This is an Opinion of Probable Construction Cost document for the Ross Marler Park parking expansion project, prepared for the Board of County Commissioners of Okaloosa County, Florida, Tourist Development Department. The project involves expanding parking capacity at Marler Park with 113 additional parking spaces in anticipation of a new splashpad facility. The scope of work encompasses site preparation and demolition activities including milling existing pavement (706 square yards), demolishing brick (117 square yards), sidewalk (265 square yards), and curbing (309 square yards), along with fence removal, wood post demolition, and tree removal (31 trees). Additionally, the project includes rough grading for a pond (122 cubic yards) and parking areas (330 cubic yards), installation of new asphalt pavement (422 tons), concrete curb (1,550 linear feet), concrete sidewalk (278 square yards), stormwater infrastructure including 18-inch RCP storm pipe (62 linear feet), relocated light poles with junction boxes (8 units), and related site improvements such as wheel stops, silt fencing, and pavement markings.

The subtotal construction cost is estimated at $610,014.52, with a 15 percent contingency of $91,502.18, resulting in a grand total of $701,516.70. Cost data is derived from FDOT Historical Costs for Okaloosa County and statewide data current between March 1, 2025, and February 28, 2026. The estimate explicitly excludes contractor operating costs and profits, permit fees, and bonds. Mobilization costs are estimated at approximately 10 percent of total project cost ($55,000). Notable line items include tree removal ($44,577.69), new asphalt pavement ($72,412.96), optional base material ($91,976.48), relocated light poles ($80,000.00), and concrete curb installation ($55,195.50).

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROSS MARLER PARK

Item Unit Quantity $ per Unit Subtotal

Mobilization (~10% cost) Each 1 $55,000.00 $55,000.00

Maintenance of Traffic Each 1 $1,500.00 $1,500.00

Construction Staking Each 1 $3,500.00 $3,500.00

As-built Survey Each 1 $3,500.00 $3,500.00

Milling 1" Existing Pavement Square Yard 706 $1.68 $1,186.27

Demolish Brick Square Yard 117 $44.58 $5,235.67

Demolish Sidewalk Square Yard 265 $56.04 $14,838.15

Demolish Curbing Square Yard 309 $56.04 $17,310.13

Fence Removal Linear Feet 64 $30.00 $1,920.00

Demolish Wood Posts Each 4 $500.00 $2,000.00

Tree Removal Each 31 $1,437.99 $44,577.69

Clearing & Grubbing Acre 2 $17,463.00 $34,926.00

Rough Grading (Pond) Cubic Yards 122 $12.87 $1,570.14

Rough Grading (Parking) Cubic Yards 330 $12.87 $4,247.10

Construction Entrance Each 1 $5,876.00 $5,876.00

Silt Fence Linear Feet 1,720 $3.53 $6,071.60

Inlet Protection Device Each 3 $187.78 $563.34

Wheel Stops Each 77 $75.00 $5,775.00

New Pavement (3.5" FC-12.5, Traffic C) Tons 422 $171.65 $72,412.96

Optional Base, Base Group 04 Square Yard 2,137 $43.04 $91,976.48

Type B Stabilization Square Yard 2,137 $11.03 $23,571.11

Overlay 1" Asphalt Pavement Tons 40 $171.65 $6,834.81

Concrete Curb, Type D Linear Feet 1,550 $35.61 $55,195.50

Concrete Sidewalk (4" Thick) Square Yard 278 $100.58 $27,961.24

Modified Catch Basin Each 1 $2,635.68 $2,635.68

Coring Existing Catch Basin Each 1 $3,500.00 $3,500.00

FDOT Type C Ditch Bottom Inlet Each 1 $6,725.35 $6,725.35

18" RCP Storm Pipe Linear Feet 62 $169.57 $10,513.34

Painted Pavement Markings, Standard, White, Solid, 6" Mile 0.7

$1,404.57 $983.20

Relocated Light Poles with Junction Boxes Each 8 $10,000.00 $80,000.00

ADA Parking Sign Post, Single Column Each 4 $560.64 $2,242.56

Rip Rap Tons 135 $117.52 $15,865.20

Subtotal $610,014.52

Contingency (15%) $91,502.18

Grand Total $701,516.70

*Cost Data from FDOT Historical Costs (between 03/01/25 to 02/28/26 for Okaloosa County) and FDOT Historical Costs

(between 03/01/25 to 02/28/26 for Statewide)

** This estimate does not include Contractor's Operating Costs and Profits, Permit Fees, or Bonds

File details come from the government source that posted it. Updated .