This is a Statement of Work (SOW) for a five-year Indefinite Delivery Contract (IDIQ) supporting demolition and abatement services at two VA New Jersey Health Care System (VANJHCS) medical facilities: East Orange VA Medical Center (385 Tremont Ave, East Orange, NJ 07018) and Lyons VA Medical Center (151 Knollcroft Rd, Lyons, NJ 07939). The contract has a minimum value of $10,000 and a maximum value of $2,000,000, with work to be performed on an as-needed basis through task orders issued by the Government. The contractor must provide all labor, materials, equipment, tools, transportation, supervision, safety management, quality control, and project management necessary to complete demolition and abatement tasks as defined in the contract line items.

All work must comply with applicable Infection Control requirements, New Jersey Administrative Code (NJAC) 5:23-8 (Asbestos Hazard Abatement Subcode), and NJAC 12:120 governing asbestos abatement, licensing, and permitting. Material testing and air monitoring services required for asbestos removal are provided by VANJHCS at no cost to the contractor. The SOW amendments add specification 02 82 13.13 (Glovebag Asbestos Abatement) to the scope and address vendor questions. No work outside the defined SOW may be performed without written Contracting Officer authorization, as unauthorized work may be deemed an Unauthorized Commitment (UAC) and will not be reimbursed.

View the file

Other files

File Type Posted
36C24226Q0857 0003.docx DOCX document
VAAR 852.219-75 corrected.docx DOCX document
36C24226Q0857 0002.docx DOCX document
LINE ITEM PRICING SHEET LYN-EO DEMOLITION AND ABATEMENT REVISED.xlsx XLSX spreadsheet
EXHIBIT C - Past Performance Questionnaire - revised v2.docx DOCX document
36C24226Q0857 0001.docx DOCX document
EXHIBIT C - Past Performance Questionnaire - revised.docx DOCX document
LINE ITEM PRICING SHEET LYN-EO DEMOLITION AND ABATEMENT.xlsx XLSX spreadsheet
WD Somerset.docx DOCX document
EXHIBIT C - Past Performance Questionnaire.docx DOCX document
VAAR 852.219-75.docx DOCX document
WD Essex.docx DOCX document
EXHIBIT B - Sample Transmittal Letter for Past Performance Evaluation Questionnaire.docx DOCX document
36C24226Q0857_1.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"General Decision Number: NJ20260042 08/13/2026

State: New Jersey

Construction Types: Building

Counties: New Jersey Counties of Somerset

Modification Number Publication Date 0 01/02/2026 1 05/18/2026 2 08/13/2026

ASBE0032-007 09/19/2024

Rates Fringes

ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES

THE APPLICATION OF ALL INSULATING MATERIALS,

PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO

ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE

APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS

AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND

CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET

COUNTY (BOROUGHS OF BERNARDSVILLE AND BOUND BROOK;

TOWNSHIP OF BRIDGEWATER; BOROUGH OF FAR HILLS;

TOWNSHIP OF GREEN BROOK; BOROUGHS OF NORTH

PLAINFIELD, PEAPACK-GLADSTONE, RARITAN, SOMERVILLE,

SOUTH BOUND BROOK AND WATCHUNG; TOWNSHIP OF WARREN).$ 51.74 46.20

ASBE0089-007 07/01/2024

Rates Fringes

ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES

THE APPLICATION OF ALL INSULATING MATERIALS,

PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO

ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE

APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS

AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND

CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (SOMERSET

COUNTY (TOWNSHIPS OF BRANCHBURG, FRANKLIN,

HILLSBOROUGH AND MONTGOMERY))

PAID HOLIDAYS:

THE LAST DAY PRIOR TO THE CHRISTMAS AND NEW YEAR'S

DAY OBSERVED HOLIDAY: 4 HRS. PAY....................$ 55.80 40.80

BRNJ0002-013 05/01/2021

Rates Fringes

BRICKLAYER (WORK ON HIGH STACKS: 22% PER HOUR

ADDITIONAL.)

.................................$ 45.20 33.26

BRNJ0004-001 05/01/2025

Rates Fringes

CEMENT MASON........................................$ 49.60 37.96

BRNJ0007-001 06/02/2025

Rates Fringes

TILE SETTER.........................................$ 64.90 37.28

TILE FINISHER (WORK GROUTING ALL EPOXY: $10.00

ADDITIONAL PER DAY.)................................$ 50.05 33.90

CARP0006-009 05/01/2025

Rates Fringes

CARPENTER: SCAFFOLD BUILDER (THE FIRST SIXTY FEET

AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR

EACH ADDITIONAL FIFTY FEET THEREAFTER.)

........$ 57.42 34.17

CARP0006-011 05/01/2025

Rates Fringes

CARPENTER: INCLUDING ACOUSTICAL CEILING

INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND

BLOWN INSULATION....................................$ 57.42 34.17

CARP0715-007 05/01/2025

Rates Fringes

MILLWRIGHT (WORK OF ERECTION AND DISMANTLING OF

ELEVATORS AND TOWERS, SUCH AS CONCRETE CONVEYORS

AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR

OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE

OR OUTSIDE OF BUILDINGS: THE FIRST SIXTY FEET AT

THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH

ADDITIONAL FIFTY FEET THEREAFTER.)..................$ 58.84 35.06

ELEC0102-022 06/02/2025

Rates Fringes

ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET

COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN

EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE

RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE

MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD;

THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND

RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE

MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE

TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE

FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31)

NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.;

THEN, WEST ALONG HARLINGEN RD. AND THE

DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP

LINE) (WORK FORTY FT. OR MORE ABOVE THE GROUND OR

PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR

TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10%

PER HOUR ADDITIONAL.) (WORK WITH, OR THE REMOVAL

OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN

RATE.)..............................................$ 65.43 42.86

ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE

WIRING) (SOMERSET COUNTY (DOES NOT INCLUDE THE

TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR

GROVE LANE FROM THE RARITAN RIVER, IN A

SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF

THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE

RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN,

SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE;

DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST

AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206

(FORMERLY STATE HWY. 31) NORTH FROM THE MERCER

COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG

HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE

HILLSBOROUGH TOWNSHIP LINE) (WORK FORTY FT. OR

MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES

NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR

HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL.)

(WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS:

112% TIMES THE JOURNEYMAN RATE.)....................$ 69.72 44.27

ELEC0269-019 07/07/2025

Rates Fringes

ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET

COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A

LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY.

31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN

RD.; THEN, WEST ALONG HARLINGEN RD. AND THE

DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP

LINE)))

..........................................$ 61.84 40.32

ELEC0456-007 05/30/2022

Rates Fringes

ELECTRICIAN: INCLUDING LOW VOLTAGE WIRING (SOMERSET

COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE

FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER,

IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE

BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST

ALONG THE RAILROAD TO THE DELAWARE AND RARITAN

CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX

COUNTY LINE)) (WORK ON LINE VOLTAGE OF 440 VOLTS

AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM

TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM

THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER

CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER

HOUR ADDITIONAL.)...................................$ 55.85 39.79

ELECTRICIAN: CABLE SPLICER (INCLUDING LOW VOLTAGE

WIRING) (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN

(EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE

RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE

MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD;

THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND

RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE

MIDDLESEX COUNTY LINE)) (WORK ON LINE VOLTAGE OF

440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK

FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE

FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR

OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY:

10% PER HOUR ADDITIONAL.)...........................$ 65.35 46.56

ELEV0001-003 03/17/2013

Rates Fringes

ELEVATOR MECHANIC: ALL OTHER WORK (PAID

HOLIDAYS:NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD

FRIDAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY,

COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, THE

FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS

DAY.)(PAID VACATION:A WORKER WHO HAS WORKED LESS

THAN 5 YEARS: 4% OF HIS OR HER HOURLY RATE FOR ALL

HOURS WORKED. A WORKER WHO HAS WORKED 5 TO 10

YEARS: 6% OF HIS OR HER HOURLY RATE FOR ALL HOURS

WORKED. A WORKER WHO HAS WORKED 15 OR MORE YEARS:

8% OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED.)

...........................................$ 57.01 27.61

ELEVATOR MECHANIC: WORK ON THE ADDITION,

REPLACEMENT, REFURBISHING OR RELOCATION OF CONTROL,

DRIVE, GENERATING EQUIPMENT, HOISTWAY OR PIT

EQUIPMENT, INCLUDING WORK INVOLVING A STRUCTURAL

RISE IN THE ELEVATOR SHAFTS IN AN EXISTING BUILDING

AND OTHER ELEVATOR WORK IN THE MACHINE ROOM,

HOISTWAY OR PIT; ALSO, CHANGES IN DESIGN AND

APPEARANCE OF BASIC ESCALATOR EQUIPMENT (PAID

HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD

FRIDAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY,

COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY, THE

FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY.)

(PAID VACATION: A WORKER WHO HAS WORKED LESS THAN 5

YEARS: 4% OF HIS OR HER HOURLY RATE FOR ALL HOURS

WORKED. A WORKER WHO HAS WORKED 5 TO 10 YEARS: 6%

OF HIS OR HER HOURLY RATE FOR ALL HOURS WORKED. A

WORKER WHO HAS WORKED 15 OR MORE YEARS: 8% OF HIS

OR HER HOURLY RATE FOR ALL HOURS WORKED.)

....$ 45.14 27.46

ENGI0825-020 07/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR: GROUP 5 OILER (HAZARDOUS

WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY

DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER

IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND

WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR

RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR

ADDITIONAL.) PAID HOLIDAYS: NEW YEAR'S DAY,

WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION

DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS

DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE

PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR,

THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY

AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS

THE WORK DAY BEFORE AND THE WORK DAY AFTER THE

HOLIDAY.............................................$ 52.88 37.50

POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID

LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT

END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER,

GRADE; PUMP, HYDRAULIC (HAZARDOUS WASTE REMOVAL

WORK: WORK ON A STATE OR FEDERALLY DESIGNATED

HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT

CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL

PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY,

SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S

BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY,

LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S

DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED

1) THAT THE WORKER WORKS THREE OF THE PRECEDING

FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY

BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE

HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY

BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 56.59 37.50

POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT SPREADER;

BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN

100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD.

AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC;

PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR

(HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR

FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE

THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS

MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS

REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION:

20% PER HOUR ADDITIONAL.) PAID HOLIDAYS: NEW

YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED,

MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,

PRESIDENTIAL ELECTION DAY, VETERAN'S DAY,

THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1)

THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE

WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY

BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE

HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY

BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 58.22 37.50

POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER

COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH);

HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT

END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.);

SCRAPER; SIDE BOOM (HAZARDOUS WASTE REMOVAL WORK:

WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS

WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT

WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL

PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY,

SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S

BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY,

LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S

DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED

1) THAT THE WORKER WORKS THREE OF THE PRECEDING

FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY

BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE

HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY

BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 60.13 37.50

POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE,

INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING

MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND

STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE

DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC

DRILL, SELF-POWERED DRILL); ELEVATING GRADER;

EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER);

PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF

LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE);

TRENCHER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A

STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE,

WHERE THE WORKER IS IN DIRECT CONTACT WITH

HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE

EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE

PROTECTION: 20% PER HOUR ADDITIONAL.) PAID

HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY

OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR

DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY,

THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1)

THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE

WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY

BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE

HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY

BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 61.72 37.50

IRON0011-010 07/01/2025

Rates Fringes

IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER

(SOMERSET COUNTY (NORTHERN HALF OF COUNTY)).........$ 52.24 50.32

IRONWORKER: REINFORCING (SOMERSET COUNTY (NORTHERN

HALF OF COUNTY))....................................$ 49.94 50.32

IRON0399-018 07/01/2024

Rates Fringes

IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER

(SOMERSET COUNTY (SOUTHERN HALF OF COUNTY)).........$ 54.24 38.40

IRONWORKER: REINFORCING (SOMERSET COUNTY (SOUTHERN

HALF OF COUNTY))....................................$ 53.24 38.40

LABO0008-001 05/01/2011

Rates Fringes

LABORER: ASBESTOS REMOVAL (THE REMOVAL, ABATEMENT,

ENCLOSURE AND DECONTAMINATION OF PERSONAL

PROTECTIVE EQUIPMENT, CHEMICAL PROTECTIVE CLOTHING

AND MACHINERY RELATING TO ASBESTOS AND/OR TOXIC AND

HAZARDOUS WASTE OR MATERIALS WHICH SHALL INCLUDE

BUT NOT NECESSARILY BE LIMITED TO: THE ERECTION,

MOVING, SERVICING AND DISMANTLING OF ALL

ENCLOSURES, SCAFFOLDING AND BARRICADES; THE

OPERATION OF ALL TOOLS AND EQUIPMENT NORMALLY USED

IN THE REMOVAL OR ABATEMENT OF ASBESTOS AND TOXIC

OR HAZARDOUS WASTE OR MATERIALS; THE LABELING,

BAGGING, CARTONING, CRATING, OR OTHER PACKAGING OF

MATERIALS FOR DISPOSAL; THE CLEAN-UP OF THE

WORKSITE; AND ALL OTHER WORK INCIDENTAL TO THE

REMOVAL, ABATEMENT, ENCAPSULATION, ENCLOSURE, AND

DECONTAMINATION OF ASBESTOS AND TOXIC OR HAZARDOUS

WASTE OR MATERIALS; AND, IN ADDITION, ALL WORK

TASKS INVOLVED IN THE MAINTENANCE AND OPERATION OF

ENERGY RESOURCE RECOVERY PLANTS (CO-GENERATION

PLANTS))............................................$ 28.37 21.62

LABO0077-002 05/01/2022

Rates Fringes

LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE........$ 36.50 30.22

LABO0077-005 05/01/2022

Rates Fringes

LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON

OR GENERAL LABORER, LANDSCAPE LABORER, POWER TOOL

OPERATOR AND SCREEDMAN..............................$ 35.75 30.22

PAIN0711-018 05/01/2025

Rates Fringes

DRYWALL FINISHER/TAPER..............................$ 44.87 30.15

PAIN0711-020 05/01/2025

Rates Fringes

PAINTER: BRUSH AND ROLLER...........................$ 45.55 29.86

PAINTER: PAPERHANGER................................$ 45.55 29.86

PAINTER: SPRAY......................................$ 45.55 29.86

PAIN0711-021 05/01/2025

Rates Fringes

GLAZIER (WORK WELDING OR USING A CUTTING TORCH:

$1.00 PER HOUR ADDITIONAL.) (WORK ON A SWING STAGE

SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING

HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON

MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE

LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE

THIRTY FEET: $1.00 PER HOUR ADDITIONAL.)............$ 52.68 31.29

PLAS0008-008 05/01/2021

Rates Fringes

PLASTERER...........................................$ 38.37 31.64

PLUM0009-020 07/01/2025

Rates Fringes

PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET

COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY

HILL))..............................................$ 59.57 46.45

PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION

(SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH

OF ROCKY HILL)).....................................$ 59.57 46.45

PLUMBER/PIPEFITTER: SERVICE AND REPAIR (SOMERSET

COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY

HILL))..............................................$ 46.23 29.23

PLUM0024-011 05/01/2025

Rates Fringes

PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (SOMERSET

COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF

MONTGOMERY; BOROUGH OF ROCKY HILL)).................$ 62.09 45.05

PLUM0475-012 05/01/2025

Rates Fringes

PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION

(SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF

MONTGOMERY; BOROUGH OF ROCKY HILL)).................$ 56.34 50.80

ROOF0004-004 06/01/2024

Rates Fringes

ROOFER: ALL TYPES

(SOMERSET COUNTY

(NORTH OF A LINE DRAWN FROM THE MERCER/SOMERSET

COUNTY LINE ALONG ROUTE #206 NORTH TO ROUTE #514;

THEN, WEST ALONG ROUTE #514 TO THE

HUNTERDON/SOMERSET COUNTY LINE))....................$ 44.52 32.25

ROOF0030-029 05/01/2025

Rates Fringes

ROOFER: SLATE AND TILE (SOMERSET COUNTY (SOUTH OF A

LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE

NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST

ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY

LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE:

$0.50 PER HOUR ADDITIONAL.) ( WORK APPLYING ROOFING

MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE

DAYS ON WHICH A FELT-LAYING MACHINE OR

SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR

ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY

BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR

HOURS PAY.).........................................$ 38.95 21.85

ROOFER: SHINGLES (SOMERSET COUNTY (SOUTH OF A LINE

DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH

ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG

ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY LINE)

(MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50

PER HOUR ADDITIONAL.) (WORK APPLYING ROOFING

MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE

DAYS ON WHICH A FELT-LAYING MACHINE OR

SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR

ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY

BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR

HOURS PAY.).........................................$ 35.95 21.85

ROOFER: ALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A

LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE

NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST

ALONG ROUTE #514 TO THE HUNTERDON/SOMERSET COUNTY

LINE) (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE:

$0.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING

MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE

DAYS ON WHICH A FELT-LAYING MACHINE OR

SLAG-DISPENSING MACHINE IS USED: $0.50 PER HOUR

ADDITIONAL.) (PAID HOLIDAY: THE LAST WORKING DAY

BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR

HOURS PAY.).........................................$ 46.03 34.27

SFNJ0669-008 07/01/2025

Rates Fringes

SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY

(TOWNSHIPS OF BRANCHBURG AND MONTGOMERY; BOROUGH OF

ROCKY HILL))........................................$ 49.97 41.35

SFNJ0696-004 01/01/2025

Rates Fringes

SPRINKLER FITTER: FIRE SPRINKLERS (SOMERSET COUNTY

(REMAINDER OF COUNTY))..............................$ 67.97 39.35

SHEE0025-005 06/01/2024

Rates Fringes

SHEET METAL WORKER: INCLUDING HVAC DUCT

INSTALLATION........................................$ 51.30 51.55

TEAM0469-005 05/01/2025

Rates Fringes

TRUCK DRIVER: OFF THE ROAD TRUCK (HAZARDOUS WASTE

REMOVAL WORK: WORK ON A STATE OR FEDERALLY

DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER

IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND

WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR

RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER

HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY

DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE

REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY

WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR

ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED

HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT

WORKING IN A ZONE REQUIRING LEVEL A, B OR C

PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.

(PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY,

DECORATION DAY, INDEPENDENCE DAY, LABOR DAY,

PRESIDENTIAL ELECTION DAY, VETERAN'S DAY,

THANKSGIVING DAY AND CHRISTMAS DAY.) (VACATION PAY

CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80

DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION

(48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID

VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID

VACATION (120 HOURS); 15 YEARS SENIORITY AND 145

DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)).

...................................................$ 48.78 42.66

TRUCK DRIVER: DUMP TRUCK (HAZARDOUS WASTE REMOVAL

WORK: WORK ON A STATE OR FEDERALLY DESIGNATED

HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT

CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL

PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY,

SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL.

WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS

WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL

PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK

DRIVER: $3.00 PER HOUR

WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS

WASTE SITE WHERE THE WORKER IS NOT WORKING IN A

ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION:

$1.00 PER HOUR ADDITIONAL.) (PAID HOLIDAYS: NEW

YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY,

INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION

DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS

DAY.) (VACATION PAY CREDIT: WORKERS WORKING OR

RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE

WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO

WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15

DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY

AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160

HOURS)).

..................$ 48.63 42.66

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than �SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The �SU� identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

�SU� wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The �SA� identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the �SA� identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION