About this file
This is a design-build project document for fire alarm and security system replacement at two buildings (B911 and B98) at McClellan VA Medical Center in McClellan Park, California (5342 Dudley Blvd). Building 911, a 63,000 square-foot former shopping center currently used as a printing center, is served by an obsolete Notifier DR-500 conventional fire alarm panel with 12 of 16 zones in use. Building 98, a 71,000 square-foot outpatient clinic, has an existing Notifier NFS2-3030 intelligent fire alarm control panel with 2 signaling line circuit loops and 19 notification appliance circuit loops. The project scope includes complete replacement of fire alarm systems in both buildings using Mircom as the basis of design, installation of new Avigilon security cameras with network video recorders in Building 911 Room 49 and Building 98 Room 2T09B, and installation of new Bosch intrusion detection systems with door contact alarms, motion detection devices, and control panels in Building 911 Room 49 and Building 98 Room 1A20B. Additional architectural work includes demolition of an existing brick wall outside the kitchen area in Building 911 for security purposes, repurposing of the existing OPS room as the new intrusion alarm control room with replacement of the door using a new metal door assembly, removal of existing freezer/cooler to facilitate installation of new metal door, and placement of new concrete curb and paving at the former freezer/cooler location. The design must conform to the VA Fire Protection Manual (latest edition), Physical Security & Resiliency Design Manual (latest edition), VA directives, and applicable codes. Required design submissions include 30%, 65%, 90%, and 100% submittals for VA review, with 100% submission stamped by California-licensed engineers. The project number is 612A4-26-051, and it is managed by New England Engineering, Inc. (30 Turnpike Road, Suite 1, Southborough, MA 01772) in collaboration with the VA Office of Construction and Facilities Management.
The drawings include comprehensive demolition plans for both buildings showing removal of existing fire alarm devices (pull stations, smoke detectors, strobes, bells), architectural elements (brick wall, doors, freezer/cooler), and ceiling sections for accessibility. New work plans detail installation locations for addressable fire alarm devices, security cameras with motion intrusion detection, door contacts, and supporting infrastructure. Fire alarm riser diagrams illustrate the transition from the existing conventional and intelligent systems to a new addressable Mircom system with integrated voice alarm and evacuation capabilities. The security system plans identify wall and ceiling-mounted camera locations, motion detection device placement, and door contact locations for exterior doors, overhead doors, and roof hatches. Existing conduits may be reused if they meet minimum standards of 3/4-inch diameter, all-metal construction, and uniform red marking. All new fire alarm wiring must be installed in separate raceway, with conduits painted red and sized to comply with voltage drop calculations meeting VA standards and NFPA code requirements. The system will reuse the existing Digital Alarm Communicator Transmitter (DACT) for central station notification and will maintain sprinkler system central station supervision throughout construction per NFPA 241 requirements.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
N/A
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/2
/2
:1
:3
P
M
COVER SHEET
PS MC G-001
98 & 911
N
BRIDGING DOCUMENTS
U.S. Department of Veterans Affairs
Project Name: DESIGN BUILD B911 AND B98 FIRE ALARM REPLACEMENT AND SECURITY UPGRADES Project Address: MCCLELLAN PARK, CA, 95652
B911
B98
DRAWING INDEX
G-001 COVER SHEET
G-002 BUILDING 911 - EXISTING CONDITION PHOTOS- SOUTH
G-003 BUILDING 911 - EXISTING CONDITION PHOTOS
CD-101 BUILDING 911 - CIVIL - DEMOLITION PLAN SOUTH
C-101 BUILDING 911 - CIVIL - NEW WORK PLAN - SOUTH
AD-101 BUILDING 911 - GROUND FLOOR DEMOLITION PLAN - NORTH
AD-102 BUILDING 911 - GROUND FLOOR DEMOLITION PLAN - SOUTH
AH-101 BUILDING 911 - GROUND FLOOR - NEW WORK PLAN - NORTH
AH-102 BUILDING 911 - GROUND FLOOR - NEW WORK PLAN - SOUTH
AD-201 BUILDING 911 - GROUND FLOOR CEILING DEMOLITION PLAN - NORTH
AD-202 BUILDING 911 - GROUND FLOOR CEILING DEMOLITION PLAN - SOUTH
AD-301 BUILDING 98 - FIRST FLOOR DEMOLITION PLAN
AD-302 BUILDING 98 - SECOND FLOOR DEMOLITION PLAN
FA-000 FIRE ALARM - SYMBOLS, NOTES, AND DETAILS
FAD-100 BUILDING 911 FIRE ALARM DEMOLITION - GROUND FLOOR REMOVALS PLAN - NORTH
FAD-101 BUILDING 911 FIRE ALARM DEMOLITION - GROUND FLOOR REMOVALS PLAN - SOUTH
FAD-200 BUILDING 911 FIRE ALARM DEMOLITION - MEZZANINE REMOVALS PLANS
FAD-300 BUILDING 911 FIRE ALARM DEMOLITION - EXISTING FIRE ALARM RISER DIAGRAM
FAD-400 BUILDING 98 FIRE ALARM DEMOLITION - BASEMENT REMOVALS
FAD-401 BUILDING 98 FIRE ALARM DEMOLITION - FIRST FLOOR REMOVALS
FAD-402 BUILDING 98 FIRE ALARM DEMOLITION - SECOND FLOOR REMOVALS
FAD-500 BUILDING 98 FIRE ALARM DEMOLITION - EXISTING FIRE ALARM RISER DIAGRAM
FA-100 BUILDING 911 FIRE ALARM - GROUND FLOOR NEW WORK PLAN - NORTH
FA-101 BUILDING 911 FIRE ALARM - GROUND FLOOR NEW WORK PLAN - SOUTH
FA-200 BUILDING 911 FIRE ALARM - MEZZANINE NEW WORK PLANS
FA-300 BUILDING 911 FIRE ALARM - NEW FIRE ALARM RISER DIAGRAM
FA-400 BUILDING 98 FIRE ALARM NEW WORK - BASEMENT
FA-401 BUILDING 98 FIRE ALARM NEW WORK - FIRST FLOOR
FA-402 BUILDING 98 FIRE ALARM NEW WORK - SECOND FLOOR
FA-500 BUILDING 98 FIRE ALARM - NEW FIRE ALARM RISER DIAGRAM
ESD-202 BUILDING 98 SECURITY PLAN - SECOND FLOOR - DEMOLITION
ES-100 BUILDING 911 SECURITY PLAN GROUND FLOOR NEW WORK - NORTH
ES-101 BUILDING 911 SECURITY PLAN - GROUND FLOOR NEW WORK - SOUTH
ES-200 BUILDING 98 SECURITY PLAN - BASEMENT - NEW WORK
ES-201 BUILDING 98 SECURITY PLAN - FIRST FLOOR - NEW WORK
ES-202 BUILDING 98 SECURITY PLAN - SECOND FLOOR - NEW WORK
THE DESIGN BUILD CONTRACTOR SHALL REPLACE THE EXISTING FIRE ALARM SYSTEMS AT BUILDING 98 AND BUILDING 911 AT THE MCCLELLAN VAMC. IN ADDITION THE DESIGN BUILD CONTRACTOR SHALL
UPGRADE THE EXISTING SECURITY CAMERA AND INTRUSION SYSTEMS.
BUILDING 911 IS APPROXIMATELY 63,000 SQUARE FEET AND IS CURRENTLY USED AS A PRINTING CENTER (FORMER SHOPPING CENTER). BUILDING 98 IS APPROXIMATELY 71,000 SQUARE FEET AND IS CURRENTLY USED AS AN OUTPATIENT CLINIC. THE PROJECT IS LOCATED AT THE MCCLELLAN VA
CAMPUS, LOCATED AT 5342 DUDLEY BLVD, MCCLELLAN PARK, CA 95652.
BUILDING 911 IS SERVED BY AN EXISTING NOTIFIER DR-500 CONVENTIONAL FIRE ALARM CONTROL
PANEL WHERE 12 OUT OF 16 ZONES ARE BEING USED.
A. THE NOTIFIER SYSTEM 500 (CPU
500, DR
500 DRESS PANEL, ETC.) IS A 1990S
CONVENTIONAL PANEL FAMILY AND IS NO LONGER A CURRENT PRODUCT IN NOTIFIER’S
CATALOG.
B. PARTS OF THE LIFE SAFETY SYSTEM THAT HAVE BEEN DISCONNECTED AND NO LONGER IN
USE SUCH AS KITCHEN HOOD ANSUL CHEMICAL SUPPRESSION ADDS TO THE DEPRECIATION
OF THE EXISTING FIRE ALARM SYSTEM.
BUILDING 98 IS SERVED BY AN EXISTING NOTIFIER NFS2-3030 INTELLIGENT FIRE ALARM CONTROL PANEL WITH 2 SIGNALING LINE CIRCUIT (SLC) LOOPS, 19 NOTIFICATION APPLIANCE CIRCUIT (NAC)
LOOPS, AND SUPPLEMENTED BY 2 REMOTE POWER SUPPLY NAC EXPANSION MODULES.
THE PROJECT SCOPE INCLUDES THE TEMPORARY REMOVAL OF SELECT CEILING SECTIONS TO
FACILITATE DEMOLITION ACTIVITIES AND THE INSTALLATION OF A NEW FIRE ALARM SYSTEM, THE INSTALLATION OF NEW SECURITY CAMERAS AND INTRUSION DETECTION SYSTEMS. FOR THE VIDEO SECURITY CAMERAS THE INTENT IS TO REPLACE THE CURRENT CAMERAS, AND INSTALL ADDITIONAL
CAMERAS THAT ARE COMPATIBLE WITH THE CENTRAL STATION SYSTEM . FOR THE INTRUSION
DETECTION SYSTEM, THE INTENT IS TO INSTALL DOOR CONTACT ALARMS AND MOTION DETECTORS
THAT REPORT TO CENTRAL STATION SYSTEM.
FOR BUILDING 911, THE SCOPE ALSO INCLUDES DEMOLITION OF THE EXISTING BRICK WALL LOCATED OUTSIDE THE KITCHEN AREA FOR SECURITY PURPOSES. THE EXISTING BRICK WALL CREATES A VISUAL OBSTRUCTION THAT COULD CONCEAL INDIVIDUALS ATTEMPTING TO GAIN UNAUTHORIZED ACCESS TO THE KITCHEN. REMOVAL OF THIS WALL WILL IMPROVE VISIBILITY AND ENHANCE OVERALL SITE SECURITY. THE EXISTING OPS ROOM WILL BE REPURPOSED TO SERVE AS THE NEW INTRUSION
ALARM CONTROL ROOM. THE CURRENT DOOR WILL BE REPLACED WITH A NEW METAL DOOR
ASSEMBLY TO PROVIDE IMPROVED SECURITY AND CONTROLLED ACCESS. THE SCOPE FURTHER
INCLUDES REMOVAL OF THE EXISTING FREEZER/COOLER TO FACILITATE INSTALLATION OF A NEW METAL DOOR. NEW CONCRETE CURB WILL BE PLACED TO PROVIDE A PLATFORM/LANDING AT THE
FORMER LOCATION OF THE FREEZER/COOLER.
MIRCOM IS SELECTED AS THE BASIS OF DESIGN FOR THE NEW FIRE ALARM (FA) SYSTEM. THE NEW
FA SYSTEM NOTED ON THE PLANS IS A ONE-TO-ONE REPLACEMENT WITH THE EXCLUSION OF
REMOVED KITCHEN HOOD ANSUL SYSTEMS AND REUSE OF THE EXISTING DIGITAL ALARM
COMMUNICATOR TRANSMITTER (DACT) TO THE EXISTING CENTRAL STATION SERVICE.
AVIGILON IS SELECTED AS THE BASIS OF DESIGN FOR THE SECURITY CAMERA SYSTEM. THE NEW
SECURITY CAMERA SYSTEM NOTED ON THE PLANS SHALL REPLACE THE EXISTING
MCCLELLAN B911 AND B98 FIRE ALARM REPLACEMENT AND SECURITY UPGRADE
MCCLELLAN VA MEDICAL CENTER 01 00 00 -3 CAMERA SYSTEM AND INSTALL ADDITIONAL CAMERAS.
THE SECURITY CAMERA SYSTEM SHALL INSTALL A NETWORK VIDEO RECORDER IN BUILDING 911 ROOM 49, AND IN BUILDING 98 ROOM 2T09B. THE NETWORK VIDEO RECORDER WILL BE ACCESSIBLE
VIA NETWORK BY MATHER VAMC VA POLICE.
BOSCH IS SELECTED AS THE BASIS OF DESIGN FOR THE INTRUSION DETECTION SYSTEM. THE NEW INTRUSION DETECTION SYSTEM NOTED ON THE PLANS SHALL INSTALL DOOR CONTACT ALARMS ON
EXTERIORS DOORS, OVERHEAD DOORS AND ROOF HATCHES. THE INTRUSION DETECTION SYSTEM
SHALL INSTALL MOTION DETECTION DEVICES IN SPACES NOTED ON THE PLANS. THE NEW INTRUSION DETECTION SYSTEM SHALL INSTALL CONTROL PANELS IN BUILDING 911 ROOM 49 AND IN BUILDING 98
ROOM 1A20B. THE CONTROL PANELS WILL REPORT TO MATHER VAMC VA POLICE VIA CELLULAR
NETWORK.
THE DESIGN SHALL CONFORM TO THE VA FIRE PROTECTION MANUAL (LATEST EDITION), PHYSICAL SECURITY & RESILIENCY DESIGN MANUAL (LATEST EDITION); VA DIRECTIVES AND APPLICABLE CODES. THE REQUIRED DESIGN SUBMISSIONS INCLUDE 30%, 65%, 90% AND 100% FOR VA REVIEW.
THE 100% SUBMISSION SHALL BE STAMPED BY ENGINEERS LICENSED IN CALIFORNIA.
SCOPE OF WORK
Revisions: Date:
UP
G-002
G -0
2 3
G -0
G-002
G -0
G-002
G
-002
G
-0
G-0
10 G -0
G -002
G-002
G-003
G-003
G--003
G-003
G-003
G-003
19G -003
G -0
G-003
22G -003
G-003
G -0
G-003
G-003
G-0
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
N/A
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:5
P M
BUILDING 911 - EXISTING CONDITION PHOTOS-
SOUTH
PS MC G-002
1" = 20'-0"1
B911 ARCHITECTURAL- GROUND FLOOR EXISTING CONDITION
PHOTO 1: EXISTING PULL STATION TO BE REPLACED PHOTO 2: EXISTING PULL STATION AND SMOKE DETECTOR TO BE REPLACED
PS
SD
PHOTO 3: EXISTING PULL STATION AND STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE
DEMOLISHED
PS
PHOTO 7: EXISTING PULL STATION AND STROBE TO BE REPLACED. FIRE ALARM BELL TO BE
DEMOLISHED
PHOTO 4: EXISTING PULL STATION AND STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE
DEMOLISHED
PHOTO 5: EXISTING SMOKE DETECTOR, RAITS AND DSD TO BE REPLACED IN THIS AREA PHOTO 6: EXISTING ANSUL AND PULL STATION TO BE DEMOLISHED IN THIS AREA
PHOTO 8: EXISTING SMOKE DETECTOR TO BE REPLACED. PHOTO 9: EXISTING PULL STATION,STROBE AND SMOKE DETECTOR TO BE REPLCAED. FIRE ALARM
BELL TO BE DEMOLISHED
PHOTO 10: EXISTING SMOKE DETECTORS TO BE REPLACED.
PHOTO 11: EXISTING PULL STATION AND STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE
DEMOLISHED
PHOTO 12: EXISTING PULL STATION TO BE REPLACED
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
N/A
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/2
/2
:1
:3
P
M
BUILDING 911 - EXISTING CONDITION PHOTOS
PS MC G-003
PHOTO 13: EXISTING PULL STATION AND STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE DEMOLISHED PHOTO 14:EXISTING SMOKE DETECTOR TO BE REPLACED PHOTO 15: EXISTING STROBE TO BE REPLACED AND NEW PULL STATION WILL BE PROVIDED.
FIRE ALARM BELL TO BE DEMOLISHED
PHOTO 16: EXISTING PULL STATION AND STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE DEMOLISHED
PHOTO 17: EXISTING PULL STATION, STROBE AND SMOKE DETECTOR TO BE REPLCAED. FIRE ALARM BELL TO BE
DEMOLISHED
PHOTO 18: EXISTING PULL STATION ADD STROBE TO BE REPLCAED. FIRE ALARM BELL TO BE DEMOLISHED PHOTO 19: EXISTING STROBE TO BE REPLACED. FIRE ALARM BELL TO BE DEMOLISHED PHOTO 20: EXISTING FACP TO BE REPLACED. NEW SMOKE DETECTOR WILL BE PROVIDED IN THIS AREA.
PHOTO 21: EXISTING FS, ACV AND TS, TO BE REPLACED PHOTO 22: EXISTING DSD TO BE REPLACED PHOTO 23: EXISTING AUDIO STROBE TO BE REPLACED PHOTO 24: EXISTING BRICK WALL AND DOOR TO BE DEMOLISHED
PHOTO 25: EXISTING CONCRETE CURB TO BE DEMOLISHED AND REPLACED. PHOTO 27: EXISTING FREEZER/COOLER TO BE DEMOLISHED.PHOTO 26: EXISTING FREEZER /COOLER DOOR TO DEMOLISHED. WALL SHALL BE FILLED AND MATCHED THE
EXISTING.
1 2 3 4 5 6 7
E
F
G
H
D.5
F.5
G.2
G.4
G.8
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
LOCATION OF MEZZ. #2
ABOVE
LOCATION OF MEZZ. #3
ABOVE
NORTH
SOUTH
NORTH
SOUTH
COOLER
BARBER
STORE/
LAUNDRY
MEN TLT
WOMEN TLT
CONCESSION
CONCESSION
STORAGE
BEAUTY
SALOON
LAB
FOOD
COURT
OFFICE
VISION
CENTER
VESTIBULE
FOOD
COURT
SEATING
FOOD
COURT
STORAGE
MECH
GNC
SECURITY
OFFICE
VESTIBULE
CLASS SIX
DRESSING
CORRIDOR
ROBIN
HOOD
FRANKS
26ANTHONY'S
TLT
VEST
19COOLER/
FREEZER
KITCHEN
BURGER
KING
EXISTING
CONCRETE PAVING
EXISTING
CONCRETE CURB
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:3
:5
P M
BUILDING 911 - CIVIL - DEMOLITION PLAN
SOUTH
PS MC CD-101
1/8" = 1'-0"1
B911 CIVIL DEMOLITION - SOUTH
KEY NOTES:
1. SECTION OF EXISITING CONCRETE CURB TO BE DEMOLISHED
AFFTECTED BY THE REMOVAL OF THE EXISTING BRICK WALL.
F
G
H
D.5
F.5
G.2
G.4
G.8
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
VESTIBULE
CLASS SIX
STORE/
LAUNDRY
BARBER
COOLER
MEN TLT
WOMEN TLT
BEAUTY
SALOON
STORAGE
VESTIBULE
VISION
CENTER
COOLER/
FREEZER
FOOD
COURT
OFFICE
LAB
KITCHEN
VEST
TLT
BURGER
KING
FOOD
COURT
FOOD
COURT
SEATING
ANTHONY'S
ROBIN
HOOD
CORRIDOR
FRANKS
DRESSING
OFFICE
MECH
STORAGE
GNC
SECURITY
CONCESSION
CONCESSION
EXISTING
CONCRETE PAVING
EXISTING
CONCRETE CURB
NORTH
SOUTH
NORTH
SOUTH
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/2
/2
:0
:1
P
M
BUILDING 911 - CIVIL - NEW WORK PLAN -
SOUTH
PS MC C-101
1/8" = 1'-0"1
B911 CIVIL NEW WORK - SOUTH
KEY NOTES:
1. PROVIDE NEW COCNCRETE CURB AND MATCH THE EXISTING.
2. PROVIDE NEW CONCRETE PAVING AT THE FORMER
FREEZER/COOLER LOCATION TO CREATE A STEP LANDING
AND MATCHING THE EXISTING.
A A
2 3
B B
C C
D D
4 5 6 7
A.5 A.5
B.5 B.5
C.5 C.5
D.5 D.5
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
LOCATION OF MEZZ . #1
ABOVE
NORTH
SOUTH
NORTH
SOUTH
LOCATION OF MEZZ . ABOVE
GEN
MANAGER
DRESSING
SEM
JANITOR
TRAINING
EMP
LOUNGE
VEST
VM RM
SEC
MAINT
TOILET
MPA
MPA OFFICE
OFFICE
OUTDOOR
LIVING
CUSTOMER
SERVICE
TELE
ELEC
Room
OFFICE
PERSONNEL
CORRIDOR
MECH
OPS
RECEPT
HARDLINES
MGR
MEN TLT
MEN'S
LOCKER
55VEST
WOMEN TLT
58WOMEN'S
LOCKER
CORRIDOR
CLOSET
51 CASH
OFFICE
VAULT
VEST
CLOSET
NEW INTRUSION
ALARM ROOM
AD-101
AD-102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 911 - GROUND FLOOR DEMOLITION
PLAN - NORTH
PS MC AD-101
KEY NOTE:
1. DEMOLISH EXISTING DOOR TO BE REPLACE
BY A NEW METAL FOR THE NEW INTRUSION
ALARM ROOM.
1/8" = 1'-0"1
B911 GROUND FLOOR PLAN - DEMOLITION - NORTH
F
G
H
D.5
F.5
G.2
G.4
G.8
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
LOCATION OF MEZZ. #2
ABOVE
LOCATION OF MEZZ. #3
ABOVE
NORTH
SOUTH
NORTH
SOUTH
COOLER
BARBER
STORE/
LAUNDRY
MEN TLT
WOMEN TLT
CONCESSION
CONCESSION
STORAGE
BEAUTY
SALOON
LAB
FOOD
COURT
OFFICE
VISION
CENTER
VESTIBULE
FOOD
COURT
SEATING
FOOD
COURT
STORAGE
MECH
GNC
SECURITY
OFFICE
VESTIBULE
CLASS SIX
DRESSING
CORRIDOR
ROBIN
HOOD
FRANKS
26ANTHONY'S
TLT
VEST
19COOLER/
FREEZER
KITCHEN
BURGER
KING
FREEZER/
COOLER
AD-101
AD-102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/2
/2
:0
:1
P
M
BUILDING 911 - GROUND FLOOR DEMOLITION
PLAN - SOUTH
PS MC AD-102
1/8" = 1'-0"1
B911 GROUND FLOOR PLAN - DEMOLITION - SOUTH
KEY NOTES:
1. DEMOLISH EXISTING BRICK WALL. REPAIR AND RECONSRUCT
CONCRETE CURB AFFECTED BY THE DEMOLITION. SEE CIVIL
DRAWINGS.
2. DEMOLISH EXISTING EXTERIOR DOOR.
3. DEMOLISH SECTION OF BRICK PLANT BOX AFFECTED BY THE
REMOVAL OF WALLS AND SECTION OF CONCRETE CURB.
4. DEMOLISH EXISTING FREEZER/ COOLER DOOR.
5. DEMOLISH EXISTING FREEZER/ COOLER.
A
2 3
B
C
D
4 5 6 7
A.5
B.5
C.5
D.5
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
OPS
RECEPT
DRESSING
SEM
GEN
MANAGER
MEN TLT
MEN'S
LOCKER
WOMEN TLT
58WOMEN'S
LOCKER
VEST
HARDLINES
MGR
VEST
CASH
OFFICE
VAULT
CLOSET
TRAINING
VM RM
JANITOR
PERSONNEL
VEST
EMP
LOUNGE
TELE
OFFICE
MECH
CORRIDOR
Room
87ELEC
SEC
SEC
MPA
MPA OFFICE
OFFICE
TOILET
OUTDOOR
LIVING
DRESSING
NEW INTRUSION ALARM ROOM
NORTH
SOUTH
NORTH
SOUTH
AD-101
AD-102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 911 - GROUND FLOOR - NEW WORK
PLAN - NORTH
PS MC AH-101
KEY NOTES:
1. PROVIDE NEW METAL DOOR - STOREROOM LOCK,
MORTISE AND 7 PIN SMALL CORE FORMAT.
1/8" = 1'-0"1
B911 GROUND FLOOR NEW WORK PLAN - NORTH
F
G
H
D.5
F.5
G.2
G.4
G.8
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
VESTIBULE
CLASS SIX
STORE/
LAUNDRY
BARBER
COOLER
MEN TLT
WOMEN TLT
BEAUTY
SALOON
STORAGE
VESTIBULE
VISION
CENTER
LAB
FOOD
COURT
OFFICE
CONCESSION
CONCESSION
SECURITY
GNC
STORAGE
MECH
OFFICE
80 DRESSING
CORRIDOR
FRANKS
ROBIN
HOOD
ANTHONY'S
COOLER/
FREEZER
VEST
TLT
BURGER
KING
KITCHEN
FOOD
COURT
FOOD
COURT
SEATING
NORTH
SOUTH
NORTH
SOUTH
AH-101
AH-102
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/2
/2
:0
:1
P
M
BUILDING 911 - GROUND FLOOR - NEW WORK
PLAN - SOUTH
PS MC AH-102
1/8" = 1'-0"1
B911 GROUND FLOOR NEW WORK PLAN - SOUTH
KEY NOTES:
1. OPENING SHALL BE FILLED WITH NEW CMU WALL AFTER
REMOVING THE EXISITNG DOOR AND MATCH THE EXISTING
BRICK FACADE.
2. REFINISH EXTERIOR BRICKWALL TO MATCH THE EXISTING
AFTER DEMOLITION.
3. PROVIDE NEW SECTION OF BRICK PLANT BOX AND MATCH THE
EXISTING.
2 3
B
C
D
4 5 6 7
A.5
B.5
C.5
D.5
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
8' - 11"
7' - 11"
7' - 11"
7' - 11" 7' - 11"
7' - 11"
7' - 11"
8' - 11"
8' - 11"
8' - 11"
9' - 0"
9' - 0"
7' - 11"
7' - 11"
7' - 11"
8' - 11"
8' - 11"
7' - 11"
8' - 11"
8' - 11"
8' - 11"
8' - 11"
8' - 11"
NORTH
SOUTH
NORTH
SOUTH
MPA OFFICE
OFFICE
TOILET
MPA
SEC
SEC
ELEC
Room
87 CORRIDOR
TELE
OFFICE
PERSONNEL
CLOSET
JANITOR
VEST
EMP
LOUNGE
VM RM
78 TRAINING
VEST
CLOSET
VAULT
CASH
OFFICE
HARDLINES
MGR
GEN
MANAGER
RECEPT
SEM
OPS
DRESSING
CORRIDOR
AD-201
AD-202
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 911 - GROUND FLOOR CEILING
DEMOLITION PLAN - NORTH
PS MC AD-201
1/8" = 1'-0"1
B911 GROUND FLOOR CEILING -DEMO. PLAN - NORTH
NOTES:
1. CONTRACTOR SHALL SURVEY AND VERIFY THE ROUTING OF
FIRE ALARM SYSTEM CONDUITS TO DETERMINE THE EXTENT OF
CEILING AREAS REQUIRING TEMPORARY REMOVAL.
2. CONTRACTOR SHALL PROTECT ALL EXISTING ITEMS TO REMAIN.
ANY EXISTING ITEMS DAMAGED DURING DEMOLITION OR
CONSTRUCTION SHALL BE RESTORED OR REPLACED AT NO
COST TO THE GOVERNMENT.
3. REFERENCE ELECTRICAL DRAWINGS FOR WORK AND
CONNECTIONS TO BUILDING SYSTEMS OUTSIDE LIMIT OF WORK
THAT REQUIRE REMOVAL AND REINSTALLATION OF CEILING
SYSTEMS OR DEMOLITION AND PATCHING OF WALLS.
4. G.C. TO PROVIDE SHOP DRAWINGS. G.C. TO SUBMIT WORK PLAN
FOR THIS TASK FOR APPROVAL
KEYED NOTES:
1. TEMPORARY REMOVAL, DEMOLITION, REPAIR AND PATCHING
OF WALLS AND ACOUSTIC CEILING TILES IN AREAS INDICATED
AROUND NEW DEVICES INCLUDING FIRE ALARM DEVICES AND
SMOKE DETECTORS. ALL DIMENSIONS AND SITE CONDITIONS
SHALL BE VERIFIED IN THE FILED (V.I.F)
Revisions: Date:
VHAMACRuizMR Text Box 612A4-26-051
F
G
H
D.5
F.5
G.2
G.4
G.8
1.7 5.2 6.1 6.45.3 5.5 6.2 6.6 6.83.12.72.32.10.5 5.1 5.6
8' - 1"
8' - 1"
9' - 6"
11' - 2"
10' - 0"
7' - 11"
7' - 11"
7' - 11"
7' - 11"
8' - 8"
7' - 11" 7' - 11"
11' - 2"
8' - 8"8' - 8"
8' - 6"
8' - 11"
7' - 11"
8' - 11" 8' - 6"
11' - 11"
NORTH
SOUTH
NORTH
SOUTH
VESTIBULE
CLASS SIX
COOLER
BEAUTY
SALOON
STORAGE
VESTIBULE
VISION
CENTER
FOOD
COURT
OFFICE
LAB
KITCHEN
COOLER/
FREEZER
VEST
TLT
BURGER
KING
FOOD
COURT
FOOD
COURT
SEATING
SECURITY
CONCESSION
CONCESSION
GNC
STORAGE
MECH
ANTHONY'S
ROBIN
HOOD
CORRIDOR
DRESSING
FRANKS
OFFICE
1 1
AD-201
AD-202
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 911 - GROUND FLOOR CEILING
DEMOLITION PLAN - SOUTH
PS MC AD-202
1/8" = 1'-0"1
B911 GROUND FLOOR CEILING DEMO. PLAN - SOUTH
NOTES:
1. CONTRACTOR SHALL SURVEY AND VERIFY THE ROUTING OF
FIRE ALARM SYSTEM CONDUITS TO DETERMINE THE EXTENT OF
CEILING AREAS REQUIRING TEMPORARY REMOVAL.
2. CONTRACTOR SHALL PROTECT ALL EXISTING ITEMS TO REMAIN.
ANY EXISTING ITEMS DAMAGED DURING DEMOLITION OR
CONSTRUCTION SHALL BE RESTORED OR REPLACED AT NO
COST TO THE GOVERNMENT.
3. REFERENCE ELECTRICAL DRAWINGS FOR WORK AND
CONNECTIONS TO BUILDING SYSTEMS OUTSIDE LIMIT OF WORK
THAT REQUIRE REMOVAL AND REINSTALLATION OF CEILING
SYSTEMS OR DEMOLITION AND PATCHING OF WALLS.
4. G.C. TO PROVIDE SHOP DRAWINGS. G.C. TO SUBMIT WORK PLAN
FOR THIS TASK FOR APPROVAL.
KEY NOTES:
1. TEMPORARY REMOVAL, DEMOLITION, REPAIR AND PATCHING
OF WALLS AND ACOUSTIC CEILING TILES IN AREAS INDICATED
AROUND NEW DEVICES INCLUDING FIRE ALARM DEVICES AND
SMOKE DETECTORS. ALL DIMENSIONS AND SITE CONDITIONS
SHALL BE VERIFIED IN THE FIELD (V.I.F)
UP
197 SF
EXAM ROOM
1C81
117 SF
EXAM ROOM
1C79
101 SF
CONSULT
ROOM
1C75
100 SF
CONSULT
ROOM
1C73
27 SF
U-TOILET
1C65A
55 SF
PRINTING
1C67
182 SF
CORRIDOR
1C82A
83 SF
DECON
1D07
38 SF
SOILED UTILITY
1D09
34 SF
U-TOILET
1E11A
118 SF
OFFICE
1B01A
95 SF
EXAM ROOM
1B06
95 SF
OFFICE
1B22
95 SF
CONSULT
ROOM
1B08
96 SF
EXAM ROOM
1B18
74 SF
VITALS
1B16
100 SF
EXAM ROOM
1C18
99 SF
OFFICE
1C22
99 SF
EXAM ROOM
1C24
109 SF
OFFICE
1C28
99 SF
EXAM ROOM
1C26
102 SF
EXAM ROOM
1C12
102 SF
EXAM ROOM
1C06
103 SF
EXAM ROOM
1C04
409 SF
CORRIDOR
1C82B
173 SF
EXAM ROOM
1D21
76 SF
CONSULT
ROOM
1D19
108 SF
BREAKROOM
1E07
49 SF
DRESSING
1E15B
57 SF
HOLDING
1E15C
67 SF
U-TOILET
1E15A
81 SF
ULTRASOUND
1E19
91 SF
W-TOILET
1A28
93 SF
M-TOILET
1A26
91 SF
OFFICE
1F02
324 SF
OFFICE
1F05
147 SF
OFFICE
1F03
113 SF
CORRIDOR
1A30
75 SF
STORAGE
1K17
86 SF
M-TOILET
1A08
97 SF
CONSULT
ROOM
1K06
112 SF
CONSULT
ROOM
1K04
123 SF
CORRIDOR
1F10
155 SF
U-TOILET
1A16
55 SF
ELECTRICAL
1H28
143 SF
U-TOILET
1A18
112 SF
HAC
1F01A
103 SF
OFFICE
1F14
97 SF
OFFICE
1F12
105 SF
EXAM ROOM
1H22
211 SF
CORRIDOR
1B10
106 SF
EXAM ROOM
1C32
97 SF
EXAM ROOM
1C34
101 SF
EXAM ROOM
1C36
94 SF
EXAM ROOM
1C38
98 SF
EXAM ROOM
1C42
96 SF
EXAM ROOM
1B12
101 SF
COPY ROOM
1B02
41 SF
ELECTRICAL
1C25
41 SF
U-TOILET
1C23A
78 SF
STORAGE
1C91
100 SF
OFFICE
1K02
394 SF
CORRIDOR
1K00
99 SF
OFFICE
1K08
97 SF
OFFICE
1J14
100 SF
OFFICE
1J12
25 SF
HAC
1J06
114 SF
STORAGE
1J08
90 SF
OFFICE
1B05
91 SF
VITALS
1B03
176 SF
CONSULT
ROOM
1K01
567 SF
OFFICE
1K05
91 SF
CONSULT
ROOM
1K12
262 SF
CORRIDOR
1J00A
138 SF
BLOOD DRAW
1J32
154 SF
ISOLATION
1D05
30 SF
IT
1C85
31 SF
U-TOILET
1C83
105 SF
EXAM ROOM
1C58
109 SF
EXAM ROOM
1C62
98 SF
EXAM ROOM
1C56
99 SF
EXAM ROOM
1C54
98 SF
CONSULT
ROOM
1C66
98 SF
EXAM ROOM
1C64
96 SF
CONSULT
ROOM
1C72
95 SF
CONSULT
ROOM
1C68
98 SF
EXAM ROOM
1C52
101 SF
EXAM ROOM
1C48
98 SF
CONSULT
ROOM
1C74
104 SF
EXAM ROOM
1C46
86 SF
CONSULT
ROOM
1C61
85 SF
CONSULT
ROOM
1C27
91 SF
EXAM ROOM
1B15
163 SF
OFFICE
1B07
150 SF
PROCEDURE
ROOM
1B09
155 SF
OFFICE
1C65
48 SF
LACTATION
1B04
178 SF
W-TOILET
1B34
404 SF
CORRIDOR
1E00
51 SF
ELECTRICAL
1E09
208 SF
MAMMO
1D17
102 SF
CONSULT
1D13
109 SF
STORAGE
1E13
145 SF
OFFICE
1D10A
190 SF
OFFICE
1D00E
334 SF
RECEPTION
1C93A
100 SF
EXAM ROOM
1C16
101 SF
EXAM ROOM
1C44
92 SF
OFFICE
1G09
121 SF
STORAGE
1G07
252 SF
MAINTENANCE
OFFICE
1F30
99 SF
CYLINDER
STOARAGE
1F28B
241 SF
CORRIDOR
1F00
583 SF
VESTIBULE
1A00
463 SF
LOADING DOCK
71 SF
W-TOILET
1A06
95 SF
OFFICE
1K05A
115 SF
EXAM ROOM
1C14
96 SF
EXAM ROOM
1C08
114 SF
TRIAGE
1C02
175 SF
STAIR
#2
29 SF
HAC
1G01
745 SF
OFFICE
1F20A
1200 SF
PHARMACY
1G00
53 SF
VAULT
1F26
48 SF
FLAMMABLE
STORAGE
1F28A
85 SF
EXAM ROOM
1B17
95 SF
EXAM ROOM
1B19
180 SF
OFFICE
1C63
138 SF
EXAM ROOM
1Z04
130 SF
EXAM ROOM
1H10
271 SF
RECORDS
1E03
326 SF
CORRIDOR
1C10
96 SF
VESTIBULE
1D00A25 SF
SHOWER
1D11
601 SF
CORRIDOR
1A32
77 SF
CORRIDOR
1B10A
256 SF
LAB
1J02
31 SF
O&IT
1A20B
1780 SF
RECEIVING
1F20
90 SF
PRINTING
1K14
129 SF
CORRIDOR
1A10
164 SF
CORRIDOR
1A04
101 SF
RECEPTION
1B14
63 SF
W-TOILET
1B11
1011 SF
RECORDS
1H20 39 SF
ELEVATOR
CONTROL
ROOM
1A20A
91 SF
OFFICE
1D01B
126 SF
OFFICE
1C21
103 SF
EXAM ROOM
1B24
369 SF
CORRIDOR
1C30A
358 SF
CORRIDOR
1C60
327 SF
CORRIDOR
1C30 407 SF
CORRIDOR
1D10
98 SF
SUPPLY ROOM
1C23
315 SF
WAITING
1B32
216 SF
CORRIDOR
1E00A
246 SF
CONTROL
ROOM
1E16
303 SF
XRAY
1E15
355 SF
XRAY
1E11
203 SF
CORRIDOR
1J00
110 SF
RECEPTION
1J04
97 SF
CONSULT
ROOM
1C69
98 SF
CONSULT
ROOM
1C71
97 SF
CORRIDOR
1C82
STAIR #3
251 SF
CORRIDOR
1H00
25 SF
HAC
1B01B
348 SF
CORRIDOR
1B00
57 SF
STORAGE
1F01
51 SF
ELECTRICAL
1C87
3388 SF
CENTRAL
WAITING AREA
1A12
87 SF
OI&T
1Z09
34 SF
DRESSING
1E12
20 SF
STORAGE
1C67A
83 SF
TOILET
1J103
1472 SF
GYM
1H20
134 SF
TREATMENT
ROOM
1Z07
198 SF
CORRIDOR
1K00A
72 SF
STORAGE
1Z10
105 SF
EXAM ROOM
1H22
46 SF
STORAGE
1Z02
202 SF
OFFICE
1H23
153 SF
RECEPTION
1E01
24 SF
SOILED LINEN
1C89
124 SF
OFFICE
1D01A
193 SF
PROCEDURE
1D03
46 SF
VAULT
1G05
150 SF
CORRIDOR
1A24
116 SF
OFFICE
1F04
118 SF
CONSULT
ROOM
1K08/27A
121 SF
CONSULT
ROOM
1K08/28
129 SF
CONSULT
ROOM
1K08/27B
150 SF
CONSULT
ROOM
1K08/27C
45 SF
STORAGE
1G07B
100 SF
OFFICE
1F11
95 SF
OFFICE
1F13
247 SF
VAULT
1G00A
93 SF
OFFICE
1D03A
144 SF
BREAK ROOM
1D01
78 SF
CONSULT
ROOM
1C69A
6 SF
CLEAN LINEN
1Z06
130 SF
OFFICE
1K14A
133 SF
OFFICE
1Z12
176 SF
OFFICE
1Z11
6 SF
CLOSET
1Z08
30 SF
STORAGE
B R
E A
K R
O O
M
90 SF
MED SUPPLY
1C21A
67 SF
ELEVATOR
1A20
336 SF
CORRIDOR
1A11
NEW INTRUSION
ALARM ROOM
1 1 1
1 1
1 1 1
1 1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 98 - FIRST FLOOR DEMOLITION
PLAN
PS MC AD-301
1/8" = 1'-0"1
B98 ARCHITECTURAL- FIRST FLOOR DEMOLITION
NOTES:
1. PROVIDE TEMPORARY CONSTRUCTION BARRIERS AS REQUIRED
TO PROTECT ADJACENT AREAS FROM CONSTRUCTION DUST
AND TO PROVIDE A SECURE WORK AREA
2. CONTRACTOR SHALL SURVEY AND VERIFY THE ROUTING OF
FIRE ALARM SYSTEM CONDUITS TO DETERMINE THE EXTENT OF
CEILING AREAS REQUIRING TEMPORARY REMOVAL.
3. CONTRACTOR SHALL PROTECT ALL EXISTING ITEMS TO REMAIN.
ANY EXISTING ITEMS DAMAGED DURING DEMOLITION OR
CONSTRUCTION SHALL BE RESTORED OR REPLACED AT NO
COST TO THE GOVERNMENT.
4. REFERENCE ELECTRICAL DRAWINGS FOR WORK AND
CONNECTIONS TO BUILDING SYSTEMS OUTSIDE LIMIT OF WORK
THAT REQUIRE REMOVAL AND REINSTALLATION OF CEILING
SYSTEMS OR DEMOLITION AND PATCHING OF WALLS.
5. G.C. TO PROVIDE SHOP DRAWINGS. G.C. TO SUBMIT WORK PLAN
FOR THIS TASK FOR APPROVAL
KEY NOTES:
1. TEMPORARY REMOVAL, DEMOLITION, REPAIR AND PATCHING
OF WALLS AND ACOUSTIC CEILING TILES/ GYP.BD CEILING IN
AREAS INDICATED AROUND NEW DEVICES INCLUDING FIRE
ALARM DEVICES AND SMOKE DETECTORS. ALL DIMENSIONS
AND SITE CONDITIONS SHALL BE VERIFIED IN THE FIELD (V.I.F)
LEGEND: :
AREA OF REPAIR AT CEILING
DN
DN
OPEN TO BELOW OPEN TO BELOW
STAIR #3
BREAK
ROOM
ROOF ACCESS
ROOF ACCESS ROOF ACCESS
145 SF
EXAM ROOM
2U13
132 SF
EXAM ROOM
2U15
129 SF
STORAGE
2U17
205 SF
OFFICE
2U19
45 SF
SOUND
BOOTHS
2L05A
107 SF
OFFICE
2L03A
108 SF
OFFICE
2L03B
310 SF
AUDIOLOGY
2L03
43 SF
HAC
2U11
69 SF
U-TOILET
2U07
115 SF
EXAM ROOM
2U05
102 SF
OFFICE
2U03C
123 SF
EXAM ROOM
2U03B
122 SF
EXAM ROOM
2U03A
256 SF
WAITING
2U01
145 SF
OFFICE
2U03
261 SF
BREAK ROOM
2T40
145 SF
OFFICE
2T40A
114 SF
OFFICE
2T40B
110 SF
CORRIDOR
2L00A
320 SF
WAITING
2L00
99 SF
RECEPTION
2L02
101 SF
TEST ROOM
2M13
102 SF
EXAM ROOM
2M09
228 SF
CORRIDOR
2M05
47 SF
U-TOILET
2M07
117 SF
EXAM ROOM
2M25
99 SF
OFFICE
2M27
102 SF
OFFICE
2M29
97 SF
EXAM ROOM
2M31
250 SF
PROVIDER
OFFICE
2M35 98 SF
OFFICE
2M37
190 SF
TREATMENT
2M39
82 SF
EXAM ROOM
2M41
103 SF
EXAM ROOM
2L07
93 SF
OFFICE
2M15
90 SF
OFFICE
2M17
82 SF
OFFICE
2M19
97 SF
OFFICE
2M21
33 SF
HAC
2M23
96 SF
EXAM ROOM
2M12
94 SF
EXAM ROOM
2M14
96 SF
EXAM ROOM
2M16
94 SF
EXAM ROOM
2M18
92 SF
OFFICE
2M22
96 SF
OFFICE
2M24
97 SF
EXAM ROOM
2M26
99 SF
EXAM ROOM
2M28
96 SF
EXAM ROOM
2M32
99 SF
EXAM ROOM
2M34
48 SF
IT
2M20A
49 SF
ELECTRICAL
2M20B
100 SF
OFFICE
2M08
125 SF
OFFICE
2M06
85 SF
COPY
2M04
98 SF
OFFICE
2M02
115 SF
EXAM ROOM
2N09
100 SF
EXAM ROOM
2N07
49 SF
ELEC.
2N05
42 SF
U-TOILET
2N117
136 SF
PROVIDER
OFFICE
2N13 86 SF
BREAK ROOM
2N15
72 SF
ELECTRICAL
COMMS
2M43
71 SF
OFFICE
2N45
208 SF
OMNICELL
2M47
367 SF
PROVIDER
OFFICE
2P19
127 SF
OFFICE
2P21
109 SF
EXAM ROOM
2P23
111 SF
EXAM ROOM
2P25
103 SF
EXAM ROOM
2P27 160 SF
TREATMENT
2P29
104 SF
OFFICE
2N00A
248 SF
CHECK-IN
2P01
100 SF
OFFICE
2P35
102 SF
EXAM ROOM
2Q03A
137 SF
STORAGE
2Q03
164 SF
EXAM ROOM
2Q05
216 SF
EXAM ROOM
2Q07
110 SF
EXAM ROOM
2P31
27 SF
U-TOILET
2P33
415 SF
CONFERENCE
2A28
161 SF
EQUIPMENT
2Q01
1564 SF
MECHANICAL
2A03A
348 SF
M-TOILET
2A16
322 SF
W-TOILET
2A18
238 SF
OFFICE
2A22
224 SF
OFFICE
2R01
88 SF
OFFICE
2R01A
134 SF
CONSULT
ROOM
2S05
89 SF
OFFICE
2S01
139 SF
STORAGE
2S03
102 SF
OFFICE
2A10A
123 SF
OFFICE
2A10
100 SF
OFFICE
2A08
187 SF
OFFICE
2T17
123 SF
OFFICE
2T15
100 SF
OFFICE
2T21
50 SF
HAC
2T19
106 SF
OFFICE
2T27
162 SF
EXAM ROOM
2T25
375 SF
CONFERENCE
2T23
374 SF
CONFERENCE
2T23A
191 SF
OFFICE
2T11
94 SF
OFFICE
2T13
274 SF
IT
2T09A
56 SF
IT
2T09B
1639 SF
MECHANICAL
2T09
143 SF
OFFICE
2T07A
219 SF
OFFICE
2T03
199 SF
OFFICE
2T01
265 SF
OI&T
2S13A
191 SF
OFFICE
2T07
335 SF
OFFICE
2T05
314 SF
OFFICE
2S13
319 SF
STORAGE
2S09B
379 SF
GROUP ROOM
2S09 101 SF
OFFICE
2S09A
100 SF
OFFICE
2S07
128 SF
OFFICE
2R07
210 SF
STORAGE
2R05
248 SF
CORRIDOR
2U00
387 SF
VESTIBULE
2T30A
92 SF
CORRIDOR
2T30
125 SF
CORRIDOR
2L00B
108 SF
CORRIDOR
2M11A
136 SF
CORRIDOR
2M20
371 SF
CORRIDOR
2M10
404 SF
CORRIDOR
2M30
189 SF
CORRIDOR
2M48
126 SF
CORRIDOR
2N18
193 SF
CORRIDOR
2N10
237 SF
CORRIDOR
2P20
325 SF
CORRIDOR
2P20A
121 SF
CORRIDOR
2Q10
174 SF
CORRIDOR
2Q00A
207 SF
CORRIDOR
2A30
113 SF
CORRIDOR
2A32
180 SF
CORRIDOR
2R02
308 SF
CORRIDOR
2T10
3434 SF
CORRIDOR
2T20
30 SF
CORRIDOR
2T00B
646 SF
MEDICAL
RECORDS
2M03
458 SF
CORRIDOR
2A12
231 SF
CORRIDOR
2T00
236 SF
CORRIDOR
2S04
261 SF
CORRIDOR
2R10
105 SF
EXAM ROOM
2M11
415 SF
PROVIDER
OFFICE
2N03A
60 SF
ELEVATOR
1H25
30 SF
TOILET
2T03A
12 SF
CLOSET
2T03B
526 SF
WAITING
2M00
145 SF
RECEPTION
2M01
384 SF
WAITING
2Q00
129 SF
EXAM ROOM
2N03B
128 SF
EXAM ROOM
2N03C
245 SF
RECEPTION
2N03 97 SF
ELEVATOR
2Q07A
60 SF
SOUND BOOTH
2L05B
106 SF
CORRIDOR
2L05
75 SF
2M05B
123 SF
SOUND BOOTH
II
2L03C
1 1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:3
P M
BUILDING 98 - SECOND FLOOR DEMOLITION
PLAN
PS MC AD-302
1/8" = 1'-0"1
B98 ARCHITECTURAL-SECOND FLOOR DEMOLITION
NOTES:
1. PROVIDE TEMPORARY CONSTRUCTION BARRIERS AS REQUIRED
TO PROTECT ADJACENT AREAS FROM CONSTRUCTION DUST
AND TO PROVIDE A SECURE WORK AREA
2. CONTRACTOR SHALL SURVEY AND VERIFY THE ROUTING OF
FIRE ALARM SYSTEM CONDUITS TO DETERMINE THE EXTENT OF
CEILING AREAS REQUIRING TEMPORARY REMOVAL.
3. CONTRACTOR SHALL PROTECT ALL EXISTING ITEMS TO REMAIN.
ANY EXISTING ITEMS DAMAGED DURING DEMOLITION OR
CONSTRUCTION SHALL BE RESTORED OR REPLACED AT NO
COST TO THE GOVERNMENT.
4. REFERENCE ELECTRICAL DRAWINGS FOR WORK AND
CONNECTIONS TO BUILDING SYSTEMS OUTSIDE LIMIT OF WORK
THAT REQUIRE REMOVAL AND REINSTALLATION OF CEILING
SYSTEMS OR DEMOLITION AND PATCHING OF WALLS.
5. G.C. TO PROVIDE SHOP DRAWINGS. G.C. TO SUBMIT WORK PLAN
FOR THIS TASK FOR APPROVAL
KEY NOTES:
1. TEMPORARY REMOVAL, DEMOLITION, REPAIR AND PATCHING
OF WALLS AND ACOUSTIC CEILING TILES/ GYP.BD CEILING IN
AREAS INDICATED AROUND NEW DEVICES INCLUDING FIRE
ALARM DEVICES AND SMOKE DETECTORS. ALL DIMENSIONS
AND SITE CONDITIONS SHALL BE VERIFIED IN THE FIELD (V.I.F)
LEGEND: :
AREA OF REPAIR AT CEILING
VHAMACRuizMR
Exhibit A
VHAMACRuizMR
Exhibit A
VHAMACRuizMR
Exhibit A
VHAMACRuizMR
612A4-26-051
VHAMACRuizMR
Exhibit A
Exhibit A
VHAMACRuizMR
EXTENT OF BUILDING ABOVE
L O
A D
IN
G
1048 SF
MECHANICAL
ROOM
200 SF
STAIRS
1H27UPDEMO
DEMO
SM
PS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:5
P M
AS INDICATED
BUILDING 98 FIRE ALARM DEMOLITION -
BASEMENT REMOVALS
PS MC FAD-400
1/8" = 1'-0"1
B98 FIRE ALARM- BASEMENT DEMOLITION
FIRE ALARM DEMOLITION PLAN NOTES:
1. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
INITIATING DEVICES AND NOTIFICATION APPLIANCES.
2. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
WIRING.
3. ALL FIRE ALARM CONDUITS, WHETHER NEW OR EXISTING AND BEING
REUSED, SHALL BE UNDAMAGED METAL AND PAINTED A UNIFORM RED
COLOR TO ENSURE CONSISTENCY THROUGHOUT THE ENTIRE FIRE
ALARM SYSTEM. ALL CONDUITS MUST MEET CODE, VA SPECIFICATIONS
AND PROJECT REQUIREMENTS.
4. DURING REMOVALS THE BUILDING SHALL HAVE FIRE ALARM
SUPERVISED COVERAGE AT THE END OF EVERY BUSINESS DAY SO
THAT THE FIRE DEPARTMENT MAY BE ABLE TO RESPOND TO ANY FIRE
EMERGENCIES.
5. THE SPRINKLER SYSTEM CENTRAL STATION SUPERVISION SHALL BE
MAINTAINED THROUGHOUT THIS PROJECT. CONTRACTOR SHALL
SUBMIT A NFPA 241 PLAN FOR VA REVIEW AND APPROVAL.
Revisions: Date:
VHAMACRuizMR Text Box Exhibit A
VHAMACRuizMR
SD
SD
SD SD
UP
UP
UP
197 SF
EXAM ROOM
1C81
117 SF
EXAM ROOM
1C79
101 SF
CONSULT
ROOM
1C75
100 SF
CONSULT
ROOM
1C73
27 SF
U-TOILET
1C65A
55 SF
PRINTING
1C67
182 SF
CORRIDOR
1C82A
83 SF
DECON
1D07
38 SF
SOILED UTILITY
1D09
34 SF
U-TOILET
1E11A
118 SF
OFFICE
1B01A
95 SF
EXAM ROOM
1B06
95 SF
OFFICE
1B22
95 SF
CONSULT
ROOM
1B08
96 SF
EXAM ROOM
1B18
74 SF
VITALS
1B16
100 SF
EXAM ROOM
1C18
99 SF
OFFICE
1C22
99 SF
EXAM ROOM
1C24
109 SF
OFFICE
1C28
99 SF
EXAM ROOM
1C26
102 SF
EXAM ROOM
1C12
102 SF
EXAM ROOM
1C06
103 SF
EXAM ROOM
1C04
409 SF
CORRIDOR
1C82B
173 SF
EXAM ROOM
1D21
76 SF
CONSULT
ROOM
1D19
108 SF
BREAKROOM
1E07
49 SF
DRESSING
1E15B
57 SF
HOLDING
1E15C
67 SF
U-TOILET
1E15A
81 SF
ULTRASOUND
1E19
91 SF
W-TOILET
1A28
93 SF
M-TOILET
1A26
91 SF
OFFICE
1F02
324 SF
OFFICE
1F05
147 SF
OFFICE
1F03
113 SF
CORRIDOR
1A30
75 SF
STORAGE
1K17
86 SF
M-TOILET
1A08
97 SF
CONSULT
ROOM
1K06
112 SF
CONSULT
ROOM
1K04
123 SF
CORRIDOR
1F10
155 SF
U-TOILET
1A16
55 SF
ELECTRICAL
1H28
143 SF
U-TOILET
1A18
112 SF
HAC
1F01A
103 SF
OFFICE
1F14
97 SF
OFFICE
1F12
105 SF
EXAM ROOM
1H22
211 SF
CORRIDOR
1B10
106 SF
EXAM ROOM
1C32
97 SF
EXAM ROOM
1C34
101 SF
EXAM ROOM
1C36
94 SF
EXAM ROOM
1C38
98 SF
EXAM ROOM
1C42
96 SF
EXAM ROOM
1B12
101 SF
COPY ROOM
1B02
41 SF
ELECTRICAL
1C25
41 SF
U-TOILET
1C23A
78 SF
STORAGE
1C91
100 SF
OFFICE
1K02
394 SF
CORRIDOR
1K00
99 SF
OFFICE
1K08
97 SF
OFFICE
1J14
100 SF
OFFICE
1J12
25 SF
HAC
1J06
114 SF
STORAGE
1J08
90 SF
OFFICE
1B05
91 SF
VITALS
1B03
176 SF
CONSULT
ROOM
1K01
567 SF
OFFICE
1K05
91 SF
CONSULT
ROOM
1K12
262 SF
CORRIDOR
1J00A
138 SF
BLOOD DRAW
1J32
154 SF
ISOLATION
1D05
30 SF
IT
1C85
31 SF
U-TOILET
1C83
105 SF
EXAM ROOM
1C58
109 SF
EXAM ROOM
1C62
98 SF
EXAM ROOM
1C56
99 SF
EXAM ROOM
1C54
98 SF
CONSULT
ROOM
1C66
98 SF
EXAM ROOM
1C64
96 SF
CONSULT
ROOM
1C72
95 SF
CONSULT
ROOM
1C68
98 SF
EXAM ROOM
1C52
101 SF
EXAM ROOM
1C48
98 SF
CONSULT
ROOM
1C74
104 SF
EXAM ROOM
1C46
86 SF
CONSULT
ROOM
1C61
85 SF
CONSULT
ROOM
1C27
91 SF
EXAM ROOM
1B15
163 SF
OFFICE
1B07
150 SF
PROCEDURE
ROOM
1B09
155 SF
OFFICE
1C65
48 SF
LACTATION
1B04
178 SF
W-TOILET
1B34
404 SF
CORRIDOR
1E00
51 SF
ELECTRICAL
1E09
208 SF
MAMMO
1D17
102 SF
CONSULT
1D13
109 SF
STORAGE
1E13
145 SF
OFFICE
1D10A
190 SF
OFFICE
1D00E
334 SF
RECEPTION
1C93A
100 SF
EXAM ROOM
1C16
101 SF
EXAM ROOM
1C44
92 SF
OFFICE
1G09
121 SF
STORAGE
1G07
252 SF
MAINTENANCE
OFFICE
1F30
99 SF
CYLINDER
STOARAGE
1F28B
241 SF
CORRIDOR
1F00
583 SF
VESTIBULE
1A00
463 SF
LOADING DOCK
71 SF
W-TOILET
1A06
95 SF
OFFICE
1K05A
115 SF
EXAM ROOM
1C14
96 SF
EXAM ROOM
1C08
114 SF
TRIAGE
1C02
175 SF
STAIR
#2
29 SF
HAC
1G01
745 SF
OFFICE
1F20A
1200 SF
PHARMACY
1G00
53 SF
VAULT
1F26
48 SF
FLAMMABLE
STORAGE
1F28A
85 SF
EXAM ROOM
1B17
95 SF
EXAM ROOM
1B19
180 SF
OFFICE
1C63
138 SF
EXAM ROOM
1Z04
130 SF
EXAM ROOM
1H10
271 SF
RECORDS
1E03
326 SF
CORRIDOR
1C10
96 SF
VESTIBULE
1D00A25 SF
SHOWER
1D11
601 SF
CORRIDOR
1A32
77 SF
CORRIDOR
1B10A
256 SF
LAB
1J02
31 SF
O&IT
1A20B
1780 SF
RECEIVING
1F20
90 SF
PRINTING
1K14
129 SF
CORRIDOR
1A10
164 SF
CORRIDOR
1A04
101 SF
RECEPTION
1B14
63 SF
W-TOILET
1B11
1011 SF
RECORDS
1H20 39 SF
ELEVATOR
CONTROL
ROOM
1A20A
91 SF
OFFICE
1D01B
126 SF
OFFICE
1C21
103 SF
EXAM ROOM
1B24
369 SF
CORRIDOR
1C30A
358 SF
CORRIDOR
1C60
327 SF
CORRIDOR
1C30 407 SF
CORRIDOR
1D10
98 SF
SUPPLY ROOM
1C23
315 SF
WAITING
1B32
216 SF
CORRIDOR
1E00A
246 SF
CONTROL
ROOM
1E16
303 SF
XRAY
1E15
355 SF
XRAY
1E11
203 SF
CORRIDOR
1J00
110 SF
RECEPTION
1J04
97 SF
CONSULT
ROOM
1C69
98 SF
CONSULT
ROOM
1C71
97 SF
CORRIDOR
1C82
STAIR #3
251 SF
CORRIDOR
1H00
25 SF
HAC
1B01B
348 SF
CORRIDOR
1B00
57 SF
STORAGE
1F01
51 SF
ELECTRICAL
1C87
3388 SF
CENTRAL
WAITING AREA
1A12
87 SF
OI&T
1Z09
34 SF
DRESSING
1E12
20 SF
STORAGE
1C67A
83 SF
TOILET
1J103
1472 SF
GYM
1H20
134 SF
TREATMENT
ROOM
1Z07
198 SF
CORRIDOR
1K00A
72 SF
STORAGE
1Z10
105 SF
EXAM ROOM
1H22
46 SF
STORAGE
1Z02
202 SF
OFFICE
1H23
153 SF
RECEPTION
1E01
24 SF
SOILED LINEN
1C89
124 SF
OFFICE
1D01A
193 SF
PROCEDURE
1D03
46 SF
VAULT
1G05
150 SF
CORRIDOR
1A24
116 SF
OFFICE
1F04
118 SF
CONSULT
ROOM
1K08/27A
121 SF
CONSULT
ROOM
1K08/28
129 SF
CONSULT
ROOM
1K08/27B
150 SF
CONSULT
ROOM
1K08/27C
45 SF
STORAGE
1G07B
100 SF
OFFICE
1F11
95 SF
OFFICE
1F13
247 SF
VAULT
1G00A
93 SF
OFFICE
1D03A
144 SF
BREAK ROOM
1D01
78 SF
CONSULT
ROOM
1C69A
6 SF
CLEAN LINEN
1Z06
130 SF
OFFICE
1K14A
133 SF
OFFICE
1Z12
176 SF
OFFICE
1Z11
6 SF
CLOSET
1Z08
30 SF
STORAGE
B R
E A
K R
O O
M
90 SF
MED SUPPLY
1C21A
67 SF
ELEVATOR
1A20
336 SF
CORRIDOR
1A11
F A
C P
FS TS FSTS
M M M M
PS
PS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS SS SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
PS
PS
PS
PS
PS
PS
PS
SS
PS
PS
SM SM SM
DEMO
DEMO
DEMO
DEMODEMO
DEMODEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMODEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMODEMO
DEMO
NEW INRUSION
ALARM ROOM
DEMO
DEMO
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:5
P M
BUILDING 98 FIRE ALARM DEMOLITION - FIRST
FLOOR REMOVALS
PS MC FAD-401
1/8" = 1'-0"1
B98 FIRE ALARM- FIRST FLOOR DEMOLITION
FIRE ALARM DEMOLITION PLAN NOTES:
1. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
INITIATING DEVICES AND NOTIFICATION APPLIANCES.
2. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
WIRING.
3. ALL FIRE ALARM CONDUITS, WHETHER NEW OR EXISTING AND BEING
REUSED, SHALL BE UNDAMAGED METAL AND PAINTED A UNIFORM RED
COLOR TO ENSURE CONSISTENCY THROUGHOUT THE ENTIRE FIRE
ALARM SYSTEM. ALL CONDUITS MUST MEET CODE, VA SPECIFICATIONS
AND PROJECT REQUIREMENTS.
4. DURING REMOVALS THE BUILDING SHALL HAVE FIRE ALARM
SUPERVISED COVERAGE AT THE END OF EVERY BUSINESS DAY SO
THAT THE FIRE DEPARTMENT MAY BE ABLE TO RESPOND TO ANY FIRE
EMERGENCIES.
5. THE SPRINKLER SYSTEM CENTRAL STATION SUPERVISION SHALL BE
MAINTAINED THROUGHOUT THIS PROJECT. CONTRACTOR SHALL
SUBMIT A NFPA 241 PLAN FOR VA REVIEW AND APPROVAL.
Revisions: Date:
VHAMACRuizMR Text Box 612A4-26-051
VHAMACRuizMR
DN
OPEN TO BELOW OPEN TO BELOW
STAIR #3
BREAK
ROOM
ROOF ACCESS
ROOF ACCESS ROOF ACCESS
145 SF
EXAM ROOM
2U13
132 SF
EXAM ROOM
2U15
129 SF
STORAGE
2U17
205 SF
OFFICE
2U19
45 SF
SOUND
BOOTHS
2L05A
107 SF
OFFICE
2L03A
108 SF
OFFICE
2L03B
310 SF
AUDIOLOGY
2L03
43 SF
HAC
2U11
69 SF
U-TOILET
2U07
115 SF
EXAM ROOM
2U05
102 SF
OFFICE
2U03C
123 SF
EXAM ROOM
2U03B
122 SF
EXAM ROOM
2U03A
256 SF
WAITING
2U01
145 SF
OFFICE
2U03
261 SF
BREAK ROOM
2T40
145 SF
OFFICE
2T40A
114 SF
OFFICE
2T40B
110 SF
CORRIDOR
2L00A
320 SF
WAITING
2L00
99 SF
RECEPTION
2L02
101 SF
TEST ROOM
2M13
102 SF
EXAM ROOM
2M09
228 SF
CORRIDOR
2M05
47 SF
U-TOILET
2M07
117 SF
EXAM ROOM
2M25
99 SF
OFFICE
2M27
102 SF
OFFICE
2M29
97 SF
EXAM ROOM
2M31
250 SF
PROVIDER
OFFICE
2M35 98 SF
OFFICE
2M37
190 SF
TREATMENT
2M39
82 SF
EXAM ROOM
2M41
103 SF
EXAM ROOM
2L07
93 SF
OFFICE
2M15
90 SF
OFFICE
2M17
82 SF
OFFICE
2M19
97 SF
OFFICE
2M21
33 SF
HAC
2M23
96 SF
EXAM ROOM
2M12
94 SF
EXAM ROOM
2M14
96 SF
EXAM ROOM
2M16
94 SF
EXAM ROOM
2M18
92 SF
OFFICE
2M22
96 SF
OFFICE
2M24
97 SF
EXAM ROOM
2M26
99 SF
EXAM ROOM
2M28
96 SF
EXAM ROOM
2M32
99 SF
EXAM ROOM
2M34
48 SF
IT
2M20A
49 SF
ELECTRICAL
2M20B
100 SF
OFFICE
2M08
125 SF
OFFICE
2M06
85 SF
COPY
2M04
98 SF
OFFICE
2M02
115 SF
EXAM ROOM
2N09
100 SF
EXAM ROOM
2N07
49 SF
ELEC.
2N05
42 SF
U-TOILET
2N117
136 SF
PROVIDER
OFFICE
2N13 86 SF
BREAK ROOM
2N15
72 SF
ELECTRICAL
COMMS
2M43
71 SF
OFFICE
2N45
208 SF
OMNICELL
2M47
367 SF
PROVIDER
OFFICE
2P19
127 SF
OFFICE
2P21
109 SF
EXAM ROOM
2P23
111 SF
EXAM ROOM
2P25
103 SF
EXAM ROOM
2P27
160 SF
TREATMENT
2P29
104 SF
OFFICE
2N00A
248 SF
CHECK-IN
2P01
100 SF
OFFICE
2P35
102 SF
EXAM ROOM
2Q03A
137 SF
STORAGE
2Q03
164 SF
EXAM ROOM
2Q05
216 SF
EXAM ROOM
2Q07
110 SF
EXAM ROOM
2P31
27 SF
U-TOILET
2P33
415 SF
CONFERENCE
2A28
161 SF
EQUIPMENT
2Q01
1564 SF
MECHANICAL
2A03A
348 SF
M-TOILET
2A16
322 SF
W-TOILET
2A18
238 SF
OFFICE
2A22
224 SF
OFFICE
2R01
88 SF
OFFICE
2R01A
134 SF
CONSULT
ROOM
2S05
89 SF
OFFICE
2S01
139 SF
STORAGE
2S03
102 SF
OFFICE
2A10A
123 SF
OFFICE
2A10
100 SF
OFFICE
2A08
187 SF
OFFICE
2T17
123 SF
OFFICE
2T15
100 SF
OFFICE
2T21
50 SF
HAC
2T19
106 SF
OFFICE
2T27
162 SF
EXAM ROOM
2T25
375 SF
CONFERENCE
2T23
374 SF
CONFERENCE
2T23A
191 SF
OFFICE
2T11
94 SF
OFFICE
2T13
274 SF
IT
2T09A
56 SF
IT
2T09B
1639 SF
MECHANICAL
2T09
143 SF
OFFICE
2T07A
219 SF
OFFICE
2T03
199 SF
OFFICE
2T01
265 SF
OI&T
2S13A
191 SF
OFFICE
2T07
335 SF
OFFICE
2T05
314 SF
OFFICE
2S13
319 SF
STORAGE
2S09B
379 SF
GROUP ROOM
2S09 101 SF
OFFICE
2S09A
100 SF
OFFICE
2S07
128 SF
OFFICE
2R07
210 SF
STORAGE
2R05
248 SF
CORRIDOR
2U00
387 SF
VESTIBULE
2T30A
92 SF
CORRIDOR
2T30
125 SF
CORRIDOR
2L00B
108 SF
CORRIDOR
2M11A
136 SF
CORRIDOR
2M20
371 SF
CORRIDOR
2M10
404 SF
CORRIDOR
2M30
189 SF
CORRIDOR
2M48
126 SF
CORRIDOR
2N18
193 SF
CORRIDOR
2N10
237 SF
CORRIDOR
2P20
325 SF
CORRIDOR
2P20A
121 SF
CORRIDOR
2Q10
174 SF
CORRIDOR
2Q00A
207 SF
CORRIDOR
2A30
113 SF
CORRIDOR
2A32
180 SF
CORRIDOR
2R02
308 SF
CORRIDOR
2T10
3434 SF
CORRIDOR
2T20
30 SF
CORRIDOR
2T00B
646 SF
MEDICAL
RECORDS
2M03
458 SF
CORRIDOR
2A12
231 SF
CORRIDOR
2T00
236 SF
CORRIDOR
2S04
261 SF
CORRIDOR
2R10
105 SF
EXAM ROOM
2M11
415 SF
PROVIDER
OFFICE
2N03A
60 SF
ELEVATOR
1H25
30 SF
TOILET
2T03A
12 SF
CLOSET
2T03B
526 SF
WAITING
2M00
145 SF
RECEPTION
2M01
384 SF
WAITING
2Q00
129 SF
EXAM ROOM
2N03B
128 SF
EXAM ROOM
2N03C
245 SF
RECEPTION
2N03 97 SF
ELEVATOR
2Q07A
60 SF
SOUND BOOTH
2L05B
106 SF
CORRIDOR
2L05
75 SF
2M05B
123 SF
SOUND BOOTH
II
2L03C
HD HD
HD
HD
D S
D
D S
D
D S
D D
S D
D S
D
DSD DSD DSD DSD
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
PS
PS
SS
SS
SS
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMODEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
DEMO
SM
DEMO
SM
DEMO
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
AS INDICATED
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:5
P M
BUILDING 98 FIRE ALARM DEMOLITION -
SECOND FLOOR REMOVALS
PS MC FAD-402
1/8" = 1'-0"1
B98 FIRE ALARM-SECOND FLOOR DEMOLITION
FIRE ALARM DEMOLITION PLAN NOTES:
1. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
INITIATING DEVICES AND NOTIFICATION APPLIANCES.
2. CONTRACTOR SHALL REPLACE ALL EXISTING FIRE ALARM SYSTEM
WIRING.
3. ALL FIRE ALARM CONDUITS, WHETHER NEW OR EXISTING AND BEING
REUSED, SHALL BE UNDAMAGED METAL AND PAINTED A UNIFORM RED
COLOR TO ENSURE CONSISTENCY THROUGHOUT THE ENTIRE FIRE
ALARM SYSTEM. ALL CONDUITS MUST MEET CODE, VA SPECIFICATIONS
AND PROJECT REQUIREMENTS.
4. DURING REMOVALS THE BUILDING SHALL HAVE FIRE ALARM
SUPERVISED COVERAGE AT THE END OF EVERY BUSINESS DAY SO
THAT THE FIRE DEPARTMENT MAY BE ABLE TO RESPOND TO ANY FIRE
EMERGENCIES.
5. THE SPRINKLER SYSTEM CENTRAL STATION SUPERVISION SHALL BE
MAINTAINED THROUGHOUT THIS PROJECT. CONTRACTOR SHALL
SUBMIT A NFPA 241 PLAN FOR VA REVIEW AND APPROVAL.
Revisions: Date:
VHAMACRuizMR Text Box 612A4-26-051
VHAMACRuizMR
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANTS
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
MCC B911 AND B98 FIRE ALARM
REPLACEMENT & SECURITY UPGRADES
612A4-26-051
5342, 5443 Dudley Blvd, McClellan Park, CA 95652New England Engineering, Inc.
30 Turnpike Road, Suite #1 Southborough, MA 01772 Phone: (508) 485-4633 Ext. 54
FAX: (508) 485-1830
March 06,2026
KEY PLAN
Drawing Scale
N/A
Exhibit A
C U s e rs \j h o u s e \D o c u m e n ts
\M C
C B a n d
B
F ir e A la rm
R e p la c e m e n t_ jh o u s e W
S
E L .r v t
/4
/2
:0
:5
P M
BUILDING 98 FIRE ALARM DEMOLITION -
EXISTING FIRE ALARM RISER DIAGRAM
PS MC FAD-500
FIRE ALARM DEMOLITION - RISER DIAGRAM OF EXISTING FA SYSTEM
GENERAL NOTES:
1. CONTRACTOR SHAL CONFIRM ALL DEVICE QUANTITIES WITH
FLOOR PLANS. FIRE ALARM RISER DIAGRAM SHALL BE USED AS
A SYSTEM INTEGRATION DIAGRAM ONLY. ACTUAL FIRE ALARM
DEVICE COUNTS SHALL BE DONE WITH FIRE ALARM FLOOR
PLANS.
2. CONTRACTOR SHALL REPLACE EXISTING FIRE ALARM SYSTEM
WITH NEW ADDRESSABLE FIRE ALARM SYSTEM WITH VOICE
ALARM AND EVACUATION.
3. THE VA USES MIRCOM FA NETWORK SYSTEMS IN THE MATHER
VA MEDICAL CENTER CAMPUS, THUS A NEW MIRCOM
ADDRESSABLE FIRE ALARM SYSTEM IS THE PREFERRED
SOLUTION AS THE FAMILIARITY…