Beasley_Opinion_of_Probable_Construction_Cost.pdf

PDF 57 KB Posted

Attached to
John Beasley and Ross Marler Parking Expansion
Solicitation number
ITB TDD 65-26
Issued by
Okaloosa County, Florida

About this file

This is an Opinion of Probable Construction Cost document prepared for the Board of County Commissioners of Okaloosa County, Florida's Tourist Development Department in connection with parking expansion projects at John Beasley Park and Ross Marler Park. The project scope includes the addition of 114 parking spaces at John Beasley Park and 113 parking spaces at Marler Park to accommodate increased patron capacity, with the Marler Park expansion undertaken in anticipation of a planned splashpad facility. The document provides detailed cost estimates and breakdowns for the construction work necessary to complete both parking area expansions.

The Opinion of Probable Construction Cost establishes the financial parameters for the proposed parking expansion projects, detailing estimated costs for site preparation, parking lot construction, drainage, lighting, landscaping, and other associated infrastructure improvements. This cost opinion serves as a planning and budgeting tool for Okaloosa County to evaluate project feasibility and establish funding requirements for the dual parking expansion initiatives. The document supports the county's capital planning process and provides the basis for budget allocation and procurement activities related to these tourist development improvements.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JOHN BEASLEY PARK

Item Unit Quantity $ per Unit Subtotal

Mobilization (~10% cost) Each 1 $50,000.00 $50,000.00

Maintenance of Traffic Each 1 $1,500.00 $1,500.00

Construction Staking Each 1 $3,500.00 $3,500.00

As-built Survey Each 1 $3,500.00 $3,500.00

Milling 1" Existing Pavement Square Yard 3,194 $1.68 $5,365.17

Demolish Sidewalk Square Yard 26 $56.04 $1,481.95

Fence Removal Linear Feet 332 $30.00 $9,960.00

Demolish Wood Posts Each 43 $300.00 $12,900.00

Tree Removal Each 16 $1,437.99 $23,007.84

Clearing & Grubbing Acre 1 $17,463.00 $17,463.00

Rough Grading (Pond) Cubic Yards 111 $12.87 $1,428.57

Rough Grading (Parking) Cubic Yards 650 $12.87 $8,365.50

Construction Entrance Each 1 $5,876.00 $5,876.00

Silt Fence Linear Feet 1,826 $3.53 $6,445.78

New Wheel Stops Each 129 $75.00 $9,675.00

Relocated Wheel Stops Each 93 $25.00 $2,325.00

New Pavement (3.5" FC-12.5, Traffic C) Tons 571 $171.65 $98,062.59

Optional Base, Base Group 04 Square Yard 2,895 $43.04 $124,581.67

Type B Stabilization Square Yard 2,895 $11.03 $31,926.95

Overlay 1" Asphalt Pavement Tons 180 $171.65 $30,912.06

Concrete Curb, Type D Linear Feet 230 $35.61 $8,190.30

Concrete Sidewalk (4" Thick) Square Yard 451 $100.58 $45,372.76

Painted Pavement Markings, Standard, White, Solid, 6" Mile 1.0

$1,404.57 $1,404.57

Thermoplastic, White, Directional Arrow Each 18 $100.00 $1,800.00

Relocated Light Poles with Junction Boxes Each 4 $10,000.00 $40,000.00

Rip Rap Tons 125 $117.52 $14,703.25

Subtotal $559,747.96

Contingency (15%) $83,962.19

Grand Total $643,710.15

*Cost Data from FDOT Historical Costs (between 03/01/25 to 02/28/26 for Okaloosa County) and FDOT Historical Costs (between

03/01/25 to 02/28/26 for Statewide)

** This estimate does not include Contractor's Operating Costs and Profits, Permit Fees, or Bonds