Amendment 4 dated 3-10-25.pdf

PDF 245 KB Posted

Attached to
Furnish and Deliver Two (2) 10, 000 Gallon Above Ground Fuel Storage Tanks
Solicitation number
JF459868
Issued by

About this file

Amendment No. 4 for Solicitation JF459868 provides clarification on the procurement of two 10,000-gallon above-ground fuel storage tanks for the Department of Energy Office of Science at Brookhaven National Laboratory. The amendment addresses key questions regarding equipment and installation responsibilities, confirming that the contractor will furnish the fuel master dispenser and piping, while Brookhaven National Laboratory (BNL) will handle installation of the fuel master dispenser, FM LIVE module, and system start-up. The tanks are to be delivered as a pre-assembled package, with BNL coordinating offloading and placement on the tank pad, and the contractor is expected to provide piping based on their product specifications and referenced standards in the statement of work.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

Procurement and Property Management Building 902B P.O. Box 5000

Upton, NY 11973-5000

Date: 3/10/25

AMENDMENT NO. 4

to Solicitation No. 459868 for

TWO (2) 10,000 GALLON ABOVE GROUND FUEL STORAGE TANKS

GENERAL: This Amendment No. 4 is issued to answer the following questions:

Question 1. There seems to be conflicting responses. Can you please clarify, Who is furnishing the fuel master dispenser?

Who is furnishing the FM LIVE module?

Who is installing the fuel master dispenser?

Who is installing the FM LIVE module?

Answer 1.

Who is furnishing the fuel master dispenser? Contractor Who is furnishing the FM LIVE module? BNL

Who is installing the fuel master dispenser? BNL Who is installing the FM LIVE module? BNL

2 | P a g e

Question 2. Is the intent for the tanks and fuel system components to come as a complete pre-assembled package that will be delivered to the site and Brookhaven will coordinate, offload and set them on to the tank pad?

Answer 2. Yes

Question 3.

Amendment 2 Question 3 asks, “What are the specifications and requirements for the new dispenser and remote fill piping?” and the answer was “New dispenser and remote fill are to be at the front end of the tank.”

What are the specifications and requirements for the dispenser and remote fill piping?

Are we supplying piping?

What type of piping?

How many feet of piping should be assumed?

Answer 3.

What are the specifications and requirements for the dispenser and remote fill piping?

Reference details and standards provided in the statement of work.

Are we supplying piping? Yes, Contractor to provide.

What type of piping? Reference details and standards provided in the statement of work.

How many feet of piping should be assumed? Contractor to make this assumption based on their product.

Question 4.

Who is responsible for the fuel system start-up?

Answer 4. BNL

End of Amendment No. 4

Date: 3/10/25