This document is a JOC (Job Order Contract) Close-Out Form that must be signed by the Prime Contractor, their Superintendent and Project Manager, as well as the Government Inspector and Project Manager to close out a JOC project. The form provides project information, including the DO# (Delivery Order), tracking number, and job description. It indicates whether the project included an Equipment List, Controls, REFRIG Form, and T&B Report, and whether the Red-Lines were per the Red-Line Drawings, Scope with Drawings, or Scope without Drawings. The signatures of all required parties are needed before the form can be submitted.
The related federal contract opportunity is a Competitive 8(a) SATOC JOC 2025 solicitation issued by the Department of the Army Materiel Command Contracting Command Redstone Arsenal. This is a 100% 8(a) small business set-aside acquisition to provide a full range of new construction, alterations, maintenance, repair, sustainment, restoration, and modernization services for the U.S. Army Garrison and tenant organizations located at Redstone Arsenal. The contract has a 1-year base ordering period with four 1-year optional ordering periods, and a 6-month priced option extension.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOC CLOSE-OUT FORM
This form must be signed by all four persons listed below and turned in with the Red-Lines, EQ List, Controls, REFRIG Form and T&B Report (If not per Red-Line Drawings send forms to 1354 Processor)
Project Information:
DO# W9124P- -F-
Tracking Number
Building Number
Job Description
This Project includes: (circle below) (Yes/Y, No/N, or Submittal/S)
Equipment List Y
Controls Y
REFRIG Form Y
N
N
N
S
S
S
T&B Report Y N S
This Project Red-Lines are: (check correct box)
Per Red-Line Drawings
Per Scope WITH Drawings
Per Scope WITHOUT Drawings
Special Notes: _____________________________
SIGNATURES
(ALL SIGNATURES/DATE REQUIRED BEFORE SUBMITTED)
Prime Contractor Superintendent
Name Printed
DATE
Prime Contractor PM
Name Printed
DATE
Government Inspector
Name Printed
DATE
Government PM
Name Printed
DATE