D) 0 LH 6,300 LH
OPTION
Items
Description Min Qty
(FY17)
Max Qty
(FY17)
0101 A-D High Flight Hour
Inspections
2 Aircraft 9 Aircraft
0102 A-D Modifications 2 Aircraft 13 Aircraft
0103 Engineering Services (A-D) 0 LH 9,550 LH
0104 Artisan Labor (A-D) 0 LH 12,100 LH
0105 Parts and Materials A-D $0 $600,000
0106 A-D Validation and/or
Verification
0 LH 4,000 LH
0107 A-D Repair Incident to
Modification
0 LH 10,400 LH
OPTION
NMCI $0 $23,000
0109 DATA NSP NSP
0110 Artisan Labor (A-D) 0 LH 17,050 LH
OPTION
Items
Description Min Qty
(FY18)
Max Qty
(FY18)
0201 A-D High Flight Hour
Inspections
2 Aircraft 9 Aircraft
0202 A-D Modifications 2 Aircraft 13 Aircraft
0203 Engineering Services (A-D) 0 LH 9,550 LH
0204 Artisan Labor (A-D) 0 LH 12,100 LH
0205 Parts and Materials A-D $0 $600,000
0206 A-D Validation and/or
Verification
0 LH 4,000 LH
0207 A-D Repair Incident to
Modification
0 LH 10,400 LH
OPTION
NMCI $0 $23,000
0209 DATA NSP NSP
0210 Artisan Labor (A-D) 0 LH 17,050 LH
SECTION I - CONTRACT CLAUSES
252.209-7010 CRITICAL SAFETY ITEMS (AUG 2011)
(a) Definitions.
“Aviation critical safety item” means a part, an assembly, installation equipment, launch equipment, recovery equipment, or support equipment for an aircraft or aviation weapon system if the part, assembly, or equipment contains a characteristic any failure, malfunction, or absence of which could cause--
(i) A catastrophic or critical failure resulting in the loss of, or serious damage to, the aircraft or weapon system;
(ii) An unacceptable risk of personal injury or loss of life; or
(iii) An uncommanded engine shutdown that jeopardizes safety.
“Design control activity” means -
(i) With respect to an aviation critical safety item, the systems command of a military department that is specifically responsible for ensuring the airworthiness of an aviation system or equipment, in which an aviation critical safety item is to be used; and
(ii) With respect to a ship critical safety item, the systems command of a military department that is specifically responsible for ensuring the seaworthiness of a ship or ship equipment, in which a ship critical safety item is to be used.
“Ship critical safety item” means any ship part, assembly, or support equipment containing a characteristic, the failure, malfunction, or absence of which could cause--
(i) A catastrophic or critical failure resulting in loss of, or serious damage to, the ship; or
(ii) An unacceptable risk of personal injury or loss of life.
(b) Identification of critical safety items. One or more of the items being procured under this contract is an aviation or ship critical safety item. The following items have been designated aviation critical safety items or ship critical safety items by the designated design control activity:
TBD per Task Order___________________
(Insert additional lines as necessary)
(c) Heightened quality assurance surveillance. Items designated in paragraph (b) of this clause are subject to heightened, risk-based surveillance by the designated quality assurance representative.
The following have been deleted:
52.204-15 Service Contract Reporting Requirements for Indefinite-
Delivery Contracts
JAN 2014
52.216-18 Ordering OCT 1995
252.227-7026 Deferred Delivery Of Technical Data Or Computer Software APR 1988
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J
SECTION J
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A: Contract Data Requirements List – DD 1423
A001 Program Plan: Quality Assurance (QA) 1 02 April 2015
A002 Program Plan: Configuration Management (CM) 1 05 May 2015
A003 Program Plans: Ground Operations 1 05 May 2015
A004 Program Plans: Airfield Operations, Flight
Planning, and Flight Missions
1 05 May 2015
A005 Program Plans: Aviation Safety 1 05 May 2015
A006 Program Protection Implementation Plan (PPIP) 1 02 April 2015
A007 Operations Security (OPSEC) Plan 1 02 April 2015
A008 Over and Above (O&A) Work Requests 1 02 April 2015
A009 Noted But Not Corrected (NBNC) Reports 1 02 April 2015
A00A Service Life Extension Authorization (SLEA)
Requests
1 02 April 2015
A00B OOMA – FAME - Logs & Records 1 02 April 2015
A00C Procurement Request Reporting 1 02 April 2015
A00D Progress Reports 1 02 April 2015
A00E Request For Technical Instruction (RFTI) 1 02 April 2015
A00F Naval Aviation Maintenance Discrepancy
Reporting Program (NAMDRP)
1 02 April 2015
A00G Action Items, Meeting Minutes, Presentation
Material
1 02 April 2015
A00H Cost Data Summary Report (CSDR): Contractor
Cost Data Reporting (CCDR)
1 03 April 2015
A00J Functional Cost-Hour Report: Contractor Cost
Data Reporting (CCDR)
1 03 April 2015
A00K Contract Work breakdown Structure (CWBS) 1 03 April 2015
A00L Integrated Master Schedule (IMS) 1 05 May 2015
A00M Contractor Cost Data Reporting 1 04 May 2015
A00N Contractor Manpower Reporting 1 02 April 2015
A00P Cyber Security Implementation Plan 1 02 April 2015
A00Q Parts & Material Summary Report 1 05 May 2015
Supplement 1 Supplement to the Exhibits 1 02 April 2015
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachments:
Attachment (1) Statement of Work (SOW) – F/A-18A/B/C/D
Contractor Depot Level Maintenance
54 04 May 2015
Attachment (2) Supplemental SOW – F/A-18A/B/C/D Contractor
Depot Level Maintenance
7 05 December 2014
Attachment (3) Cyber Security Plan (Located in the
Technical
Library)
20 January 2015
Attachment (4) HFH Induction Configurations 1 15 June 2014
Attachment (5A) HFH Inspection Results Summary 1 15 June 2014
Attachment (5B) HFH Inspection - Engineering Analysis Results 14 15 February 2014
Attachment (6A) Procurement Request (PR)Tracking 1 15 February 2014
Attachment (6B) PR Tracking 1 15 June 2014
Attachment (7) Unit Price Matrix (FFP) 2 26 February 2015
Attachment (8) DD-254 (Located in the
Technical
Library)
14 July 2014
Attachment (9) Task Order Summary 2 26 February 2015
Attachment (10) NAVAIR DFC Requiring NMCI Access 2 22 April 2013
Attachment (11) OOMA Server Requirements Specification (Navy
Homeguard) V1.0
11 09 January 2013
Attachment (12) Program Protection Plan (PPP) (Located in the
Technical
Library)
01 March 2007
Attachment (13) Government Furnished Property (GFP) List 3 27 May 2015
Attachment (14) RESERVED Small Business Subcontractor Plan TBD TBD
Attachment (15) Cost Summary Data Report 4 2 April 2015
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
L-1 CONTENT OF PROPOSALS (SUPPLIES OR SERVICES) (JUN 2011) (DEC 2014)
PART A GENERAL INSTRUCTIONS
1.0 GENERAL
In accordance with FAR Subpart 6.202(a)(1), The Boeing Company and all its subsidiaries are excluded from the role of prime contractor and/or subcontractor for this contract in order to establish an alternative source for the supplies/services being procured. Should an offeror propose The Boeing Company or any of its subsidiaries as a
Joint Venture team member, principal subcontractor, critical team member, or subcontractor at any tier, the proposal submission shall be rejected in its entirety. If during the course of the evaluation of the proposal, the United States
(US) Government becomes aware that the offeror proposed any portion of this effort be performed by The Boeing
Company, the offer shall be unawardable.
Offerors are required to submit sufficient information concerning all evaluation factors to enable US Government personnel to fully assess the capabilities of the Offeror to perform all requirements. The proposal must be sufficient in detail and scope to enable evaluation and provide the evaluators a clear understanding of the Offeror’s approach, expertise, experience and capability as required by the solicitation. All proposals must clearly and convincingly demonstrate that the Offeror has a thorough understanding of all requirements and associated risks; is able, willing, and competent to devote the resources necessary to meet all requirements; and has valid and practical solutions for all requirements and potential risk areas. The Offeror shall not alter or rearrange the solicitation. The burden of proof for all substantiation within the proposal rests with the Offeror. Offerors are advised that the US Government may incorporate any part of the Offeror’s proposal deemed beneficial to the US Government, into the final contract.
With the exception of Annex B (Small Business Subcontracting Plan); Volume 4 Price; and Volume 5 Contract
Administration, no price should appear in any other volume. Alternate proposals will not be accepted.
In presenting material in the proposal, the Offeror is advised that quality of information is more important than quantity. Clarity, brevity, and logical organization should be emphasized during proposal preparation. It is the responsibility of the Offeror to present enough information to allow the various work efforts, support, and management approaches, as well as price, to be meaningfully evaluated. Unsubstantiated statements that the Offeror understands, can or will comply with the specifications, or paraphrasing the requirements or parts thereof are considered inadequate and may render a rating of unacceptable.
The Offeror shall include any data necessary to illustrate the adequacy of the various assumptions, approaches, and solutions to problems. There is no need to repeat information in more than one volume. The detailed information must be included in the most logical place and summarized and referenced in other areas if an overlap exists.
Unnecessarily elaborate brochures or other presentation materials beyond that sufficient to present a complete and effective proposal is neither necessary nor desired.
Throughout these instructions, Offeror is defined as the prime contractor with its CAGE/NCAGE code identified in
Block 15A on Standard Form (SF) 33, Solicitation, Offer, and Award. A “Joint Venture” (JV) is a partnership or teaming arrangement that is formed for the purpose of responding to this solicitation when the prime contractor consists of more than one legal entity. A “JV Team Member” is defined as one of the entities that make up a JV or any other partnership or teaming arrangement formed for the purpose of responding to this solicitation. The term
“entity” is used to mean any or all of the following: prime contractor, JV, critical team members, JV team members, any subcontractor, and corporate parent, division, subsidiary, or affiliate (e.g. any contractor with a different
CAGE/NCAGE code/DUNS than the Offeror). A “principal subcontractor” is defined as a subcontractor who provides at least 10% of the proposed total price (excluding the Offeror’s profit/fee) for the contract. “Critical team member” is defined as one of the entities of the Offeror that perform a critical technical function (i.e.
Security/Safeguarding, MAUS inspections and aircraft X-Rays) in the performance of the resulting contract.
Only the following entities will be used in the past performance evaluation: (a) the prime contractor; and (b) critical team members (c) JV Team Members and (d) principal subcontractors (excluding the Offeror’s profit/fee). These entities are considered relevant entities and only relevant entities will be used in the past performance evaluation.
All other entities will be considered non-relevant. The Offeror must demonstrate through the price proposal and/or other proposal information that these entities meet the definition of a relevant entity, or the US Government may deem the entity to be not relevant and thereby not include them in the past performance evaluation.
2.0 PROPOSAL FORMAT AND SUBMISSION
Proposals must be formatted using a Times New Roman 12 point normal font (no reduction permitted), single-spaced with 1-inch margins all around, and formatted for/printed on standard 8.5 x 11 inch paper. All pages should be numbered with volume, paragraph, and page numbers. When fold-out pages are used, they must not exceed 11 x
17 inches and will be counted as 1 page. Drawings/Diagrams may be provided separately and may be any size but should be folded to approximately 8.5 x 11 inch standard size and will count as 1 page. If the Offeror uses graphs to convey information the graphs must show enough detail to easily discern the information described. Graphs and tables shall be presented in no smaller than a 10 pt font. Graphs should contain a grid, which allows values to be read directly from the graph to the same detail that a 10 x 10 to the ½ inch grid provides. Graphic resolution should be consistent with the purpose of the data presented. Text utilized in charts, figures, and graphics shall also be no smaller than a 10pt font and may use a font type selected by the Offeror. Each volume, book, or annex shall be provided separately in a 3-ring binder. The binders should be of an appropriate thickness for the number of pages it contains (e.g., a 30-page book should not be placed in a 2-inch binder).
2.1 Electronic Submission of Proposal
This section is intended to provide information to the Offeror on the electronic format and application software to be used for submitting proposals. Use of the software and procedures described in this section will reduce the amount of time and effort needed to receive and install proposals onto the electronic evaluation system, and will ensure that the proposals received are suitable for reading electronically.
2.1.1 Electronic Proposal Media
The Offeror should submit all volumes of its proposal electronically on CD-ROM(s) compatible with the operating system and applications defined in Section 2.1.2 below. The Offeror should put as much proposal material as possible on each CD-ROM, keeping the portions of the proposal that contain pricing information on separate CD-
ROM(s) from the portions of the proposal that do not contain pricing information. For this solicitation, Annex B
(Small Business Subcontracting Plan)); Volume 4 Price; and Volume 5 Contract Administration contain price information and should be delivered on separate CD-ROM(s) from the remainder of the proposal. Gen Inst Table 2
(Proposal Structure) identifies the number of sets of CD-ROMs that contain its proposal the Offeror should submit.
The first set of CD-ROM disks should be marked "Original." Subsequent sets of CD-ROM disks should be marked
"Copy 1, Copy 2, etc.” The sets of CD-ROM disks should be clearly marked with the Offeror's name and address, the point of contact's name and phone number, date of submittal and proposal volumes contained therein. The
Offeror is responsible for ensuring electronic proposals are virus free in accordance with Section 2.1.4. If a discrepancy exists between the original paper copy of the proposal and the disk copy, the disk copy shall take precedence.
2.1.2 Operating System and Applications
The proposals will be accessed utilizing the Microsoft Windows 7 Professional Operating System. The Offeror shall submit two identical proposals in separate, electronic versions: one version in Portable Document Format (.pdf) and one version in Microsoft Office 2010 Applications (Microsoft Word, Microsoft Excel, Microsoft PowerPoint, and
Microsoft Project). The .pdf document must be fully searchable. The Offeror is responsible for ensuring that the
.pdf and the appropriate Microsoft Office 2010 applications versions contain identical information. The US
Government shall have the discretion to use the information in either version, and shall not be responsible for any differences in content between the two proposal formats submitted by the Offeror. Use of other application software for submission of proposals is prohibited except where specific instructions for non- PDF or Office 2010 applications are provided.
2.1.3 Hyperlinks
Offerors may use hyperlinks within and among proposal Volumes 1 through 3.There shall be no links from Volumes
1 through 3 into Volume 4. However, in Volume 4, links to other Volumes may be used.
2.1.4 Virus Free Electronic Submission
Offerors are responsible for ensuring that its electronic proposal is virus free. The Offeror shall certify, in its proposal cover letter, that all electronic proposal information has been checked and is virus free, and specify the software, version, and virus definition used to check the data. With each subsequent submission of proposal information (e.g., responses to Evaluation Notices, Final Proposal Revisions, etc.), the Offeror shall ensure and certify that its files are virus free.
2.1.5 Multimedia
The Offeror should not embed sound or video (e.g., MPEG) files within the proposal submission.
2.1.6 Graphics
Large files require greater computer system resources and are discouraged. The Offeror is encouraged to:
a. Simplify the color palette used in creating figures;
b. Minimize size of graphics files; and
c. Avoid scanned images.
2.1.7 Evaluation Hardware
The source selection facility uses the following type workstation computer systems and printers.
ITEM EQUIPMENT
Workstations Intel® Core ™ Duo CPU or better
2.94 GB RAM
CD-ROM Drive
Windows 7 Operating System
Network Printers Xerox Phaser 6350DP PS
2.1.8 File Naming Conventions
There is no limit to the number of files that may be submitted. However, unless otherwise stated, it is preferable that each volume, book, or annex not be broken up into multiple electronic files. Valid extensions for files using their associated applications follow:
Type of Application/Files Valid Extensions
Portable Document Files .pdf
Microsoft Word documents .docx
Microsoft Excel documents .xlsx
Microsoft Power Point .pptx
Microsoft Project .mpp
Files should have the following naming convention ("#" represents the sequential numbering of files and the suffix is for illustration, and may be .pdf, .docx, .xlsx, .pptx, or .mpp). For electronic file submissions (e.g. proposal volumes, annexes, appendices, enclosures) the Offeror should follow the basic structure of the file naming convention suggested in Table Gen Inst 1 (Offeror Electronic File Naming Convention). Offeror’s shall keep the file name as short as possible (under 40 characters) so that it is accessible on US Government share drives. The
Offeror shall ensure that the electronically submitted file names are directly traceable to hard copy submittals. In general, the Offeror should provide each binder (e.g. volume, book, or annex) as one separate file (i.e. do not provide each section/paragraph as separate files).
Table Gen Inst 1 Offeror Electronic File Naming Convention
VOLUME
NUMBER
TITLE FILE NAMING
CONVENTION
1 EXECUTIVE SUMMARY Vol 1 ES#.pdf and Vol 1
ES#.docx
Table ES-1 Offeror Summary
Table ES-2 Relevant Contract Summary
Vol 1 ES Tables.xlsx and
Vol 1 ES Tables.pdf
2 TECHNICAL Vol 2 Tech#.pdf and Vol 2
Tech#.docx
Tech#.mpp
General
Instructions
Table Gen Inst 4 Cross Reference Matrix (CRM) GenInst CRM.xlsx and
GenInst CRM.pdf
3 PAST PERFORMANCE Vol 3 PP#.pdf and Vol
3PP#.docx
Table PP-1 Past Performance Contract Data Vol 3 PP-1 PP Con Data.pdf and Vol 3 PP-1 PP Con
Data.xlsx
Release of Adverse Past Performance Authorization Letters;
and/or Past Performance Point of Contact Information for
Principal Subcontractors and Joint Venture Team Members
Vol 3 Rel Ad PP Ltr#.pdf and Vol 3Rel Ad PP Ltr
#.docx; and/or PP POC
Info#.pdf and PP POC
Info#.docx
4 PRICE Vol 4Price#.pdf and Vol 4
Price#.docx
Unit Price Matrix Vol 4 Unit Price Matrix.xlsx
Draft CSDR Plan Vol 4CSDR.xlsx
5 CONTRACT ADMINISTRATION (Excluding Model
Contract which is to be provided under a separate file name.)
Vol 5 CA#.pdf and Vol 5
CA#.docx
Model Contract Vol 5 MC.pdf and
Vol 5 MC.docx
ANNEXES
Annex A Quality Assurance Program Plan Ann A QAPP.pdf and Ann
A QAPP.docx
Annex B Small Business Subcontracting Plan Ann B SBG SBSP.pdf and
Ann B SBG SBSP.docx
Annex C Final Versions of Previous SOW/PWS for Past Performance Ann C Previous
SOWPWS#.pdf and Ann C
Previous SOWPWSs #.docx
Please note: The Offeror should provide both a .pdf and .docx version if they are available. If not, a searchable .pdf version only is acceptable.
3.0 PROPOSAL CONTENT AND VOLUMES
The Offeror shall present its proposal information in a manner that facilitates a one for one comparison between the information presented and these proposal instructions. Proposal information must be structured such that its paragraph numbers/letters correspond to the proposal instructions paragraph numbers/letters, although the Offeror may add lower tier sub paragraphs.
Each volume and annex of the proposal shall be submitted as original and additional hard and electronic copies as specified in Table Gen Inst 2 (Proposal Structure). The Offeror shall submit all paper and electronic copies of the proposal to the address provided in section 4.0 (Proposal Packaging and Submission). Page limits for each volume, if any, are also specified in Table Gen Inst 2 (Proposal Structure). The title and table of contents pages are not included in the page limits.
Information submitted as an Annex to a particular proposal volume could include manuals, specifications, plans, procedures, and company policies, as well as other information requested in Section B Specific Instructions and do not count towards the page count limit. Additionally, the individual subcontracting reports for the past performance volume are not included in the page limit.
Table Gen Inst 2 Proposal Structure
VOLUME
NUMBER
VOLUME TITLE PAGE LIMIT
HARD
COPIES
REQUIRED
ELECTRONIC
COPIES (CD-
ROM DISKS)
1 EXECUTIVE SUMMARY
1 Original/
6 Copies
1 Original/
2 Copies
2 TECHNICAL
100 1 Original/
6 Copies
1 Original /
2 Copies
3 PAST PERFORMANCE
50 1 Original/
6 Copies
1 Original /
2 Copies
4 PRICE As Needed 1 Original/
6 Copies
1 Original /
2 Copies
CONTRACT
ADMINISTRATION
As Needed
1 Original/
4 Copies
1 Original /
2 Copies
ANNEXES
Annex A Quality Assurance Program Plan As Needed 1 Original/
6 Copies
1 Original/
2 Copies
Annex B Small Business Subcontracting
Plan As Needed
1 Original/
6 Copies
1 Original /
2 Copies
Annex C Final Versions of Previous
SOW/PWSs for Past Performance As Needed
1 Original/
6 Copies
1 Original /
2 Copies
Each binder must contain the following information:
a. Cover and title page;
b. Title of proposal and proposal number as applicable;
c. Offeror’s name, address, CAGE/NCAGE and POC;
d. Solicitation number;
e. Proposal volume/book/annex number;
f. Copy number;
g. Table of Contents (The table of contents must provide sufficient detail to easily locate important elements). At a minimum it must include the paragraphs identified in the Cross Reference Matrix (CRM); and
h. Tabs and dividers.
Catalog Card - Each volume must contain an 8 1/2" x 11" Catalog Card containing the information required for the cover and title page. The back of the card must be formatted with three columns entitled "Name", "Date Out", and
"Date In". This card must be removable from the back of each binder.
The following, Table Gen Inst 3 (Section L List of Attachments) lists the attachments provided to the Offeror with
Section L, to assist with proposal development.
Table Gen Inst 3 Section L List of Attachments
ATTACHMENT NUMBER ELECTRONIC FILE TITLE ATTACHMENT NAME
L-1 Vol 1 ES Tables Table ES-1 Offeror Summary and
Table ES-2 Relevant Contract
Summary
L-2 Vol 3 PPQ Past Performance Questionnaire
L-3 Vol 3 PP-1 PP Contract Data Table PP-1 Past Performance
Contract Data
L-4 Vol 4 Unit Price Matrix Unit Price Matrix
L-5 Vol 4 CSDR.xlsx Draft CSDR Plan
A CRM, Table Gen Inst 4, is included to help the Offeror develop its proposal and to ensure traceability of Section L paragraphs to the requirements. The Offeror’s CRM may be identical to the one provided or revised to add information. The Offeror’s CRM shall cross-reference its proposal volumes, paragraph numbers, and pages to specific solicitation requirements identified within the table, as well as other parts of the proposal that contain relevant information.
Table Gen Inst 4 Cross Reference Matrix
Section L –
Proposal
Instructions
Volume or
Paragraph
Numbers
Section L - Proposal
Instructions Volume or
Paragraph Title
Section M
SOW
Volume
Page
Reference
Paragraph
Reference
Volume 2.0 Technical II.A N/A
2.1 Management Support
Approach
II.A In support of all paragraphs
2.2 Maintenance Approach II.A 3.1/ 3.2/ 3.3.2/
3.3.4/ 3.4/ 3.5/
3.6/ 3.7/ 3.8
2.3 Engineering II.A 3.7
Volume 3.0 Past Performance II.B N/A
Volume 4.0 Price II.C N/A
No price information, (e.g., Dollar Values and/or Hourly Rates) shall be included in any volume other than
Annex B (Small Business Subcontracting Plan); Volume 4(Price); or Volume 5 (Contract Administration).
4.0 PROPOSAL PACKAGING AND SUBMISSION
For proposal validity information, see Section A (Solicitation/Contract Form).
Clearly mark all packages with the solicitation number. The submission date for all Volumes shall be no later than the date and time specified in Block 9 of Standard Form 33 (Solicitation, Offer, and Award) of the RFP (Caution to
Offerors: see FAR 52.215-1 regarding late proposals). However it is requested that Volume 1 (Executive
Summary), Table ES-1 (Offeror’s Summary); Volume 1 (Executive Summary), Table ES-2 (Relevant Contract
Summary); Volume 3 (Past Performance), Table PP-1 (Past Performance Contract Data); and Annex C (Final
Versions of Previous SOW/PWS) shall be submitted two weeks prior to the submission date/time specified on
Standard Form 33 (Solicitation, Offer, and Award Block 9). Failure to submit Volume 3 (Past Performance), Table
PP-1 (Past Performance Contract Data); and Annex C (Final Versions of Previous SOW/PWS) by the date/time established for receipt will cause the proposal submission to be rejected in its entirety. Offerors that desire to update information submitted prior to the submission date/time specified on Standard Form 33 Standard Form 33
(Solicitation, Offer, and Award Block 9) may do so any time up to the date/time specified.
Proposals shall be submitted via either the United States Postal Service, a commercial carrier, or preferably hand delivered to the address provided below. Initial proposals shall not be submitted by facsimile or electronically via email.
PROPOSAL PACKAGING:
All proposals must be UNCLASSIFIED.
The Offerors shall package the proposal volumes in cartons or equivalent packaging containers in the most efficient manner possible grouping like volumes to the maximum extent possible. Each box should identify its contents by including a packing slip detailing each volume/book number and title, and copy number. Each carton should be double wrapped. The outside of the carton should be plain and the inside carton shall be stamped or marked ― For Official Use Only; and Source Selection Information – See FAR-2.101 and 3.104, marked for the intended recipient as identified below, and should only contain those proposals intended for that person. Each container shall be single person portable. The original set of proposals should be marked for
NAVAIR PCO, Melanie Bateman, AIR- 2.2.3.1. The original set shall include hard copies of all original proposal volumes, all proposal volumes on CD-ROM, a completed and original signed Standard Form 33
(Solicitation, Offer, and Award), acknowledgement of all solicitation amendments (if applicable) and
Representations, Certifications and Other Statements of Offerors or Respondents (Section K of this RFP), and other applicable fill-ins. Note: Any documents which contain cost data shall be on a separate disk(s) from the other disks.
Outer wrapper:
NAVAIR
DEPARTMENT OF THE NAVY
NAVAL AIR SYSTEMS COMMAND (HQ)
F/A-18 AIRCRAFT CONTRACTS BRANCH
ATTN: MELANIE BATEMAN, PCO, CODE AIR 2.2.3.1
47394 BUSE ROAD, BLDG 2455, ROOM 103
PATUXENT RIVER, MD 20670-1547
SOLICITATION NUMBER: N00019-15-R-0090
Inner wrapper:
NAVAIR
DEPARTMENT OF THE NAVY
NAVAL AIR SYSTEMS COMMAND (HQ)
F/A-18 AIRCRAFT CONTRACTS BRANCH
ATTN: MELANIE BATEMAN, PCO, CODE AIR 2.2.3.1
47394 BUSE ROAD, BLDG 2455, ROOM 103
PATUXENT RIVER, MD 20670-1547
SOLICITATION NUMBER: N00019-15-R-0090
5.0 CHANGES TO SOLICITATION
All amendments to this solicitation will be posted at https://www.fbo.gov/
Search the database for the solicitation number: N00019-15-R-0090
6.0 TECHNICAL LIBRARY
A Technical Library of information directly related to the requirements of the F/A-18 A-D Contractor Depot Level
Maintenance Requirements solicitation is available to all Offerors intending to submit a proposal.
The F/A-18 DLM N00019-15-R-0090 Technical Library is hosted on a Department of Defense (DoD) Information
System. There will be two (2) Technical Libraries made available; one (1) available to all Offerors and one (1) restricted to United States Contractors only (no foreign national access allowed).
Access to the libraries requires a DoD Common Access Card (CAC) or External Certification Authority (ECA) certificate. An ECA certificate can be obtained from IdenTrust, Inc., Operational Research Consultants, Inc. (ORC) or VeriSign, Inc. Additional information on obtaining an ECA certificate is available at http://iase.disa.mil/pki/eca/index.html
The link to access both technical libraries is: https://pma265.navair.navy.mil/
Once a Technical Library access request is received, recorded, and validated by the US Government, notification of access will be provided via e-mail.
PART B SPECIFIC INSTRUCTIONS
1.0 VOLUME 1 –EXECUTIVE SUMMARY
Note: This volume shall not contain any reference to price aspects of the offer.
The following is a list of Attachments that the Offeror shall utilize to provide information for this volume:
L-1 Executive Summary Tables (ES-1 (Offeror Summary) and ES-2 (Relevant Contract Summary))
The purpose of the Executive Summary is to provide the US Government with an overview of the Offeror’s entire proposal, excluding price. Each section within the Executive Summary shall contain the salient points contained in each of the proposal volumes. In addition, this volume should be used by the Offeror to identify and highlight significant features of its proposal. The Executive Summary volume should be divided into the areas outlined below:
a. Offeror Summary Table
(1) The Offeror shall complete Table ES-1 (Offeror Summary), provided in L-1 (Executive Summary Tables), according to the instructions within the attachment, and submit it within this section and as a separate electronic file. This table summarizes the Offeror and its entities’ (the prime contractor, JV, JV Team
Members, any principal subcontractor, critical team members and any corporate parent, division, subsidiary, or affiliate) proposed type and level of work, indicating a commitment to that effort during contract performance. Offerors are advised that in order to demonstrate work commitment, each entity identified in Table ES-1 (Offeror Summary) must be identified in the Price Volume and associated with a dollar value commensurate with the Percent of Total Proposed Price identified in Table ES-1 (Offeror
Summary). Therefore, this table must be a reflection of what is proposed in the Price Volume.
(2) The Offeror shall provide a written explanation if multiple CAGE/NCAGE codes/DUNS for the same physical location are provided in Table ES-1 (Offeror Summary). The written explanation shall detail the distinct roles and responsibilities for entities with different CAGE/NCAGE codes/DUNs at the same physical location for where the work is being performed or from where the work is being directed. The description shall include all changes in the organization as a result of a corporate acquisition, reorganization, merger, or other administrative reason. However, all CAGE/NCAGE codes must be appropriately identified in the table to be considered.
Note: Place of Performance for this solicitation pertains to the physical location of the prime, all principal subcontractors, critical team members and JV team members who will perform the work.
http://iase.disa.mil/pki/eca/index.html https://pma265.navair.navy.mil/
ES-1 Offeror Summary Table
Offeror:
Entity Name Place of
Performance
CAGE/NCAGE Codes/
DUNs
Roles &
Responsibilities with Work
Description
% of Total Proposed Price
Total
Proposed
Price
(must add up to 100%)
100%
b. Relevant Contract Summary Table
The Offeror shall complete the Table ES-2 (Relevant Contract Summary) provided in L-1 (Executive Summary
Tables), for all contracts proposed as relevant for Past Performance for the relevant entities. Complete the table according to the instructions within the attachment and submit it within this section and as a separate electronic file. The contract references designated in Table ES-2 (Relevant Contract Summary) shall be used in completing Volume 3, Table PP-1 (Past Performance Contract Data).
ES-2 Relevant Contract Summary Table
Offeror: Referenced in:
Entity Name Contract
Reference
Contract
Number
Contract
Type
Contract
Title
Volume 3
(PP)
Prime or Joint Venture
Company
P1
P2
Pn
Corporate Parent, Division, Subsidiary, or
Affiliate (where applicable)
C1
C2
Cn
JV team member A
(where applicable)
T1
T2
T3
JV team member N
(where applicable)
T4
Tn
Critical Team
Member/Principal
Subcontractor A
S1
S2
Subcontractor B
S3
S4
Subcontractor N
S5
Sn
c. Technical
The Offeror shall provide a summary of the effort and identify how its approach addresses the requirements of this solicitation as well as the salient features of the Offeror’s technical approach.
d. Past Performance (PP)
The Offeror shall provide a summary of the Prime’s, and its relevant entities’ past performance and systemic improvements which pertains to the tasks required by this solicitation.
e. Contract Administration
The Offeror shall provide a summary of any exceptions or deviations, and proposed Section H clauses addressed in Volume 5 (Contract Administration).
2.0 VOLUME 2 - TECHNICAL
Note: This volume shall not contain any reference to price aspects of the proposal.
The following is a list of Section L Attachments and a General Instruction Table that the Offeror shall utilize to provide information for this volume:
Table Gen Ins 4 Cross Reference Matrix (CRM)
Please provide a printed copy of the Offeror’s CRM or Table Gen Inst 4 (Cross Reference Matrix), as the first page of this volume. The Offeror’s CRM may be identical to the one provided or revised to add information.
The Offeror shall address the following elements in its proposal:
Note: (*) denotes an element where specific emphasis will be placed.
2.1 Management Support Approach
The Offeror shall:
a. Provide an overview of the management approach, baseline assumptions and resource management strategies to perform the requirements of this solicitation to include identifying risks with associated mitigations.
b. Describe the management approach for each principal subcontractor(s) and/or critical team member utilized to perform the requirements of this solicitation and identify risks and associated mitigations. Identify what portion of the contract, or specific tasks, shall be passed to the principal subcontractor(s) and/or critical team member to ensure compliance with the contract.
c. Describe the lines of authority and the levels of responsibility of management personnel proposed for this solicitation. Provide a detailed organization chart that clearly differentiates between management and direct personnel, and highlight positions filled by principal subcontractors and/or critical team member.
d. Provide a high level organizational chart that clearly reflects the position of this program within the structure of the corporate organization.
e. Submit a detailed transition plan and an associated narrative, in PDF and Microsoft project format from contract award to receipt of first aircraft that describes critical tasks and timelines associated with supporting aircraft inductions. The detailed plan shall include: Time phased manning including required certifications/qualifications; Access to US Government IT systems; Integration of ground operations;
Security/safeguarding; Fuel services; and Support Equipment.
f. Small Business Utilization Strategy
1) All Offerors (Large and Small Businesses) shall address their strategies for utilizing SB Concerns in the performance of this contract, whether as a joint venture, teaming arrangement or subcontractor/vendor.
SB Offerors may meet this requirement using work they perform themselves. For purposes of this solicitation, the term SB Concern shall also include the subcategories of Small Disadvantaged Business
(SDB), Women-Owned SB (WOSB), HUBZone SB (HUBZone), Veteran-Owned SB (VOSB), and
Service-Disabled Veteran-Owned SB (SDVOSB). Each subcategory of SB shall be addressed. This strategy is separate from, but shall be consistent with, the SB Subcontracting Plan, if such a Plan is required.
2) Demonstrate (Large Business only) that its SB Utilization Strategy is consistent with its SB Subcontracting
Plan. If the Offeror is a participant in the DoD Comprehensive Subcontracting Test Program specified in
DFARS 219.7, the Offeror shall describe how SB participation on this contract will contribute to its overall Comprehensive Subcontracting Plan goals.
3) Small Business Subcontracting Plan
Large Business Offerors shall provide a Small Business Subcontracting Plan conforming to the requirements of FAR 19.7 and DFARS 219.7 as part of Annex B. The SB Subcontracting Plan of the successful Offeror will be reviewed and approved by the PCO prior to contract award. See FAR
19.702(a)(1) Statutory requirements, regarding failure of the apparent successful Offeror to negotiate and submit a SB Subcontracting Plan or submit a Comprehensive SB Subcontracting Plan acceptable to the
Contracting Officer. The successful Offeror’s approved Subcontracting Plan will be incorporated into the contract.
2.2 Maintenance Approach*
a. Using flowcharts and narrative, describe your value stream/process flows and timeline in maintenance days per step (to not include number of days for US Government response/actions related to engineering or parts/materials), assuming one (1) eight (8) hour shift , to optimize throughput, from aircraft arrival to departure for the following scenarios, in accordance with the notional induction schedule provided within the Technical
Library:
1. The first FY16 High Flight Hour (HFH) induction with concurrent modifications.
2. Overarching approach to all FY16 - 17 inductions.
b. Provide any risks and associated mitigation strategies. Describe how Continuous Process Improvement (CPI) strategies will be utilized.
c. Describe how aircraft parts/components will be handled from time of aircraft recovery until US Government acceptance of the aircraft.
d. Provide documentation of a DSS facility(s) clearance of SECRET, in good standing, or a plan for obtaining the
DSS facility(s) clearance of SECRET upon contract award.
e. Provide Offeror’s approach to ensure compliance with SOW paragraphs 3.2.3, 3.2.6 and 3.4.1.
f. Describe how the Offeror will comply with SOW paragraph 3.1.3.
g. Provide an internal hangar spotting diagram for FY16 - 17 aircraft to be inducted in accordance with the notional induction schedule provided within the Technical Library. Provide maximum number of aircraft that can be hangared to include space(s) allocated for aircraft parts/components and GFE.
h. In the event the Offeror does not have a facility at the time of proposal submission, and/or cannot currently provide any of the sub-elements (d) through (g), the Offeror shall provide a detailed plan, which shall include all subsidiary plans and supporting documentation describing how the Offeror will meet the requirements upon contract award.
i. Provide a Quality Assurance Program Plan and identify any major challenges and inherent risks per SOW
Paragraphs 3.3.1 and 3.3.2. as Annex A.
j. Demonstrate knowledge of applicable export control requirements by presenting an effective export compliance strategy that identifies applicable export control requirements associated with the scope of work covered under this solicitation, and the approach to address them.
2.3 Engineering
a. Describe the Offeror’s approach to providing liaison engineering services IAW SOW paragraph 3.7.2.
b. The Offeror shall provide a repair disposition for each non-conformance provided below. The Offeror shall also describe its approach, policies, processes and analyses utilized for each repair disposition:
1. F/A-18C, Lot 17, Left Hand, Upper Outboard Longeron, corrosion and small cracks (not to exceed
0.050 inches) found at fastener holes under door 41 (any of the holes);
2. F/A-18C, Lot 18, Right Hand, Vertical Stab spars and ribs under actuator cover found with corrosion and small cracks (not to exceed 0.050 inches) at fastener holes under door 100/124 (any of the holes); and
3. F/A-18D, Lot 14, delaminations (2.0 inches in length, random depths) at fastener holes in graphite / epoxy wing torque box skins common to the fold rib (any of the holes, upper or lower skin).
3.0 VOLUME 3 – PAST PERFORMANCE
Note: This volume shall not contain any reference to the price aspects of the proposal.
The following is a list of L Attachments that the Offeror shall utilize to provide information for this volume:
L-2 Past Performance Questionnaire (PPQ)
L-3 Table PP-1 Past Performance Contract Data
For this volume, the Offeror shall identify relevant contracts, or those portions of a relevant contract, whose performance is within five years of the proposal due date and contains efforts similar to those efforts (e.g., end product or…