J.2 Specific Contract Definitions and Work Requirements.pdf
PDF 756 KB Posted
- Attached to
- Oscar Dyson FSV Midlife Extension Program Federal contract opportunity
- Solicitation number
- 1305M224R0081
About this file
This document is the Specific Contract Definitions and Work Requirements for the Oscar Dyson FSV Midlife Extension Program solicitation. It details the general requirements, work definitions, and specification requirements for the contract work.
The key details include:
- General requirements for the contractor, such as providing all necessary facilities, engineering, labor, materials, etc. to fully complete and deliver the vessel.
- Specific work requirements, including welding/brazing processes, removals, installations, addressing interferences, structural, piping, HVAC, and electrical modifications, and painting requirements.
- Administrative requirements such as personnel, schedule, regulatory compliance, quality assurance, testing, and documentation.
- Detailed specifications for the various systems and equipment being modified or installed, including materials, construction, installation methods, and performance requirements.
The document provides a comprehensive overview of the technical and operational requirements that the contractor must meet to successfully execute the Oscar Dyson FSV Midlife Extension Program contract.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specific Contract Definitions and Work Requirements
INDEX
Section 1 - SCOPE
Section 2 - REFERENCES
Section 3 - GENERAL REQUIREMENTS
Section 4 - DEFINITION OF TERMS
Section 5 - WORK REQUIREMENTS
5.1 - General Requirements
5.2 - Welding & Brazing Processes and Inspections
5.3 - Removal Requirements
5.4 - Installation Requirements
5.5 - Interferences
5.6 - Structural Access Openings
5.7 - Disruption of Ship Systems
5.8 - Fluid Handling and Disposition Requirements
5.9 - Safet Requirements
5.10 - Completion of Work and Vessel Reconstitution
Section 6 - SPECIFICATION REQUIREMENTS
6.1 - Structural Modifications
6.2 - Piping Modifications
6.3 - HVAC Modifications
6.4 - Electrical Modifications
6.5 - Painting Requirements
Section 7 - ADMINISTRATIVE REQUIREMENTS
7.1 - Personnel Requirements
7.2 - Schedule Requirements
7.3 - Meeting & Reporting
7.4 - Regulatory Bodies, Laws, Classification Rules, Rules, Regulations, Standards, & Certificates
7.5 - Quality Assurance, Test, & Inspection Plans
7.6 - Weight Controls
7.7 - Materials
7.8 - Substitutions
7.9 - Scrap & Salvage
7.10 - Inspections
7.11 - Test & Trials
7.12 - Drawings & Engineering
7.13 - Technical Documentation
NOAA Ship OSCAR DYSON MEP – Definitions and Work Requirements
1 SCOPE
1.1 Objective - This appendix contains the general requirements for work by the repair Contractor.
These requirements apply to all specifications in the Statement of Work (SOW), any additional growth work items, and appendices unless specifically exempted in the original contract.
2 REFERENCES
2.1 Rules for Building and Classing Marine Vessels, American Bureau of Shipping (ABS)
2.2 Shipbuilding and Repair Quality Standard: International Association of Classification Societies (ICAS), 47, Rev. 7, 2013
3 GENERAL REQUIREMENTS
3.1 The ship will be delivered to the Contractor’s facility in “as is” condition. It is the Contractor’s responsibility to remove, modify, repair, or replace all systems necessary to accomplish the contracted work.
3.2 The Contractor shall satisfactorily perform all work and details connected therewith to construct, equip, outfit, test, and deliver to the Government, fully certificated and afloat, and ready for the intended service vessel. The completed vessel shall fully comply with all requirements applicable to maintaining classification, as well as all salient requirements of the regulatory bodies cited for the affected areas.
3.3 The Contractor shall provide all necessary plant facilities, engineering, labor, services, materials, machinery, equipment, outfit, gas-freeing, spare parts, appurtenances, tools, appliances, transportation, supplies, fuel, water, power, lighting, air, crane, lift and disposal services, rigging, communication, handling lines, wharfage, docking, and shifting of vessel.
3.4 The Contractor shall provide the services of manufacturers’ representatives to accomplish highly specialized work for which the Contractor does not have adequately trained personnel. Where installation supervision, adjustments, tests, and/or calibration of equipment by a manufacturer’s representative is required by these specifications, any charges therefore shall be to the Contractor’s account, unless it is for Owner-furnished equipment or stated otherwise.
3.5 The Contractor shall safeguard the vessel’s machinery and electrical equipment, the use of which will be made only upon approval by the Government and under the supervision of trained and competent personnel. The Contractor shall protect by masking and other means all machinery, equipment, finished surfaces, and any other items or surfaces requiring protection during the course of the work.
3.6 During work installations shall permit free passage along walkways and ladderways; free access for operation, inspection, and routine maintenance; free access to all doors, hatches, and openings;
free access to life saving equipment and firefighting equipment; and, as much as is practicable, access to equipment and system components.
3.7 The Contractor shall submit to the Government the necessary documentation for all proposed subcontractors, whether listed in the specifications or not, to demonstrate compliance of the subcontractor with the applicable experience criteria for proposed involved engineering/ technical staff, as outlined in the Statement of Work (SOW). Specifically, the Contractor shall identify the subcontractor(s), the scope assigned to each subcontractor(s), and provide resumes demonstrating the ability to meet the requirements of the SOW.
3.8 Order of Precedence - In the case of inconsistency between contract and regulatory documents, the following order of precedence (from highest to lowest) applies:
1. Contract.
2. General specifications.
3. Regulatory Bodies
4. Contract drawings.
3.8.1 Silence of one document with respect to details shown on another will not be considered an inconsistency, error, or omission. Where two or more requirements provide inconsistent direction, the more stringent requirement will apply. Where such a requirement conflicts with the order of precedence of contract documents, the COR will make the appropriate determination after being notified, in writing, by the Contractor. The COR’s determination will not be cause for a monetary and/or a schedule claim by the Contractor
3.8.2 Where the standards described in these specifications and drawings are less than the standards of any of the listed regulatory bodies, the requirements of the regulatory body shall be met. Where the standards described in these specifications and drawings exceed the standards of the regulatory bodies, the standards of these specifications and drawings shall apply. In certain respects, the requirements of the specifications and accompanying drawings may exceed those of the regulatory bodies referenced herein. These requirements will not be relaxed
4 DEFINITIONS OF TERMS
Wherever used in this specification and in all other work items in this contract, the following definitions of terms apply:
Approved - Where the words “approved” or “for approval” are used, they shall mean “approved by the Government” and “for the Government’s approval,” unless indicated otherwise. Approval of any drawings, methods, materials, or procedures and supporting documentation will indicate only that the general method of construction and detailing is satisfactory and will not relieve the Contractor of the responsibility for any error or compliance with regulatory requirements.
As-Original - A condition meeting the original system and manufacturer’s design.
As-Found - The condition which was found upon close inspection by an individual with knowledge on the item(s) in question. It is intended that the observations will find all relative conditions, both those requiring repairs and those not.
CFE/CFM - Contractor Furnished Equipment and Contractor Furnished Material are used interchangeably.
COR - Contracting Officer’s Representative.
COR Approval - Indicates only that the general method of construction and detailing as presented by the Contractor appear to be satisfactory and will not relieve the Contractor of the responsibility of any error.
Contracting Officer - Identifies the Contracting Officer for NOAA
Contractor - The person, firm, co-partnership, joint venture, or corporation, undertaking to perform the work herein specified. Wherever any pronoun is used as referring to the word “Contractor,” it shall mean the Contractor as defined herein
Days - Any reference to “days” herein shall be “calendar days.
Delivery - The term “delivery” is the correct contractual term for the point in time when the Contractor accepts the ship into his custody Detach / Disconnect - To disconnect all attachments to the unit to enable the unit to be moved.
Attachment points shall be tagged, identified, blanked, and protected to facilitate reinstallation. Individual specifications do not necessarily identify interferences, and the Contractor is responsible for the identification and resolution of interferences affecting a detachment and subsequent movement.
Furnish - The term “furnish” shall mean deliver to the ship. When applied to “Owner-furnished,” it shall mean delivery by the Owner, unless otherwise specified, to the Contractor’s facility for off-loading and care by the Contractor.
GFE and GFM - Government Furnished Equipment and Government Furnished Material are used interchangeably.
Good Marine Quality - Constructed of materials unaffected by moisture, sea spray, extremes of temperature, and other hazards of the marine environment, and has been designed and constructed to perform its intended function in the marine environment conditions, plus the dynamic motions and cyclic loads imparted in a marine environment. The item shall further be designed and constructed for ease and safety of operation under dynamic conditions, and shall require minimum maintenance.
Good Shipbuilding Practice - Construction to soundly conceived, and engineered detailed working plans, prepared by the Contractor or Government, incorporating the specified components and utilizing recognized shipbuilding construction and testing methods to ensure that the completed ship conforms to specification requirements. Inspection by the COR is for the purpose of verifying the proper functioning of the Contractor's quality assurance measures and is not a substitute for in-process control of quality by the Contractor, nor does it replace or supersede Regulatory Body approvals.
Government - the United States Government, specifically NOAA.
Guidance Document(s) - Those Documents or models that illustrate Owner’s concept, intent, or goal regarding a certain system, aspect, or feature of the Vessel.
HAZWASTE - Hazardous wastes are those RCRA identifies in one of four hazardous waste lists (F- list
– 40 CFR 261.31, K-list – 40 CFR 261.32, P-list 40 CFR 262.32, or U-list 40 CFR 261.32), or exhibits at least one of four characteristics – ignitability, corrosivity, reactivity or toxicity as defined in 40 CFR Part 261, Subpart C.
Install, Extend, & Modify - Means that the Contractor shall install any CFE or GFE equipment, material, or system and shall provide the materials, structural supports, tools, and labor to attach, connect, and test the equipment or system to affect a finished fully operational installation complete in all aspects.
This also pertains to any equipment, material, or system that is temporarily removed, relocated, modified, or refurbished. When new material or equipment is not specified by type, the material or equipment shall be identical to the existing. When “install” is used with reference to GFE, conditions of the above definition except the requirement to provide the piece of equipment are applicable.
Interference - Any object(s), equipment(s), system(s), or component(s) that must be temporarily removed and reinstalled, relocated, modified or designed around to facilitate the installation of new or modified equipment or systems.
Inspect - Visually evaluate the specified surface, item, part, or component for evidence of contamination, damage excessive wear, scoring, and any other condition which could interfere with the proper operation or functioning of the surface, item, part or component.
Manifests - The official shipping document forms originated and signed by the generators, transporters, and operators of the hazardous waste disposal facility as required by Federal, state, or local regulations.
NDT or Non-Destructive Testing - NDT shall be accomplished to satisfy ABS and USCG requirements for all weld repairs, hull inserts or structural installations. Testing shall utilize currently calibrated equipment and certificated testing personnel.
Or Equal - Components, materials or equipment shall be equivalent in terms of performance (flow rate, pressure, heat transfer characteristics, etc.), services required (power, cooling water, HVAC, etc.), compatibility with interrelated systems and arrangements Contract Guidance Drawings or Work Package, the Contractor shall submit a written request delineating the design and performance data on both the specified and substituted piece of equipment for COR approval and if approved. The Contractor shall take full contractual and technical responsibility for ensuring installation of the components, materials or equipment are compatibility with the interrelated systems, and supportability over the service life of the components or equipment.
Piping - A system of pipe, tube, elbows, tees, valves, couplings, and other pipe fittings. Unless otherwise specified in the detailed item description, all piping systems and components shall comply with material and installation requirements of reference 2.8 and other documents.
Provide - The term “provide” shall mean the Contractor shall supply all materials, equipment, tools, and labor to perform the work required.
Qualified Welders - Welders, whether contractor or subcontractor provided, shall hold qualification documentation from American Bureau of Shipping (ABS), and United States Coast Guard (USCG) for the material to be welded. Welding procedures shall be approved by the ABS Surveyor for the particular applications.
Refurbish / Rebuild - To temporarily remove, disassemble, clean, inspect, and submit an as-found condition report; reassemble the unit, equipment or system, set and adjust in accordance with manufacturer’s specifications, test the unit, equipment, or system to demonstrate proper function to the manufacturer’s specifications; The reinstalled refurbished unit, equipment, or system shall be fully operational and complete in all aspects. New screws, bolts, nuts, washers, gaskets, packing, pins, keys, seals, valve stems, bearings, “o” rings, and shims shall be used when reassembling and reinstalling the unit, equipment, or system. Components and parts shall meet the manufacturer's applicable rebuild specifications.
Relocate - To provide labor and materials to detach the unit, equipment, or system and to reinstall the same unit, equipment, or system at a new or modified location. The requirements of an installation as set forth in the above paragraphs with regard to completeness, operation, testing, the identification and resolution of interferences, etc. also apply to relocation.
Remove or Rip Out - Provide labor and materials to disconnect, detach, and transfer the unit, equipment, materials, or system in its entirety off the ship as specified. Supports, stuffing tubes, collars, and other appurtenances shall be removed. Areas affected by removals / rip outs shall be restored as set forth in the above paragraphs:
Replace or Renew - Remove the unit, equipment, or systems including interferences, and to install a new unit, equipment, or system which is either identical to or equal to that which was removed; the installation shall include but not be limited to any hook-ups, supports, and adapters, which are required to affect a finished fully operational installation complete in all aspects.
Restore - Perform those processes (including but not limited to weld build-up, chrome plate, machine, grind, lap, NDT, etc.) which are required to return a component to the manufacturer’s specifications regarding dimensions, tolerances, angles, surface finish and clearances. To restores removed materials/equipment/systems that were identified as interferences.
SOW or Statement of Work - The contract document that consist of individual specifications for all work. identifies each work item
Tag out - A procedure to both notify personnel that tagged-out equipment, components, or systems are either isolated or not in a normal operating condition and to prevent injury to personnel, improper operation, or damage to the tagged-out equipment, components, or systems.
Temporary Installation or Temporarily Install - Provide labor and materials to install the unit, material, equipment or system to completely provide the function described and to remove the same unit, material, equipment or system prior to redelivery of vessel All the requirements of an installation and removal with regard to completeness, operation, testing, the identification and resolution of interferences, disconnection, detachment and transfer of the unit, material, equipment, or system in its entirety off the ship as specified apply to a temporary installation and subsequent removal.
Temporary Removal or Temporarily Remove - To provide labor and material to disconnect and move the unit, equipment, or system from its initial location, and to reinstall the same unit, equipment, or system either in the same location or elsewhere on the ship as described. All the requirements of an installation with regard to completeness, operation, testing, the identification and resolution of interferences, etc. also apply to a temporary removal and reinstallation.
Work - “Work” shall mean the furnishing by the Contractor of all labor, materials, equipment, and other incidentals necessary or expedient to the successful completion of the project and the carrying out of all the duties and obligations imposed by the contract, REGULATORY BODIES, LAWS, CLASSIFICATION, RULES, REGULATIONS, STANDARDS, AND CERTIFICATES
5 WORK REQUIREMENTS
The provisions of this subsection apply throughout the repair period and time at the vendors facility unless specifically exempted.
5.1 GENERAL REQUIREMENTS
5.1.1 Vessel Condition Assessment
Upon delivery of the vessel to the Contractor and prior to the beginning any work, the Contractor shall prepare a video showing the existing interior and exterior condition of the vessel and in all intended work areas prior to conduct of work, except for work intended in tanks and voids. A copy of the video shall be provided to the COR within five (5) days after receipt of the vessel from the Government.
A joint survey of those areas of the vessel impacted by the contracted work will be conducted by the COR and the Contractor before work begins. The purpose of this preliminary survey is to establish an understanding between the COR and Contractor of the extent of work required to complete the contract and develop an initial punch list.
5.1.2 Contractor Work Hours.
At the beginning of the repair period, the Contractor shall advise the COR in writing of the planned regular work day schedule. In the event the Contractor desires to work at times other than those previously scheduled, notify the COR at least 4 hours prior to the end of the scheduled work day preceding the unscheduled work time. If previously unscheduled work is to be performed on a weekend or federal holiday, the COR must be notified prior to 9:00am on the last regular work day before the unscheduled work.
5.1.3 Contractor Storage on Vessel
No space or compartment on the ship shall be used for storage of materials or tools by the Contractor. The materials allowed at the work site shall be limited to those that will be installed, consumed, or otherwise used during the work shift in progress. When needed or required, provide a temporary dockside storage area to store materials and tools
5.2 WELDING / BRAZING PROCESSES & INSPECTIONS
5.2.1 General
The Contractors welding and brazing qualifications, procedures, inspections, and documentation shall be in accordance with the American Bureau of Shipping Rules. The Contractor shall only use welders and welding operators pre-qualified by tests to the satisfaction of ABS, and at no expense to the Government, for the type of material(s) and welding process(es) being used.
5.2.2 Documentation
Within five (5) days of the vessel’s arrival at the Contractor’s facility, the Contractor shall provide to the Government a list of all welders and welding operators’ qualifications. The Government reserves the right to review Contractor copies of the certificates.
Within five (5) days of the vessel’s arrival at the Contractor’s facility, the Contractor shall submit project-specific welding procedures and sequences to the Government, as well as to ABS, for review and approval (pre-existing, ABS-approved generic sequences will be accepted). The submitted documentation shall identify type and size of electrode or filler metal, current values, shielding gas, and other details of welding and silver brazing processes and procedures as they relate to the work being addressed.
5.2.3 Welding Process
Continuous welding for sealing purposes shall be performed on all new structure and attachments where normally exposed to the weather Structural welding shall be carried out in such sequence as to compensate for shrinkage as the work progresses, to prevent locked-in stresses, and to hold distortion to an acceptable minimum. Peening of weld material will not be allowed except as specifically approved by the Government and ABS. Steel to be welded shall be kept entirely free of paint or oil other than weld-through primers.
While the ship is water-borne, welding shall be permitted only when welding leads are properly grounded. Welding machines and other welding power sources shall have both cables connected only to the ship where welding is done. The return ground cable shall never be grounded to anything but the ship it is servicing. The ground cable shall be securely fastened to grounding plates or to an integral part of the ship, with contact areas thoroughly cleaned to bare metal. The total cross-sectional areas of the return ground cable shall be at least one million circular mils per 1,000 amperes per 100 feet, but not less than 85,000 circular mils. All welding cables shall be fully insulated and not be permitted to drop overboard into the water.
When welding on equipment, machinery, pressure vessels, or piping, the return ground cable to the welding machine shall be connected in the immediate vicinity (as close as practical) of the work to ensure that current does not flow through bearings, pipe hangers or other areas where arcing or high resistance paths exist.
5.2.4 Welding Inspections
New welds shall be inspected as necessary to satisfy the regulatory bodies. Should the regulatory bodies or the Government deem it necessary to increase the area of inspection because of the discovery of unsatisfactory welding, all such additional inspections shall be at the Contractor’s expense.
Weld inspections shall occur prior to painting the welds. Weld inspection shall be made by either visual, radiographic, ultrasonic, hydrostatic, air, or magnetic tests, separately or in combination, as required by ABS or the Government. All weld inspection equipment and materials shall be provided by the Contractor. Weld inspections shall be performed by third party AWS Certified Welding Inspectors, satisfactory to ABS for weld inspections.
5.3 REMOVAL REQUIREMENTS
5.3.1 Whenever removal of equipment or machinery is specified, and reinstallation is not, the Contractor shall remove all related electric cables, brackets, foundations, ducting, and piping.
Removal of cables shall be to the nearest circuit breaker or terminal not needed for operation of other equipment or machinery. Removal of piping shall include all related piping, fittings, valves not used by other systems or equipment. Install pipe caps as needed to maintain remaining piping tight.
Whenever removals of piping or cables involve penetration through bulkheads, decks, hull plating or other watertight/fire tight boundaries, crop out the penetration and install an insert plate of same thickness as the adjacent plating. Package supports, stuffing tubes, collars, and other appurtenances shall be removed. Areas affected by removals shall be restored and surface irregularities shall be ground smooth and flush with adjacent surfaces as required in the specification.
When removals of the electrical wiring join a circuit that is not being removed (i.e., at a junction box), the electrical wiring or cable shall be entirely removed to the junction point. All other attachments including but not limited to fasteners, supports, and brackets shall be entirely removed.
When electric cable is designated for removal, it shall be physically and electrically traced to the power source. When cable is removed from multiple cable runs, the remaining cables shall be bound and strapped.
Once tasked work in the affected area is complete, the areas affected by the removal shall be restored to the condition before the removal action. This includes but is not limited to painting of steel, restoring floor coverings and joiner work, painting, replacing items and equipment removed for access, plugging wiring and pipe penetrations, and restoring all other disturbed areas to match the surrounding areas.
5.4 INSTALLATION REQUIREMENTS
5.4.1 General Requirements - The Contractor shall place the specified item in position for service and make all connections needed to insure proper use, service, appearance, and operation. Except as may otherwise be specified, this shall include but not be limited to the following
• Foundations - Provide new or modify existing foundations. Securely mount equipment and components using new fasteners. Align connected equipment and components to meet manufacturers’ specifications.
• Electrical - Make all electrical connections. Provide new electric cable runs between controllers and motors of new equipment. Existing cables may be reused in other applications, except where the existing cables are too short to make connections. Renew cables, which are too short and less than 20 feet long. Junction boxes may be used to increase the cable run length where the existing cable runs are longer than 20 feet.
• Piping - Modify new piping to suit the new equipment, including the rerouting of existing piping and adding of new piping as needed to properly connect equipment and components. Piping modifications greater than five feet from the equipment are not required. New piping is required only to the extent necessary to accommodate modifications of existing piping.
• Ducting - Modify new ducting to suit the new equipment, including the rerouting of existing ducting and adding of new sections as needed to properly connect equipment and components. Ducting modifications greater than five feet from the equipment are not required. New ducting is required only to the extent necessary to accommodate modifications of existing piping.
5.5 INTERFERENCES
5.5.1 Removals
The Contractor is responsible to identify all interferences and obstructions necessary to complete the required work. All interferences in way of the modifications shall be removed by the Contractor.
Interferences include but are not limited to:
• Joiner bulkheads and linings
• Drop ceilings and overhead panels
• Primary Structure
• Piping
• Pumps
• Valves
• Ventilation ducting and components
• Insulation
• Deck coverings
• Electrical cabling and support structure
• Lights
• Receptacles,
• Cricut panel boxes and control centers
• Fittings
All items removed as interferences shall be retained for re-installation where possible or replaced if not useable. The Contractor shall be responsible for proper handling and storage of such items so as to prevent loss, damage, or deterioration.
Whenever an interference to be removed involves a structural strength member, temporary supports shall be provided to compensate for the strength loss. Whenever watertight integrity is violated by a removed interference, provide a temporary means of maintaining watertight integrity, except when work is actually being performed or the space is otherwise manned.
5.5.2 Restoration, Modification & Alterations
Restore all interferences to their existing configuration and condition. In place of material that is rendered unsuitable for reinstallation during removal or storage, provide and install new materials which are equal in composition, strength, design, type, and size as existed prior to removal.
Material condition and operability of re-installed items and systems shall be equal to the same state prior to removal. Align and conduct strength, tightness, and operational tests to ensure that the reinstalled interferences safely perform their normal functions All re-installed items shall be tested and demonstrated to confirm satisfactory re-installation.
Alterations made to strength members (such as stanchions, structural steel, etc.) shall maintain the structural integrity of the original installation and are to be approved to the satisfaction of ABS and the COR.
Except as otherwise specified, this does not include relocations made necessary by new installations, which physically prevent an interference from being returned to its existing location.
5.6 STRUCTURAL ACCESS OPENINGS
5.6.1 Requirements
The Contractor may, with prior approval, cut access openings in ship's structure if required to perform work. Such openings shall be limited to those which are essential for access to otherwise inaccessible areas or which greatly improve accessibility for removals or installations.
5.6.2 Procedures
Prior to making any access opening in ship's structure, submit to the COR a sketch of the proposed opening, showing the location and dimensions of the proposed access cut, adjacent framing members, nearby penetrations, and scantlings of the structure. Generous radii shall be provided at all corners. Also include a description of the eventual restoration configuration, with material and welding details, and a narrative justification for cutting the opening. The Contractor shall proceed with the access cut only after return by the COR of a signed copy of the sketch.
All temporary openings into the vessel shall be marked and protected at all times. Tarps and temporary doors shall provide 100% protection of the openings (overhead and sides) except for the short durations when lifting operations are underway. Steel coamings shall be installed around each deck opening to prevent water intrusion into the space. Coamings shall be suitably sealed to prevent any leakage into the space.
5.7 DISRUPTION OF SHIP SYSTEMS
5.7.1 General
Except as necessary to perform work, none of the ship's fire main, electrical, steam, heating, potable water, drainage, or other systems which are vital to crew safety or comfort shall be shut off or disrupted. The COR shall have advanced notice of a disruption at least 4 hours in advance.
Disruptions shall be limited to 4-hour intervals. If the required work will need a longer interval, temporary bypass hoses, blank flanges, or piping shall be installed to keep the system in operation.
5.7.2 For purposes of this specification, a "disruption" occurs whenever a large section of a system will be unusable. If the only section of the system affected is that on which work is being performed and the remainder of the system can be operated, a "disruption" has not occurred and the requirements of this paragraph do not apply.
5.8 FLUID HANDELING & DISPOSITION REQUIREMENTS
5.8.1 Fuel Oil and Lube Oil On & Offloading
Whenever the Contractor is required to or elects to offload fuel oil or lube oil from the ship, the oil shall be pumped to and stored in clean moisture-free storage tanks. Meter the oils with a calibrated meter during offloading and during return. Take test samples during offloading and during return as close as possible to the ships fuel riser, and have the test samples analyzed by a lab for water and impurities to verify that the oils were not contaminated while in the Contractor's possession. Provide copies of lab reports to the COR.
After all work, which necessitated the oil’s removal, has been completed, return the oil to the ship.
In lieu of storing the oil, the Contractor may accept title and responsibility for disposal of the oil and provide an equal amount of new clean oil, same as that removed. Test samples are required, even if this option is exercised by the Contractor.
5.8.2 Disposal of Fluids.
Whenever work requires that equipment, machinery, piping, or tanks be drained of fluids, the Contractor shall be responsible for draining and proper disposal of the fluid. If the Contractor drains the fluid into the ship's bilges, the Contractor shall pump all fluid from the applicable bilges into dockside tanks and properly dispose of the fluid, including the fluid that existed prior to and the fluid that accumulates between the time the equipment, machinery, piping or tanks were drained and the time the bilges have been pumped dry by the Contractor.
5.9 SAFETY REQUIREMENTS.
5.9.1 General
The name(s) and telephone number(s) of the Contractor’s safety representative(s) shall be provided to the COR prior to beginning work, so as to provide 24-hour-per-day communication capability for safety-related issues. The name(s) and telephone number(s) of the Contractor’s safety representative(s) shall be posted aboard the vessel.
5.9.2 Security
The Contractor shall provide and maintain an adequate watchman service including onboard roving security for the entire vessel until redelivery, so as to protect the vessel from damage, fire, flooding, and pilferage.
5.9.3 Fire Protection
The Contractor shall provide and be solely responsible for all firefighting protection on board the vessel as may be required by various regulatory agencies, including the local fire department and Port Authority, during the contract performance period. Note: The ship’s existing fire main system may be unavailable for use by the Contractor during the contract period. As such, the Contractor shall not rely on use of the installed system, or any portions thereof, in planning firefighting protection.
At least ten (10) days prior to the vessel’s arrival at the Contractor’s facility, the Contractor shall submit, for COR review, comment, and approval, a fire plan identifying:
• The Contractor’s personnel responsible for implementation of the plan.
• Detailed procedures to be followed in the event of a shipboard fire.
• The location and capabilities of Contractor-supplied firefighting equipment.
• A certified statement that the plan satisfies all applicable federal, state, and local codes, rules, and regulations.
The Contractor’s fire plan shall not make use of ship’s personnel, nor shall it rely on the availability or proper operation of the vessel’s firefighting systems, equipment, and alarms.
On the day of the vessel’s arrival at the Contractor’s facility, the Contractor shall provide, along with the Contractor’s approved fire plan, a meeting with the local fire chief responsible for emergency response to the vessel, the purpose of which will be familiarization with the vessel and discussion of firefighting procedures.
In the event of a shipboard fire, the Contractor shall be held responsible for and make good at their expense any and all damage of whatever nature and/or loss to the vessel, and/or its machinery and/or its stores, outfit, furniture and furnishings, spare parts, tools, and removable equipment.
5.9.4 Gas Free Certification
The Contractor shall be responsible for certifying that a safe atmosphere exists in and about a compartment, tank, or void prior to the commencement of any work. Whenever compartments must be gas free to meet state and federal regulations, the Contractor shall pump down, open, remove sludge, clean, wipe, ventilate and take all other action required to make the compartment, tank, or void safe for the work to be performed. When requested by the Contractor, and to the extent empty tank space is available, the Government will shift fuel as required to facilitate gas free requirements.
If offloading of fuel oil is necessary because of insufficient empty tank space, the Contractor shall off-load the fuel. Copies of gas free certificates, issued by a Marine Chemist certified by the National Fire Protection Association, shall be posted on the ship in two locations designated by the COR. Follow-up inspections by the Contractor's Competent Person shall also be documented at the same two locations.
The Contractor shall be responsible for identifying the compartments that require gas free certification. Specific requirements for gas free certifications are not normally included in the detail specifications of any work item.
5.9.5 Written Hot Work Notice.
Twenty-four (24) hours prior to starting hot work on any job or separate area of the ship, provide a written notice to the OOD. The notice shall state the location of the work, the time hot work will commence and the current gas free status of the area if needed.
5.9.6 Welding & Torch Safety
Proper control of welding and grounding leads shall be maintained for the protection of the hull, systems, and appendages. Control shall be maintained during the contract period, whether waterborne or in dry dock. The following precautionary measures shall be, at a minimum, adhered to:
• The vessel’s welding power source and ground cables shall not be used for another vessel or structure.
• Welding and ground cables shall be properly insulated and not immersed in standing water.
• Grounding lugs shall be tightly secured and contact surfaces periodically cleaned.
Oxygen, acetylene, and gas supply manifold systems shall be located off the ship and have a shutoff valve to the gas supply located on the dock. The shutoff shall be in addition to the master shutoff valve at the inlet to each portable outlet header.
5.9.7 Fire Watch Standers.
Hot work is permitted only when the Contractor provides fire watch standers. A fire watch stander is required whenever welding, flame cutting, cutting, or other hot work is performed where combustible materials are present within 35 feet; or where wall or deck openings within a 35-feet radius expose combustible materials in adjacent areas; or when combustible materials are adjacent to the opposite side of metal partitions exposed to hot work, and could be ignited by conduction or radiation. In the latter case, a fire watch stander is required on both sides of the partition. The fire watcher shall be equipped and perform as follows:
• Each fire watch stander shall be outfitted by the Contractor with a fire extinguishing agent of a suitable size and type for the combustible hazard.
• The fire watch stander only duty will be as a fire watcher and shall remain on watch for 30 minutes after hot work is completed.
• Prior to leaving the work site, the fire watch stander shall verify with the worker performing the hot work that no further hot work will be performed.
• Vessel firefighting equipment shall not be used as fire watch equipment.
Insulation, sheathing, or other materials which limit access to either side of a partition or structure on which hot work is being performed shall be considered to be an interference, and shall be removed and restored by the Contractor.
5.9.8 Vessel Fire & Water Boundaries
During the repair period, the Contractor shall maintain the watertight and fire boundary integrity of the ships on all decks. Rigging of hoses, welding leads, and temporary lights shall be kept clear of the deck on temporary "trees" or brackets and be arranged so as to minimize tripping and other safety hazards. Passageways shall be kept as clear of obstructions as possible.
Rigging of said hosed, welding leads, temporary lighting, etc., through water tight and fire boundary doors shall be prohibited. If these boundaries are utilized all hose, welding leads, lighting, etc., shall be arranged/configured to be breakable at these boundary points to allow closure of water tight and fire boundary doors in the event of fire and/or flooding incident.
5.9.9 Miscellaneous Safety Requirements
Material brought onto the ship shall be stored until used in areas which do not interfere with access to firefighting equipment or personnel access. Crating and packing shall be removed prior to bringing the equipment or material aboard the ship, unless needed to protect the equipment or material from damage during handling. In that case, the crating and packing shall be removed from the equipment or material, and shall be removed from the ship, immediately after being brought aboard.
All temporary openings into the vessel shall be marked and protected at all times. Tarps and temporary doors shall provide 100% protection of the openings (overhead and sides) except for the short durations when lifting operations are underway. Steel coamings shall be installed around each deck opening to prevent water intrusion into the space. Coamings shall be suitably sealed to prevent any leakage into the space.
The Contractor shall protect dangerous areas, such as access openings in the deck, with suitable temporary hand rails, and take all necessary and reasonable safety precautions to prevent injury to any person who may enter the work area for any reason.
5.10 COMPLETION OF WORK & VESSEL RECONSTITUTION
5.10.1 Completion of Work
The Contractor shall complete all contracted work by 1800 hours on the work completion date shown on the contract documents with the vessel clean and free of defects and deficiencies and the final joint condition survey punch list work completed.
The vessel shall be complete and ready for service, afloat pier-side, with all its areas (related to contract work) thoroughly cleaned and free of all dunnage and dirt. Potable water tanks shall be filled to capacity (accomplished by the Governments crew) and any diesel oil or similar fluids removed from the vessel to accomplish the contracted work, which would otherwise have been retained by the Government, shall have been replaced by the Contractor.
A timetable for completion of work on a revised final joint condition survey punch list will be agreed to between the COR and Contractor. The Contractor shall provide, prior to acceptance, the Coast Guard approved stability guidance necessary for the vessel to commence an operational schedule.
5.10.2 Compartment Closeouts
After all work on the vessel is substantially complete, each compartment in the vessel affected by the contracted work shall be inspected with an COR present to check fixtures, lighting, HVAC controls, cable penetrations, labeling, coatings, joiner doors, outfitting, and other miscellaneous items in the compartment. A preliminary inspection shall take place prior to installing or replacing the overhead panels.
When a compartment has been proven satisfactory to the COR, the compartment shall be “closed out” by locking or otherwise preventing general access to the space.
5.10.3 Vessel Reconstitution
During this time, crew will move tools, equipment, personal belongings, etc. aboard the vessel. The Contractor shall provide pier-side crane service and fork lift service during this time to facilitate vessel reconstitution. The Contractor shall move the storage containers possessing vessel equipment/supplies from their storage site to a location in close proximity to the ship for unloading.
6 SPECIFICATION REQUIREMENTS
The provisions of this subsection apply throughout the specifications and to all addenda, appendices, and change orders, unless specifically exempted.
6.1 STRUCTURAL MODIFICATIONS
6.1.1 Workmanship
The arrangements and scantlings of the structure shall be as shown on the drawings. The structural drawings have been developed in accordance with the rules of the American Bureau of Shipping (ABS), and any development of details shall maintain the same standards. Where details and scantlings are not shown, those in the existing vessel are to be used where applicable, but all details and scantlings must meet ABS requirements.
Care shall be taken to obtain good alignment of structural members, particularly where such members oppose each other on opposite sides of bulkheads or decks. In such cases, misalignment exceeding half the thickness of the thicker member shall be considered cause for rejection. Where discontinuities of structure are unavoidable, suitable brackets or other reinforcement shall be installed.
Within tanks, cofferdams, and peaks, and in any other spaces or areas that could trap liquids, adequate limbers shall be provided to ensure effective drainage. Similar limbers shall be cut in the framing members at the tops of tanks to prevent air pockets. Semi-circular “rat holes” are to be provided in framing members in way of passing welded seams or butts in the attached plating.
Where it is necessary to provide holes for passage of wiring, piping, or ductwork in structural members, compensation shall be provided where appropriate. In general, if such holes remove more than 30% of the depth of the web of a member or if they are unfavorably located, reinforcement will be required.
Where reinforcement is required in way of penetrations of decks, shell bulkheads or framing members, the use of doublers shall be avoided in favor of insert plate or reinforcing rings. Wherever insert plates are used, rounded corners with a radius of not less than 3" are to be provided. Cuts in strength decks or the shell shall be radiused at the corners as shown on the drawings or, where not indicated, with a radius of 1/8 the transverse dimensions of the opening not to exceed 24". Trunks and coamings in general should be worked with corners rounded to a 3" radius. In longitudinal structural bulkheads and in deckhouse sides, the radii shall be 1/8 the vertical dimensions but not exceed 6". In main transverse structural bulkheads, the radii shall be equal to 1/20 of the vertical dimensions of the cut, but radii need not exceed 6" and shall not be less than 1".
Shims, liners, “dutchmen,” or “sleepers” shall not be used for the purpose of correcting improper fit.
All penetrations of fire boundaries shall be collared as appropriate to meet the requirements of their particular classification or regulatory body requirements.
6.1.2 Foundations
Strength and rigidity of all foundations shall be sufficient for the weight of the equipment, including operating fluids, weight of supported ancillary components, and dynamic loading induced by vessel motion and equipment operation.
Foundations shall be made from steel plate and shapes, welded together and to the ship’s structure. Foundations shall be attached to primary structure, which shall be stiffened where necessary to carry both static and dynamic loads. Foundation design and construction shall account for variations in the flatness of the existing, decks, bulkheads, frames, etc. For example, foundations may need to be scribbed to match waviness in a deck in order to achieve effective connection of a flat mounting surface for equipment.
Items weighing less than 100lbs may be supported by foundations or bracket assemblies, as appropriate for the installation and adjoining structure.
6.2 PIPING MODIFICATIONS
6.2.1 General Requirements
All new and modified piping systems shall comply with ABS Rules, SOLAS and USCG regulations, The World Health Organization Guide to Ship Sanitation, and CDC Vessel Sanitation Program Standards. Other applicable regulations and standards are listed in 3.1 of these specifications. All valves, flanges, and fittings shall be supplied by manufacturers acceptable to those agencies.
All new piping is assumed to be of the same materials and construction methodology as currently exists on the vessel, unless otherwise specified. All new overboards shall be 316L stainless steel.
Piping systems utilizing mechanical connections that have ABS, USCG, and SOLAS approvals for the appropriate service may be substituted with the approval of the COR.
Piping systems and related material shall be designed, furnished, and installed as necessary to ensure complete and efficient operation of all systems, components, and machinery under all conditions of service.
Except where open ceiling systems are intended, all piping in accommodation spaces shall be concealed behind ceiling panels and sheathing as much as possible. In order to maintain maximum headroom, all piping shall be kept behind framing and as close as practical to deck beams, bulkheads, and the underside of decks. Piping may pierce girders, provided approved compensation is made at the penetration.
Welded joints shall be incorporated in the design to the maximum extent consistent with maintenance requirements of system components. Where piping is connected to machinery and equipment, provision shall be made so that stresses due to expansion and contraction of piping are not transmitted to the machinery or equipment.
The selection and application of thermal insulation and lagging for all new and disturbed previously insulated piping shall be in accordance with ASTM F683, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery, except as specifically required otherwise by the specifications. The following systems shall be thermally insulated against sweating:
• Chill water
• Fresh water cooling
• Potable water (hot and cold)
• Refrigeration (both stores and scientific refrigeration)
• Seawater cooling
6.2.2 Materials
Materials for the various piping systems shall be in accordance with the applicable sections of these specifications and/or shall match existing systems on the vessel and/or as indicate din the specification. ABS Rules and USCG regulations, in conjunction with ASTM F1155, shall be used in selecting materials. Where allowed by Regulatory Bodies and where feasible, piping replacement for they Gray and Black water system shall be replaced with SeaCor material.
Galvanized material shall generally be done by the “hot dip” process; per ASTM A123 and/or A153 as appropriate. Galvanizing damaged during installation shall be repaired in accordance with ASTM A780.
6.2.3 Corrosion Precautions
Piping conveying corrosive media shall be protected from the effects of corrosion and/or corrosion-erosion by the adoption of the following:
• Type valves and fittings in nonferrous piping runs shall be bronze or a material compatible to the applicable piping material.
• Connections between ferrous and nonferrous metal pipe shall be made with a “waster piece” to limit the effects of galvanic corrosion. The waster piece shall be made of
Schedule 160 black pipe with flanged ends and shall be at least 2.5 times as long as the nominal pipe size.
• In lieu of a waster piece, an insulated coupling may be installed between the dissimilar metal lines.
• Turbulence of flow(s) shall be minimized to curb corrosion/erosion by restricting…