J10_Progress Chart.xlsx
XLSX spreadsheet 106 KB Posted
- Attached to
- Competitive 8(a) SATOC JOC 2025
- Solicitation number
- Not on record
About this file
The provided document is a Construction Progress Chart for a federal contract opportunity. The key details are:
The contract is for a Job Order Contract (JOC) to provide new construction, alterations, maintenance, repair, sustainment, restoration, and modernization services for the U.S. Army Garrison and tenant organizations located at Redstone Arsenal. The contract is a 100% 8(a) small business set-aside with a NAICS code of 236210 (Industrial Building Construction). The projected period of performance is from June 20, 2025 through June 19, 2030, with a 6-month priced option extension. The place of performance is Redstone Arsenal. The agency involved is the Department of the Army Materiel Command Contracting Command Redstone Arsenal. The Construction Progress Chart provided details the planned and actual progress for various construction tasks such as demolition, architecture, mechanical, communications, plumbing, flooring, and others.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
Construction Progress Chart
Project Description:
Contractor: ________________________ Date:
Contract No: _______________________ Task Order No: _________________ Building No:
Item Contract Feature Wt. Estimated Cost Actual Cost January February March April May June
| 100 | ||||||
| Scheduled | ||||||
| 01 | Demo | 0.0653992883 | $20,400.00 | |||
| Actual | ||||||
| 100 | ||||||
| Scheduled |
AGM: AGM:
| 02 | Arch. | 0.2949379669 | $92,000.00 | |||||
| Actual | 0.0816208765 | |||||||
| 60 | 100 | |||||||
| Scheduled | 0.3379078639 | |||||||
| 03 | Mech. | 0.20 | $62,740.00 | |||||
| Actual | 0.4543214824 |
| Scheduled | 100 | 0.6196646684 | ||||||||||||
| 04 | Comm. Floor | 0.0699996794 | $21,835.00 | |||||||||||
| Actual | 0.9397467381 | |||||||||||||
| 50 | 100 | |||||||||||||
| Scheduled | 1 | |||||||||||||
| 05 | Plumbing | 0.0224409323 | $7,000.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 06 | Flooring | 0.0352643221 | $11,000.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 07 | Ceramic Tile | 0.0093610746 | $2,920.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 08 | Sprinkler System | 0.0160933543 | $5,020.00 | |||||||||||
| Actual | ||||||||||||||
| 80 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 09 | Secondary Power | 0.1272240567 | $39,685.00 | |||||||||||
| Actual | ||||||||||||||
| 60 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 10 | Civil | 0.0259673645 | $8,100.00 | |||||||||||
| Actual | ||||||||||||||
| 10 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 11 | Primary Power | 0.0392075145 | $12,230.00 | |||||||||||
| Actual | ||||||||||||||
| 50 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 12 | Communications | 0.0705286442 | $22,000.00 | |||||||||||
| Actual |
| Scheduled | 100 | ||||||||||
| 13 | Doors | 0.0224409323 | $7,000.00 | ||||||||
| Actual | |||||||||||
| 8.16% | 33.79% | 45.43% | 61.97% | 93.97% | 100.00% | ||||||
| Scheduled | |||||||||||
| TOTAL | 1.00 | $311,930.00 | |||||||||
| Actual |
Attachment J10 Progress Chart 02 May 2023