This is a Pricing Proposal Form for the General Contracting Pool IDIQ contract with Fermi National Accelerator Laboratory. The detailed Excel spreadsheet provides labor and equipment rates for multiple construction trade categories across five years (base year and four option years), including journeymen, foremen, and apprentices in trades such as bricklayer, carpenter, electrician, plumber, and others. The form instructs offerors to provide fully burdened rates that include wages, overhead, bonds, and administrative costs, with clear guidance on completing rate columns and restrictions on overtime work.
The pricing template covers an extensive range of labor categories and equipment rentals, with estimated quantities for daily, weekly, and monthly equipment use. Key instructions include that proposed rates should be all-inclusive, no overtime is permitted without written approval, and equipment rates include transportation charges. The form allows for markup on sub-subcontract and third-party rental equipment, with a contractor-proposed markup field. The solicitation is part of a broader effort by Fermi National Accelerator Laboratory to establish a pool of subcontractors for facility repair, maintenance, and modernization projects located in Du Page and Kane County, Illinois, with proposals originally due on 12/02/2025 and subsequently amended to 12/04/2025.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Labor Rates
| Labor Straight Time | Company Name: | ||||||||
| Completed by Offeror | Date of Submission: | ||||||||
| Labor Category | Evaluated Quantity (Estimated Hours Per Year) | Base Year 1 | Option Year 1 | Option Year 2 | Option Year 3 | Option Year 4 | Extended Price | ||
| (Base Year 1) | Extended Price | ||||||||
| (Option Year 1) | Extended Price | ||||||||
| (Option Year 2) | Extended Price | ||||||||
| (Option Year 3) | Extended Price | ||||||||
| (Option Year 4) | Extended Total | ||||||||
| (Base & All Options) | Request for Proposal (RFP) No. ISD_368518_DA |
General Contracting Pool
| (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (All Date Ranges) | Pricing Proposal Form | ||
| Bricklayer | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | INSTRUCTIONS TO OFFERORS | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | A. The proposed rates shall be fully burdened and include all wages, overheads, bonds, General and Administrative (G&A), fee, etc. for straight/overtime time work. | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Carpenter | B. No overtime work is permitted without the prior, written approval of the Technical Representative identified on the applicable Task Order. | ||||||||||||
| Journeyman | 3500 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 2500 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1200 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | C. Offeror’s hourly rates are inclusive of Tools and Consumable Items as identified in Exhibit Q and Exhibit R of this RFP. | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Cement Mason | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | D. Offeror shall complete Columns C, D, E, F, and G with the appropriate labor rates. Columns I, J, K, L, M, and N will calculate automatically and should not be modified. | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Electrician | |||||||||||||
| Journeyman | 500 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 200 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 150 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Excavation | |||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Laborer | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| General | |||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| HVAC | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Insulator | |||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Iron Worker | |||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Laborer | |||||||||||||
| Journeyman | 300 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 100 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Landscaper | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Millwright | |||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Operating Engineer | |||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Painter | |||||||||||||
| Journeyman | 250 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 100 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Pipefitter | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Plumber | |||||||||||||
| Journeyman | 350 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 100 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 150 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Project Management | |||||||||||||
| Project Manager | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Roofer | |||||||||||||
| Journeyman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Sheet Metal Worker | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Sprinkler Fitter | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Superintendent | |||||||||||||
| Representative | 2080 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Welder | |||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Labor STRAIGHT TIME Total | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Time and One Half | ||||||||
| Completed by Offeror | ||||||||
| Labor Category | Evaluated Quantity (Estimated Hours Per Year) | Base Year 1 | Option Year 1 | Option Year 2 | Option Year 3 | Option Year 4 | Extended Price | |
| (Base Year 1) | Extended Price | |||||||
| (Option Year 1) | Extended Price | |||||||
| (Option Year 2) | Extended Price | |||||||
| (Option Year 3) | Extended Price | |||||||
| (Option Year 4) | Extended Total |
(Base & All Options)
| (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (All Date Ranges) | ||
| Bricklayer | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Carpenter | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Cement Mason | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Electrician | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Excavation | ||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Laborer | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| General | ||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| HVAC | ||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Insulator | ||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Iron Worker | ||||||||||||
| Journeyman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Laborer | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Landscaper | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Millwright | ||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Operating Engineer | ||||||||||||
| Journeyman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Painter | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Pipefitter | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Plumber | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Project Management | ||||||||||||
| Project Manager | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Roofer | ||||||||||||
| Journeyman | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Sheet Metal Worker | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 1 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 2 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 3 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Apprentice 4 | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Sprinkler Fitter | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Superintendent | ||||||||||||
| Representative | 2080 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Welder | ||||||||||||
| Journeyman | 80 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Foreman | 40 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||
| Labor TIME AND ONE HALF Total | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Equipment Rates
| Equipment Rates | Company Name: | ||||||||
| Completed by Offeror | Date of Submission: | ||||||||
| Equipment Category | Evaluated Quantity (Estimated Hours Per Year) | Base Year 1 | Option Year 1 | Option Year 2 | Option Year 3 | Option Year 4 | Extended Price | ||
| (Base Year 1) | Extended Price | ||||||||
| (Option Year 1) | Extended Price | ||||||||
| (Option Year 2) | Extended Price | ||||||||
| (Option Year 3) | Extended Price | ||||||||
| (Option Year 4) | Extended Total | ||||||||
| (Base & All Options) | Request for Proposal (RFP) No. ISD_368518_DA |
General Contracting Pool
| Date Range: | (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (1/1/26 - 12/31/26) | (1/1/27 - 12/31/27) | (1/1/28 - 12/31/28) | (1/1/29 - 12/31/29) | (1/1/30 - 12/31/30) | (All Date Ranges) | Pricing Proposal Form | |
| 10' Scissors lift | |||||||||||||
| Daily | 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | INSTRUCTIONS TO OFFERORS | |||||
| Weekly | 3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | A. The above rates are fully burdened and include all transportation (pickup/return) charges. | |||||
| 2" electric water pump | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | B. Sub-subcontract and Third Party Rental Equipment costs incurred as a result of performance of this subcontract that are not included in this tab, Exhibit Q or Exhibit R shall be billed at invoice cost plus ____ percent (__) markup. | |||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 2" gas water pump | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | Offeror Proposed Markup for Sub-subcontract and Third Party Rentals | |||||
| 20' Scissors lift | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | C. Offeror-owned Equipment costs incurred as a result of performance of this subcontract and not included in this tab, Exhibit Q or Exhibit R shall be billed at rates approved in writing by the Laboratory. Such rates shall not exceed fair market, third party rental rates for like equipment; nor shall any additional charges be added to such billing. | |||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 3" gas water pump | |||||||||||||
| Daily | 16 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 30' Articulating Manlift | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | D. Offerors shall complete Columns C, D, E, F, and G with the appropriate equipment rates. Columns I, J, K, L, M, and N will calculate automatically and should not be modified. | |||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 30' Scissors lift | |||||||||||||
| Daily | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 35' Bucket Truck | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 4 Wheel Tractor w/1.5 yard front end loader and .5 cubic yard backhoe attachment | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 45' Articulating Manlift | |||||||||||||
| Daily | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| 60' Articulating Manlift | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Air Nailer w/small Compressor | |||||||||||||
| Daily | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Airless Paint Sprayer | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Backhoe (410 Deere equivalent) with all attachments | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Cable Trailer w/truck | |||||||||||||
| Daily | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Compact ("mini") Excavator (26G Deere equivalent) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Conduit bender (up to 4") | |||||||||||||
| Daily | 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Crawler Dozer (750L Deere equivalent) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Cut off saw (Stihl 440 equivalent) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Dump Truck 5 cubic yards | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Dump Truck 12 cubic yards | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Gas powered air compressor (100-500 CFM) w/100 foot hose, air hammer with points | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Gas Welder | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| High Power Auger | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| High Pressure Washer | |||||||||||||
| Daily | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 3 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Laser Level-Interior/Exterior w/sensor | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Light tandem roller (Bomag BW135 equivalent) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Mid Size Excavator (210 Deere equivalent) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Mig Welder | |||||||||||||
| Daily | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Oxy/Acetylene Cutting Torch | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Pipe Threader (up to 4") with gruvlok attachment. | |||||||||||||
| Daily | 15 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Plate Compactor (300lb equivalent) | |||||||||||||
| Daily | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Roustabout Hanger (15', 1500lb capacity equivalent) | |||||||||||||
| Daily | 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Skid Steer (330G Deere equivalent) | |||||||||||||
| Daily | 10 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 2 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Stick Welder | |||||||||||||
| Daily | 20 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 4 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Tig Welder | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Trench Shield-Excavation Box(es) | |||||||||||||
| Daily | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Vacuum Excavator (Ditch Witch FX65 equivalent or greater) | |||||||||||||
| Daily | 60 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Walk Behind Trencher 8” minimum depth | |||||||||||||
| Daily | 60 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Weekly | 12 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Monthly | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Total Equipment Cost | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Proposal Total
| Company Name: |
| Date of Submission: |
Request for Proposal (RFP) No. ISD_368518_DA General Contracting Pool
Pricing Proposal Form
| Straight Time | Date Range | LABOR |
| Labor Total Base Year 1 | (1/1/26 - 12/31/26) | $ - 0 |
| Labor Total Option Year 1 | (1/1/27 - 12/31/27) | $ - 0 |
| Labor Total Option Year 2 | (1/1/28 - 12/31/28) | $ - 0 |
| Labor Total Option Year 3 | (1/1/29 - 12/31/29) | $ - 0 |
| Labor Total Option Year 4 | (1/1/30 - 12/31/30) | $ - 0 |
| Straight Time Subtotal | $ - 0 |
| Time and One Half | ||
| Labor Total Base Year 1 | (1/1/26 - 12/31/26) | $ - 0 |
| Labor Total Option Year 1 | (1/1/27 - 12/31/27) | $ - 0 |
| Labor Total Option Year 2 | (1/1/28 - 12/31/28) | $ - 0 |
| Labor Total Option Year 3 | (1/1/29 - 12/31/29) | $ - 0 |
| Labor Total Option Year 4 | (1/1/30 - 12/31/30) | $ - 0 |
| Time and One Half Subtotal | $ - 0 | |
| Total Labor Price | $ - 0 |
| Date Range | EQUIPMENT | |
| Equipment Total Base Year 1 | (1/1/26 - 12/31/26) | $ - 0 |
| Equipment Total Option Year 1 | (1/1/27 - 12/31/27) | $ - 0 |
| Equipment Total Option Year 2 | (1/1/28 - 12/31/28) | $ - 0 |
| Equipment Total Option Year 3 | (1/1/29 - 12/31/29) | $ - 0 |
| Equipment Total Option Year 4 | (1/1/30 - 12/31/30) | $ - 0 |
| Total Equipment Price | $ - 0 |
Total Proposal Price (Labor + Equipment) $ - 0
Contractor Proposed Markup for Subcontract and Third Party Rentals 0%