J.9 List of Deliverables.pdf

PDF 138 KB Posted

Attached to
Oscar Dyson FSV Midlife Extension Program Federal contract opportunity
Solicitation number
1305M224R0081
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This document is an Appendix to a federal solicitation that lists the required deliverables for the Oscar Dyson FSV Midlife Extension Program solicitation. The solicitation is issued by the Department of Commerce National Oceanic and Atmospheric Administration (NOAA) and seeks a contractor to perform the midlife extension work on the Oscar Dyson Fishery Survey Vessel.

The Appendix lists over 200 specific deliverables required, including technical reports, drawings, test data, training materials, manuals, equipment, and other contractual documents such as bonds and subcontracting plans. The deliverables have due dates ranging from proposal submission to one week prior to the end of the contract. Key deliverables include a production schedule, work package network, manpower loading curves, insurance certificates, performance and payment bonds, and revised technical drawings and documentation. The solicitation also references additional potential deliverables outlined in the work specification. Offerors must submit the required deliverables as part of their proposal for this federal contract opportunity.

View the file

Other files for this federal contract opportunity

Other files attached to Oscar Dyson FSV Midlife Extension Program, newest first.
File Type Posted
1305M224R0081-0006.pdf PDF
DY-505-FP25 - Piping Standard Details Rev 04.pdf PDF
1305M224R0081-0005.pdf PDF
DY-085-FA04 - Docking Drawing Rev 4.pdf PDF
1305M224R0081-0004.pdf PDF
S.O. 17218 MANUAL.pdf PDF
1305M224R0081-0003.pdf PDF
1305M224R0081-0002.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification-001.pdf PDF
1305M224R0081-0001.pdf PDF
J.8 Propulsion System Technical Specification.pdf PDF
J.13 AIRs Process Document.docx DOCX document
J.14 SF 1416 Payment Bond.pdf PDF
J.5 List of Industry Standards & Public Documents.pdf PDF
J.10 Schedule of Items and Prices.xlsx XLSX spreadsheet
1305M224R0081.pdf PDF
J.1 NOAA Ship Oscar Dyson FSV Midlife Extension Program Work Specification.pdf PDF
J.2 Specific Contract Definitions and Work Requirements.pdf PDF
J.6 List of Ship Drawings.pdf PDF
J.12 Past Performance Questionnaire.docx DOCX document
J.15 SF 1418 Performance Bond.pdf PDF
J.16 Subcontracting Plan.pdf PDF
J.3 NOAA Standard Specifications.pdf PDF
J.4 List of Technical Publications.pdf PDF
J.7 Government Furnished Material.pdf PDF
J.11 Past Performance Information Form.xlsx XLSX spreadsheet
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX I – List of Deliverables Solicitation List of Deliverables

ITEM Deliverable Reference Due 1 SF33 and Solicitation

Amendments FAR 52.212-1 Proposal Submission

2 FAR 52.204-8 Annual Representations & Certifications

FAR 52.212-1 Proposal Submission

3 FAR 52.204-24

Representation

FAR 52.212-1 Proposal Submission

4 FAR 52.204-29

Representation & Disclosures

FAR 52.212-1 Proposal Submission

5 FAR 52.209-7 Representation FAR 52.212-1 Proposal Submission

6 FAR 52.212-3 Representation & Certifications

FAR 52.212-1 Proposal Submission

7 Resumes – Key & Critical Personnel

FAR 52.212-1 Proposal Submission

8 Insurance Certificate CAR 1352.271- 79 & 1352.271-90

Proposal Submission

9 Production Schedule FAR 52.212-1 &

CAR 1352.271-73

Proposal Submission

10 Work Package Network CAR 1352.271-73 Proposal Submission

11 Total Manpower Loading Curve

CAR 1352.271-73 Proposal Submission

12 Trade Manning Curves CAR 1352.271-73 Proposal Submission

13 Subcontracting List CAR 1352.271-73 Proposal Submission

14 Sexual Assault & Harassment Training Certificates

NAM 1330-

52.222-70

5 days after Contract Award

15 Performance & Payment Bonds

FAR 52.228-16 15 days after Contract ward

16 Bid Bond (Guarantee) FAR 52.228-1 15 days after Contract ward

17 Subcontracting Plan FAR 52.219-9 & 52.212-1

Proposal Submission

Work Specification - This list is not inclusive and additional items may be required as per the work specification

ITEM PARAGRAPH DELVERABLE DUE

20101 5.1 Required reports At checkpoints

20101 6.2 Required reports At checkpoints

20101 6.2.2 Required equipment and parts One week prior to contract end

20103 5.1 Required reports At checkpoints

20104 4.10. Revised Drawings One week prior to contract end

20104 5.1 Required reports At checkpoints

20105 5.1 Required reports At checkpoints

20105 4.6 Revised Drawings One week prior to contract end

20105 6.1 Revised Drawings One week prior to contract end

20105 6.2 Test data Completion of Item

20107 5.1 Required reports At checkpoints

20201 5.1 Required reports At checkpoints

20201 6.1 New and revised drawings One week prior to contract end

20201 6.1 Required equipment Prior to work

20201 6.1 Test data End of work item

20201 6.1 Spare parts One week prior to contract end

20202 5.10 Required reports At checkpoints

20203 4.2 Required reports Completion of item

20203 4.3 Required reports Completion of item

20203 4.4 Required reports Completion of item

20203 5.1 Required reports At checkpoints

20204 5.1 Required reports At checkpoints

20205 4.2 Required reports Completion of item

20205 4.3 Required reports Completion of item

20205 4.4 Required reports Completion of item

20205 4.5 Required reports Completion of item

20205 4.6 Test Requirements At checkpoints

20301 5.1 Required reports At checkpoints

20301 5.2 ABS approval Prior to Work

20302 5.1 Required reports At checkpoints

20302 5.2 Approval of Transit Operate Program Completion of Item

20303 5.1 Required reports At checkpoints

20304 5.1 Required reports At checkpoints

20305 5.1 Required reports At checkpoints

20306 4.3 Required reports At checkpoints

20306 4.4 Required reports At checkpoints

20306 5.1 Required reports At checkpoints

20307 4.1.3 Safety test procedures Prior to testing

20307 4.1.2 Drawings One week prior to contract end

20307 4.1.23 Required Equipment Prior to work

20307 4.3.9 Required Equipment Prior to work

20307 4.3.10 Required Equipment Prior to work

20307 4.3.11 Required Equipment Prior to work

20307 4.3.12 Required Equipment Prior to work

20307 4.8.3 Required Drawings One week prior to contract end

20307 5.1 Required reports At checkpoints

20401 5.1 Required Reports At checkpoints

20402 5.1 Required reports At checkpoints

20403 4.2.1 Required Drawings One week prior to contract end

20403 4.6 Training One week prior to contract end

20403 4.6.2 Technical Documentation Completion of item

20403 4.6.3 Revised Drawings One week prior to contract end

20403 5.1 Required reports At checkpoints

20404 4.1.4 Required Equipment Prior to work

20404 4.1.5 ABS approval Prior to work

20404 4.1.6 Technical Documentation Completion of Item

20404 5.1 Required reports At checkpoints

20405 4.1.2 Required equipment Prior to work

20405 4.5.2 Technical Manuals One month Prior to Training

20405 5.1 Required reports At checkpoints

20406 4.5 Training Two weeks prior to contract end

20406 4.5 Required technical Documentation Completion of item

20406 5.1 Required reports At checkpoints

20407 4.5 Training One week prior to contract end

20407 4.5 Required technical Documentation Completion of item

20407 5.1 Required reports At checkpoints

20501 4.8 Technical Documentation Completion of item

20501 5.1 Required reports At checkpoints

20501 5.2 Design drawings Prior to work

20502 4.1.5 ABS approval Prior to work

20502 5.1 Required reports At checkpoints

20503 5.1 Required reports At checkpoints

20504 4.3 New equipment Prior to work

20505 5.1 Required reports At checkpoints

20506 4.1.2 Required equipment Prior to work

20506 5.1 Required reports At checkpoints

20507 5.1 Required reports At checkpoints

20507 5.2 Installation Report End of work Item

20507 5.3 Testing After commissioning

20508 4.5.1 Testing Prior to commissioning

20508 4.6 Testing Completion of item

20508 5.1 Required reports At checkpoints

20508 5.2 Installation Report End of work Item

20508 5.3 Testing After commissioning

20509 5.1 Required reports At checkpoints

20511 5.1 Required reports At checkpoints

20512 5.1 Required reports At checkpoints

20513 4.7.1 Training Two weeks prior to contract end

20513 4.7.2 Technical Documentation Completion of Item

20513 4.7.3 Revised Drawings One week prior to contract end

20513 5.1 Required reports At checkpoints

20513 4.2 Installation Report End of work Item

20514 4.7 Updated drawings One week prior to contract end

20514 5.1 Required reports At checkpoints

20515 5.1 Required reports At checkpoints

20516 4.2.5 Required Equipment Prior to work

20517 4.1.3 Required Equipment Prior to work

20517 4.3 Required testing Completion of item

20517 5.1 Required reports At checkpoints

20518 5.1 Required reports At checkpoints

20519 5.1 Required reports At checkpoints

20520 5.1 Required reports At checkpoints

20521 5.1 Required reports At checkpoints

20521 5.2 Required reports At checkpoints

20522 5.1 Required reports At checkpoints

20523 5.1 Required reports At checkpoints

20524 5.1 Required reports At checkpoints

20525 4.3 Required Equipment (A-Frame) Prior to work

20525 4.6 Dockside Testing Completion of item

20525 4.7 Sea testing Completion of item

20525 4.11 Revised Drawings One week prior to contract end

20525 5.1 Required reports At checkpoints

20526 4.8 Required testing Completion of item

20526 4.10. Technical documentation Completion of item

20526 5.1 Required reports At checkpoints

20527 4.5 Required testing Completion of item

20527 5.1 Required reports At checkpoints

20528 4.1.2 Required material Prior to Work

20528 5.1 Required reports At checkpoints

20529 5.1 Required reports At checkpoints

20530 5.1 Required reports At checkpoints

20531 4.1.5 Required equipment Prior to work

20531 5.1 Required reports At checkpoints

20532 4.7 Required testing Completion of item

20532 5.1 Required reports At checkpoints

20533 5.1 Required reports At checkpoints

20534 4.5.1 Dockside trials End of trials

20534 4.5.2 Sea trials End of trials

20534 4.6 Training Two weeks prior to contract end

20534 4.6.1 Technical Documentation Completion of item

20534 4.6.2 Updated drawings One week prior to contract end

20534 5.1 Required reports At checkpoints

20535 4.5 Required testing Completion of item

20535 5.1 Required Reports At checkpoints

20536 5.1 Required reports At checkpoints

20601 5.1 Required reports At checkpoints

20602 5.1 Required reports At checkpoints

20603 5.1 Required reports At checkpoints

20604 5.1 Required reports At checkpoints

20605 5.1 Required reports At checkpoints

20606 5.1 Required reports At checkpoints

20607 5.1 Required reports At checkpoints

20608 4.2 Required reports At checkpoints

20608 4.3 Required reports At checkpoints

20609 5.1 Required reports At checkpoints

20610 5.1 Required reports At checkpoints

20611 5.1 Required reports At checkpoints

20611 5.2 Required testing At checkpoints

20612 5.1 Required reports At checkpoints

20613 5.1 Required reports At checkpoints

20614 5.1 Required reports At checkpoints

20614 6.2.1 Required test data Completion of item

20614 6.2.2 Revised Drawings One week prior to contract end

20615 5.1 Required reports At checkpoints

20616 5.1 Required reports At checkpoints

20801 4.1.2 Revised Drawings One week prior to contract end

20801 4.3 Revised Drawings One week prior to contract end

20801 5.1 USCG/ABS Approval letters Prior to work

20802 4.8 Stability Test Report Completion of item

20802 4.9 Weight report Completion of item

20802 5.3 USCG/ABS Approval Prior to work

20803 5.1 Required Equipment and Spare parts One week prior to contract end

20804 4.1 Technical Manuals Completion of item

20804 4.2 Updated EOS manual One month Prior to Training

20804 4.3.4 Software manuals and licenses One week prior to contract end

20804 4.3.5 Spare parts One week prior to contract end

20805 5.1 Weekly and final summary report Weekly

20806 4.1 Crew training, material, and schedules 1 month Prior to Training

20806 4.2 Crew training, material, and schedules 1 month Prior to Training

20806 4.3 Crew training, material, and schedules 1 month Prior to Training

20901 4.2 Dock trials Completion of item

20901 5.1 Required reports At checkpoints

20902 5.1 Required reports At checkpoints

20903 5.1 Required reports At checkpoints

20904 4.2 Required reports Completion of item

20904 4.3 Required reports Completion of item

20906 4.1 Vessel Condition video Upon Arrival

20907 4.8 Required reports Completion of item

20906 4.2 Required reports Completion of item

20906 4.3 Required reports Completion of item

20906 4.5 Required reports Completion of item

20906 4.6 Required reports Completion of item

20906 4.7 Required reports Completion of item

20906 4.8 Required reports Completion of item

20906 5.1 Required reports At checkpoints

60102 4.5 Required reports Completion of item

60103 4.6 Required reports Completion of item

60104 4.4 Required testing Completion of item

60105 4.3 Required testing Completion of item

60502 4.3 Required equipment Prior to work

60502 4.5 Required testing Completion of item

60502 4.6 Required training Completion of item

60502 5.1 Required reports At checkpoints

60504 4.7 Required reports Completion of item

60505 4.4 Required reports Completion of item

60506 4.3 Required reports Completion of item

60506 4.4 Required reports Completion of item

60506 4.5 Required reports Completion of item

60506 5.1 Required reports At checkpoints

60507 4.3 Required reports Completion of item

60507 4.4 Required reports Completion of item

60507 4.5 Required reports Completion of item

60507 4.6 Required reports Completion of item

60507 5.1 Required reports At checkpoints

60602 5.1 Required reports At checkpoints

60603 5.1 Required reports At checkpoints

60604 2.1 Required reports Completion of item

60605 2.1 Required reports Completion of item

60605 4.1 Required reports Completion of item