MDVL042061 Statement of Work - Addendum Number 1.pdf
PDF 104 KB Posted
- Solicitation number
- W50S7J23B0001
- Issued by
-
Department of the Army National Guard
About this file
This solicitation seeks fixed-price construction services to repair fire suppression systems in three buildings at the 186th Air Refueling Wing in Meridian, Mississippi. Offerors must perform work in accordance with attached construction plans, statements of work, technical specifications, and an addendum. Services include removing detection, releasing, and interface equipment and modifying sequence of operations and sprinkler densities. The North American Industry Classification System code for this work is 236220. This opportunity is a 100% total small business set-aside for qualified small businesses with average annual revenues under $45 million for the previous three years. The period of performance is to be determined. The pre-bid conference will be held on May 16, 2023 and bids are due by June 1, 2023. The Department of the Army National Guard is the contracting agency.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
186TH AIR REFUELING WING
KEY FIELD, MERIDIAN, MS
PROJECT NUMBER MDVL042061
REPAIR FIRE SUPPRESSION SYSTEMS IN BLDGS 150, 151, AND 160
20 JANUARY 2023
ADDENDUM #1
STATEMENT OF WORK
1.0 SCOPE & PURPOSE. This addendum to the Statement of Work (SOW) provides updated requirements for the referenced project.
2.0 APPLICABLE DOCUMENTS.
2.1 Original project bid documents.
3.0 REQUIREMENTS.
3.1 DELETE all Det-tronics IRRR detection and Det-tronics RSFACU panel (i.e. releasing panel) and all associated conduit, wire, battery cabinet, batteries, etc. Note: this system was required to be installed in separate conduit, so all conduit and wiring would be removed with this system.
3.2 DELETE RSFACU redundant transceiver (as necessary). Note: this includes cabling, conduit, wiring, and antenna.
3.3 DELETE all FACU / RSFACU interface points (i.e. conduit, wiring, modules and terminal cabinets).
3.4 MODIFY sequence of operations to NOT include IRRR detection or RSFACU signals to
FACU.
3.5 REVISE sprinkler density in Bldg 150 (Sheet 01F-002) and Bldg 160 (Sheet 03F-002) to 0.20 gallons per minute per foot over 5,000 square feet.
3.6 REVISE Specification Section 21 13 13.00 10 Wet Pipe Sprinkler System, Fire Protection:
3.6.1 §1.1 References - DELETE the following reference: “FM Data Sheet 3-26 Fire
Protection for Nonstorage Occupancies.”
3.6.2 §1.2.1 Hydraulic Design - DELETE the following statement: “Provide automatic sprinkler systems in hangars meeting the hydraulic requirements of FM Data Sheet 3-26 per Sundown Policy. Increase system remote design area by 30% for sloped ceilings that exceed a slope of 2 in 12.”
4.0 WORK SCHEDULE. No change.
5.0 PERIOD OF PERFORMANCE. No change.
6.0 WARRANTY. No change.
7.0 DEMOLISHED MATERIALS. No change.
8.0 SAFETY. No change.