This is a Line Item Pricing Sheet for an Indefinite Delivery Indefinite Quantity (IDIQ) contract for demolition and abatement services at VA New Jersey Health Care System (VANJHCS) facilities in East Orange and Lyons, New Jersey. The contract has a five-year term with a minimum value of $10,000 and maximum value of $2,000,000. The pricing sheet establishes estimated annual quantities and unit pricing structures for 55 line items across two primary service categories: general demolition activities and abatement demolition activities that must comply with Infection Control Risk Assessment (ICRA) Level 4 standards for hospital work.

General demolition line items (1-28) cover removal of flooring, walls, drywall, partitions, tiles, wall coverings, doors, electrical components, fixtures, plumbing, and furniture, with quantities ranging from 2 to 150 units and unit measurements in square feet, linear feet, or each. Abatement line items (29-52) address asbestos-containing material (ACM) removal, lead-based paint removal, Transite-type material removal, and glovebag operations, with quantities ranging from 0 to 200 units. The pricing sheet includes base-year unit costs (all currently listed as $0.00 pending contractor proposals), with option-year pricing escalating at 3% annually compounded over a four-year option period. Additional provisions include mobilization/demobilization fees, performance bond requirements for projects exceeding $35,000, emergency call-in services with 30-minute response time and 2-hour on-site arrival requirement, and rate multipliers for off-hours and weekend work. All work must comply with New Jersey Administrative Code regulations governing asbestos abatement and licensing, with material testing and air monitoring provided by the government at no contractor cost.

View the file

Other files

File Type Posted
36C24226Q0857 0003.docx DOCX document
LINE ITEM PRICING SHEET LYN-EO DEMOLITION AND ABATEMENT REVISED.xlsx XLSX spreadsheet
EXHIBIT C - Past Performance Questionnaire - revised v2.docx DOCX document
VAAR 852.219-75 corrected.docx DOCX document
36C24226Q0857 0002.docx DOCX document
WD Somerset 8-13.docx DOCX document
36C24226Q0857 0001.docx DOCX document
EXHIBIT C - Past Performance Questionnaire - revised.docx DOCX document
WD Somerset.docx DOCX document
EXHIBIT C - Past Performance Questionnaire.docx DOCX document
VAAR 852.219-75.docx DOCX document
WD Essex.docx DOCX document
EXHIBIT B - Sample Transmittal Letter for Past Performance Evaluation Questionnaire.docx DOCX document
36C24226Q0857_1.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

New IDIQ

VHANJHS DEMOLITION AND ABATEMENT ID INDEPENDENT GOVERNMENT COST ESTIMATE.
WORKING ESTIMATE: Base-year unit costs reflect the available baseline increased by 20%. Option-year unit prices escalate 3% annually, compounded. Review and revise individual line items as needed.
Item
No.:Description of Tasks:Units:Div.:Est.

Annual Quantity: Price Per Unit (Year 1) Price Per Unit (Year 2) Price Per Unit (Year 3) Price Per Unit (Year 4) Price Per Unit (Option Year IV) Extended Price (Base Year) Extended Price (Option Year I) Extended Price (Option Year II) Extended Price (Option Year III) Extended Price (Option Year IV)

GENERAL DEMOLITION ACTIVITIES ARE REQUIRED TO MEET INFECTION CONTROL RISK ASSESSMENT (ICRA) LEVEL 4 FOR WORK INSIDE OF THE HOSPITAL
1.0Removal of existing flooring and associated adhesives (•Subfloor to be free of all residue and ground to a flat, smooth finish)SFD120.00$0.00$0.00$0.00$0.00$0.00
2.0Removal of partition metal stud and drywall with or without plaster skim coat and flattened expanded metal fastened to metal studs, including demountable partitions and repair damage to other wall surfaces. Remove all debris from Government property.SFD35.00$0.00$0.00$0.00$0.00$0.00
3.0Removal of drywall with or without plaster skim coat on one side of partition or wall. Remove all debris from Government property.SFD150.00$0.00$0.00$0.00$0.00$0.00
4.0Removal of wall protection, including but not limited to IPC rigid vinyl sheets and removal of all debris from Government property.LFD40.00$0.00$0.00$0.00$0.00$0.00
5.0Removal of masonry style wall, including removal of all debris from Government property.EAD9.00$0.00$0.00$0.00$0.00$0.00
6.0Removal of existing ceramic, porcelain, or quarry tile (wall and floor) and associated thinset/mortarSFD3.00$0.00$0.00$0.00$0.00$0.00
7.0Removal of existing flooring and associated adhesives (• Subfloor to be free of all residue and ground to a flat, smooth)SFD4.00$0.00$0.00$0.00$0.00$0.00
8.0Remove wall covering, vinyl or fabric, including cleaning of the wall surface and remove from the Government property.SFD20.00$0.00$0.00$0.00$0.00$0.00
9.0Remove door and frame from masonry type wall. Door and frame shall be removed from Government property unless requested to be returned to the Government.SFD2.00$0.00$0.00$0.00$0.00$0.00
10.0Remove door and frame from drywall and/or demountable partition. Door and frame shall be removed from Government property unless requested to be returned to the Government.SFD3.00$0.00$0.00$0.00$0.00$0.00
11.0Remove lockset from existing door and return to the Government.LFD7.00$0.00$0.00$0.00$0.00$0.00
12.0Remove ceiling tile and suspension system, any type, and remove from the Government property.LFD20.00$0.00$0.00$0.00$0.00$0.00
13.0Remove ceiling tile only and remove from the Government property.SFD20.00$0.00$0.00$0.00$0.00$0.00
14.0Remove plaster style or solid ceiling, any type, and remove from Government propertySFD2.00$0.00$0.00$0.00$0.00$0.00
15.0Remove light fixture any type including exit, emergency light.SFD5.00$0.00$0.00$0.00$0.00$0.00
16.0Remove electrical switch, any type. Remove electrical wall receptacle, any type including wiring up to 50'-0".SFD2.00$0.00$0.00$0.00$0.00$0.00
17.0Remove rigid style conduit, including installed feeders (not powered) up to 2 inches in diameter and remove from the Government property.EAD4.00$0.00$0.00$0.00$0.00$0.00
18.0Remove rigid style conduit, including installed feeders (not powered) larger than 2 inches in diameter and remove from the Government property.EAD2.00$0.00$0.00$0.00$0.00$0.00
19.0Remove electrical floor/wall receptacle flush or pedestal and provide cap and plug assembly. Remove telephone floor/wall, data, or communication outlet and provide cover when needed.SFD1.00$0.00$0.00$0.00$0.00$0.00
20.0Removal of furniture, remove from Government property unless requested to be returned to the Government. Price shall be determined by the number of items.CYD3.00$0.00$0.00$0.00$0.00$0.00
21.0Remove carpet tack-less method, glued down, or carpet tile including cleaning of the floor surface to remove residual glue and remove from the Government property.EAD10.00$0.00$0.00$0.00$0.00$0.00
22.0Remove carpet pad any type and remove all debris from Government property, including cleaning of the floor surface.SFD10.00$0.00$0.00$0.00$0.00$0.00
23.0Remove cove base molding or carpet base and remove from the Government property.LFD5.00$0.00$0.00$0.00$0.00$0.00
24.0Remove resilient floor tile, including cleaning of the floor surface and remove all debris from Government property.SFD3.00$0.00$0.00$0.00$0.00$0.00
25.0Removal of plumbing fixtures, including but not limited to toilets, sinks, urinals, restroom partitions, etc.JBD3.00$0.00$0.00$0.00$0.00$0.00
26.0Removal of abandoned or isolated plumbing supply or return lines smaller than 2 inches in diameter.LFD3.00$0.00$0.00$0.00$0.00$0.00
27.0Removal of abandoned or isolated plumbing supply or return lines greater than 2 inches in diameter.LFD3.00$0.00$0.00$0.00$0.00$0.00
28.0Mobilization/Demobilization fee for all demolition activities.JBD3.00$0.00$0.00$0.00$0.00$0.00
ABATEMENT DEMOLITION ACTIVITIES ARE REQUIRED TO MEET INFECTION CONTROL RISK ASSESSMENT (ICRA)
29.0Removal, clean-up and disposal of asbestos containing material (ACM) and asbestos/waste related contaminated elements or debris of flooring and mastic (multiple layers will double the SF).SFAB200.00$0.00$0.00$0.00$0.00$0.00
30.0Removal, clean-up and disposal of asbestos containing material (ACM) and asbestos/waste related contaminated elements or debris of only flooring (multiple layers will double the SF).SFAB25.00$0.00$0.00$0.00$0.00$0.00
31.0Removal, clean-up and disposal of asbestos containing material (ACM) and asbestos/waste related contaminated elements or debris of only mastic (multiple layers will double the SF).SFAB55.00$0.00$0.00$0.00$0.00$0.00
32.0Removal, clean-up and disposal of asbestos containing material (ACM) and asbestos/waste related contaminated elements or debris of carpet.SFAB30.00$0.00$0.00$0.00$0.00$0.00
33.0Glovebag removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation up to 2 inches in diameter.LFAB0.00$0.00$0.00$0.00$0.00$0.00
34.0Glovebag removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation between 2 inches - 6 inches in diameter.LFAB75.00$0.00$0.00$0.00$0.00$0.00
35.0Glovebag removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation larger than 6 inches in diameter.LFAB20.00$0.00$0.00$0.00$0.00$0.00
36.0Glovebag removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of fittings, saddle blocks, valves, T's or other mechanical appurtenances 2 inches to 6 inches in diameter.JBAB40.00$0.00$0.00$0.00$0.00$0.00
37.0Removal and disposal of lead-based paint from Government property.SFAB5.00$0.00$0.00$0.00$0.00$0.00
38.0Removal, clean-up and disposal of asbestos containing material (ACM) and asbestos/waste related contaminated elements of Transite-type materials.SFAB9.00$0.00$0.00$0.00$0.00$0.00
39.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of Transite-type pipe up to 2 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
40.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of Transite-type pipe between 2 inches - 6 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
41.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of Transite-type pipe larger than 6 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
42.0Removal (above glovebag limit), clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation up to 2 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
43.0Removal (above glovebag limit), clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation between 2 inches - 6 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
44.0Removal (above glovebag limit), clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of pipe insulation larger than 6 inches in diameter.LFAB10.00$0.00$0.00$0.00$0.00$0.00
45.0Removal (above glovebag limit), clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of fittings, saddle blocks, valves, T's or other mechanical appurtenances 2 inches to 6 inches in diameter.JBAB5.00$0.00$0.00$0.00$0.00$0.00
46.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of duct insulation.SFAB5.00$0.00$0.00$0.00$0.00$0.00
47.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of radiator insulation and mastic.SFAB20.00$0.00$0.00$0.00$0.00$0.00
48.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of plaster ceiling/wall.SFAB5.00$0.00$0.00$0.00$0.00$0.00
49.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of drywall and/or drywall joint compound.SFAB13.00$0.00$0.00$0.00$0.00$0.00
50.0Removal, clean-up and disposal of asbestos containing material and asbestos/waste related contaminated elements of miscellaneous material.SFAB50.00$0.00$0.00$0.00$0.00$0.00
51.0Mobilization/Demobilization fee for all Abatement Activities at above the glovebag limit.JBAB2.00$0.00$0.00$0.00$0.00$0.00
52.0Mobilization/Demobilization fee for all Abatement Activities at or below the glovebag limit.JBAB2.00$0.00$0.00$0.00$0.00$0.00
53Emergency Call-In Service shall respond to that call within thirty (30) minutes and be onsite within two (2) hours ready to mobilize associated with any of the above services.EACI2.00$0.00$0.00$0.00$0.00$0.00
55Performance Bonds (individual projects above $35,000.00)(LEAVE BLANK)
OFF-HOURS AND WEEKEND WORK
54Rate multiplier for any of the above services to be performed off-hours or during the weekend.(ENTER RATE MULTIPLER ONLY)
Yearly Subtotal:$0.00$0.00$0.00$0.00$0.00
UNITS/Division KeyTotal Evaluated Price:
DDemolition Line Items$0.00
ABAbatement Activity - Includes removal, encapsulation, enclosure, clean-up and disposal of ACM and record keeping as requested by the VA. Contract to follow all requirements detailed in "12 NYCRR part 56".
CIEmergency Call-In
OHOff-Hour and Weekend Work Multiplier
UKUnits Key:
SFSquare Feet
LFLinear Feet
JBJob
PBPerformance Bonds (individual projects above $35,000.00)
FOR OFFICIAL GOVERNMENT USE ONLY

File details come from the government source that posted it. Updated .