This is a Design Build Request for Proposal (RFP) for an IRS Fire Alarm Replacement project issued by the General Services Administration (GSA) under Solicitation No. 47PB5126R0029. The Government seeks proposals for the design and construction of a complete fire alarm system replacement at the IRS headquarters located at 1111 Constitution Ave. NW, Washington, DC 20224.

The estimated contract value ranges from $20,000,000 to $25,000,000 with a firm fixed-price contract type. Proposals are due by August 20, 2026 at 4:00 PM local time via email to Douglas.tumbrello@gsa.gov. A pre-proposal conference and site visit are scheduled for July 21, 2026 at 9:00 AM local time, with virtual attendance and in-person site touring available. A bid guarantee of 20 percent of the bid price or $3,000,000 (whichever is less) is required, and upon award, the contractor must provide performance and payment bonds. Award will be made to the responsible offeror whose proposal represents the best value, evaluated on three equally-weighted technical factors: Past Experience (35%), Past Performance (35%), and Site Specific Project Management Plan (30%), combined with total evaluated price. The offeror must demonstrate three similar projects completed within the last five years involving fire alarm replacement in occupied buildings of at least 800,000 gross square feet, with at least 70 percent self-performed work and minimum $15 million contract values. Key personnel requirements include a Project Manager with PMP Certification and five years' experience and an On-Site Construction Superintendent with Construction Manager Certification and three years' experience. The Site Specific Project Management Plan must address construction and staffing plans, accident prevention, quality control, permitting procedures, and commissioning responsibilities.

View the file

Other files

File Type Posted
SF 30 Amendment 1.pdf PDF
Fire Alarm Modernization Project Walkthrough _Virtual List - Walkthrough _ Virtual List.pdf PDF
Pre-Proposal Site Visit Agenda 07 21 2026.pdf PDF
SOW Attachment 3 _ IRS FAS Replacement CD Waste Mgmt Plan Reporting Template v2.xlsx XLSX spreadsheet
SOW Attachment 12 _ Child Care Center Design Guide.pdf PDF
SOW Attachment 4 _ C and D Waste Monthly Report.pdf PDF
Individual Model_Subcontracting_Plan - Dec 2025 - 508 Compliant.docx DOCX document
SOW Attachment 7 _ HISTORIC STRUCTURES REPORT MARCH 1981.pdf PDF
SOW Attachment 6 _ NDA Document Security.pdf PDF
SF1442-22.pdf PDF
DRAFT IRS Fire Alarm Replacement Agreement.pdf PDF
SOW Attachment 11 _ IRS Feasibility - Program Study Fire Life Safety Replacement.pdf PDF
SOW Attachment 8 _ DC0022 IRS Building Annual Asbestos Inspection _ Survey Report-FINAL.pdf PDF
SOW Attachment 1 _ 283176 - FIRE ALARM AND VOICE EVACUATION SYSTEM.pdf PDF
SOW Attachment 10 _ 02085-Asbestos-April 2013.pdf PDF
SOW Attachment 2 _ 284800 EMERGENCY RADIO COMMUNICATION ENHANCEMENT SYSTEM.pdf PDF
Contractors Qualifications and Financial GSA527-21a.pdf PDF
Davis Bacon Wage Rates Washington DC.pdf PDF
SOW Attachment 5 _ GSA Affiliated Customer Accounts (GACA).pdf PDF
SOW Attachment 9 _ 01546-Safety and Health.pdf PDF
SOW FINAL IRS FA Replacement SOW Design-Build Services April 2026.pdf PDF
Bid Bond form SF24-23a.pdf PDF
Attachment PPQ.pdf PDF
GSA Cost Bid Form IRS HQ Fire Alarm Project.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sol_DB_1_Phase

GSA Solicitation No.47PB5126R0029

Design Build Contract for: IRS Fire Alarm Replacement

The Solicitation

Document: DB201A/MAY 2026 (The Solicitation)

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. Receipt of Offers

II. Proposals

A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions

A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Notice Concerning Preparation of Proposals F. Bond Requirements G. Contractor Performance Information H. Safeguarding and Dissemination of Controlled Unclassified Information

(CUI) Building Information

IV. FAR/GSAR Solicitation Provisions FAR 52.209-7 Information Regarding Responsibility Matters (GSA Class Deviation RFO-2025-09) FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (GSA Class Deviation RFO-2025-09) FAR 52.216-1 Type Of Contract (GSA Class Deviation RFO-2025-16) FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work Buy American Requirements Buy American Exceptions FAR 52.233-2 Service of Protest (GSA Class Deviation RFO-2025-33) FAR 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (GSA Class Deviation RFO-2025-09) FAR 52.252-1 Solicitation Provisions Incorporated by Reference GSAR 552.102 Incorporating Provisions and Clauses by Reference

GSAR 552.252-5 Authorized Deviations in Provisions Small Business Subcontracting Plan

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (GSA

Class Deviation RFO-2025-15) B. 52.222-90 Addressing DEI Discrimination by Federal Contractors C. Security Requirements D. Additional Clauses

VI. Method Of Award

A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offers

I. General Information I.A. The Solicitation and Contract

(1) This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award (4)The Agreement and Attachments to the Agreement

(5) The Statement of Work, Specifications, Drawings, and Exhibits

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information

Name: Douglas Tumbrello

Authorized Representative Information:

Address: One World Trade Center, 54th Floor, New York, NY 10007

Telephone: 917-574-3499

Email: douglas.tumbrello@gsa.gov

Alternate POC Information

Name: Mark Lewandowski

Address:100 South Independence Mall West, Philadelphia, PA 19106

Email: mark.lewandowski@gsa.gov

I.D. Pre-Proposal Conference

Date: July 21, 2026

Time:9 AM local time

Location: Virtual

GSA will host a virtual pre-proposal conference and a site visit. The virtual pre-proposal conference will provide Offerors with a briefing on the project, GSA's source selection procedures, and the overall process, allowing time for general questions. A site visit, intended to allow Offerors the opportunity to tour the project site, will be conducted immediately following the virtual pre-proposal conference for all in-person attendees at 1111 Constitution Ave. NW, Washington, DC 20224.

To register for the pre-proposal conference and site visit, please email Douglas Tumbrello at douglas.tumbrello@gsa.gov by Friday, July 17, 2026, at 4:00 p.m. with a list of individuals interested in attending. The list should include each attendee’s name, email address, title, company, and whether they will be attending the virtual pre-proposal conference, the site visit, or both. Additional information, including instructions for joining the virtual conference, will be provided to those who register.

I.E. Estimated Price Range

Offerors are advised that this is a procurement with an estimated range of $20,000,000

- $25,000,000.Offerors are cautioned that price proposals exceeding this range may be determined ineligible for award based on budgetary limitations.

I.F. FAR 52.228-1 Bid Guarantee (Sep 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids;

and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm local time on the following date and at the following address.

● Date: August 20, 2026

● Address: Email: Douglas.tumbrello@gsa.gov cc:mark.lewandowski@gsa.gov mailto:Douglas.tumbrello@gsa.gov mailto:mark.lewandowski@gsa.gov

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

2. Technical Proposal

3. Representations and Certifications

4. Standard Form 24, Bid Bond

5. Subcontracting Plan

6. GSA Form 527 – Contractor’s Qualification and Financial Information

7. Other Documents as Required

II.B. Proposal Format Offerors are encouraged to make their proposals only as voluminous as is necessary to respond to the preparation instructions set forth in the solicitation.

In addition, notice should be taken of the size and page limitations specified in the instructions below. Each proposal shall consist of two (2) separate parts as indicated below. Offerors are required to submit proposals as delineated below:

Part I – Technical Proposal and Related Documents Part II – Price Proposal and Related Documents

● Technical Proposal:

The technical proposal must contain all of the necessary information to address the evaluation factors as set forth in the solicitation. The maximum page limit for the technical proposal submission is 12 pages. If more than 12 pages are submitted, only the first 12 pages will be evaluated.

Note: The CPARS or Past Performance Questionnaire(s) are excluded from the page limitation. All other pages (including cover page), are included in the page limitation. All pages in the technical proposal must be

8.5 inches by 11 inches. Pages that differ from these page dimensions will not be evaluated.

● Pricing Proposal

The pricing proposal, which must be separate from the technical proposal, must contain the following information:

○ Signed Standard Form 1442 with all amendments acknowledged

○ Completed and signed offer sheet (GSA Pricing Form)

○ Evidence of Bonding Capacity

○ GSA Form C301, Representations and Certifications

○ GSA Form 527, Contractor’s Qualifications and Financial

Information

○ If applicable, Joint-Venture Agreement and any Mentor-Protégé

Agreements

○ The information required under FAR 52.215-1(c)(2) (GSA Class

Deviation RFO-2025-15)

○ Any other information required by the solicitation

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

II.D. Technical Proposal

Technical Factor Relative Weight

1. Past Experience 35%

2. Past Performance 35%

3. Site Specific Project Management Plan 30%

3.7 Evaluation Factors Defined

Technical Factor # 1 Past Experience on Similar Projects - 35% - This factor evaluates the Offeror’s past experience as a firm in providing relevant work to determine its ability to complete the tasks detailed in the scope of work. The SSEB agrees that Past Experience would be deemed relevant in terms of scope, magnitude and complexity of the project. For the purposes of this solicitation, "self-performed" means that the work was executed by the Offeror's direct employees, utilizing the Offeror's own equipment and resources, and under the direct supervision and control of the Offeror's management. The Offeror must demonstrate successful experience within the last five (5) years from the date of award. The Offeror must submit three (3) similar projects, such that each project description does not exceed two (2) pages. In this solicitation, projects are defined as “similar” if the project meets the following characteristics:

1. Project(s) where the Offeror self-performed at least 70% of the design and phased installation of new and code compliant fire alarm addressable devices and phased demolition of the old devices.

2. Project(s) were performed in an occupied and functioning building(s) of at least 800,000 GSF.

3. Project(s) involved the following disciplines in the design build process:

architectural, electrical, fire alarm, elevator, and historical preservation.

4. The total project(s) construction cost at award of the contract was not less than $15 million.

5. The project(s) installation and demolition work were performed during building off hours with pertinent noise and dust control. The projects description must include how the offeror managed requirements for noise and dust control in an occupied facility during operational hours

For each project offered under this evaluation factor, the Offeror must include the following project details:

○ Project Title

○ Site Geographical Location

○ Type of Contract (i.e. design build, firm fixed price)

○ Initial Construction Contract Amount

○ Final Construction Contract Amount

○ Initial Completion Date

○ Actual Completion Date

○ Gross square footage of the building

○ Scope summary and description of fire alarm and device replacement work in the fully occupied facility with historic features and/or areas.

○ Professional Project Reference of where work was performed (first/last name, company, email address, and telephone number)

Standard for Evaluation The standard is met when the Offeror submits three (3) distinct, similar projects that demonstrate successful experience within the last five (5) years from the date of award, with each project description not exceeding two (2) pages, and providing all required project details.

Technical Factor #2 Past Performance on Similar Projects - 35% – This factor will be a subjective assessment. The Government is seeking to determine whether the offeror has consistently demonstrated a commitment to customer satisfaction, timely delivery of services, adherence to contract schedules, subcontractor management, safety management, quality control programs, good workmanship, conformance to specifications, and fair and reasonable prices.

The Offeror must submit a Past Performance Questionnaire (PPQ); included in the solicitation as an attachment, completed by the applicable client, for performing services for each project listed in Factor 1. Ensure correct phone numbers and email addresses are provided for the client point of contact.

Offerors should follow up with clients/references to ensure timely submission of questionnaires.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/UEI numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain a database of PPQs submitted by Offerors.

Higher scores will be awarded to offerors who provide CPARS or PPQ with a rating of “Satisfactory” or higher for the projects listed in Factor 1.

Standard for Evaluation The standard is met when the Offeror submits a completed Past Performance Questionnaire (PPQ) for each of the three (3) projects submitted under Technical Factor #1, ensuring all required client contact information (name, company, email, and telephone number) is accurate and that the PPQs are received by the Government.

Technical Factor #3 - Site Specific Project Management Plan - 30% – This factor evaluates the Offeror's on site management capabilities and ability for planning, organizing and controlling the execution fire alarm replacement site work projects including scheduling work, trades coordination, minimization of delays and compliance with campus tenants’ needs. The Site Specific Project Management Plan must address each of the five (5) elements listed below:

1. Project Specific Construction, Staffing and Administrative Plan.

● The project specific construction plan must address who will obtain the necessary permits and how the permits will be obtained by all relevant local permitting agencies.

● Include NICET License (if applicable)

● An organizational chart illustrating key functions and personnel available to support the contract. The staffing plan should include an Organizational Chart and Lines of Authority for project phases.

○ For each key person, identify the proposed duties in the project; identify the person as a part-time or full-time employee and identify which personnel will be responsible for the quality control and safety programs.

○ Provide all professional, technical/subcontractor, managerial and administrative staff needed to perform the scope of work.

○ The Offeror must provide a Resume for the following Key Personnel:

■Project Manager for Construction: Must have a minimum of five (5) years’ experience successfully managing construction projects that meet the criteria for similar projects as defined in the evaluation factor above. The Project Manager must have a PMP Certification.

■On-Site Construction Superintendent: Must have a minimum of three (3) years’ experience successfully managing construction projects that meet the criteria for similar projects as defined in the evaluation factor above. The Superintendent must have a Construction Manager Certification.

■Suggested team members can include the following: Project Executive; Project Manager;

Construction; Superintendent; Quality; Control Coordinator/Superintendent; Project Engineer;

Fire, Life and Safety Coordinator; Construction Supervisor; Testing Engineering firms; and other key individuals.

■Identify who is the full-time on-site contractor representative. This representative is required for the duration of the IRS HQ Fire Alarm Modernization Project

2. Site Specific Accidental Prevention Plan

○ The plan shall address how accidents will be reported to the GSA

PM/COR and Building Manager for IRS. The plan should demonstrate that any accidents shall immediately be reported and any injuries to personnel must be reported to the GSA (Authority Having Justification ‘AHJ’) for the project. The offer must address corrective actions to mitigate on site accidents and injuries.

○ The plan shall address having the onsite Superintendent write a report within 24 hours of the accident and or injury to the GSA AHJ, following OSHA (Occupational Safety and Health Administration) protocols. Incidents without injury must submit a written report to the GSA PM/COR and IRS Building Manager within 24 hours. All accidents or injuries are to be included in daily reports.

○ The plan shall address how the offeror will handle OSHA protocols for this specific site.

○ The plan shall be ready to submit to the GSA AHJ for approval within 7 days of award

3. Site Specific Quality Control Plan

○ The plan must be based upon the USACE (US Army Corp of

Engineers) Three-Phases of Control.

○ The plan shall identify personnel, procedures, instructions, records and forms to be used in carrying out the requirements of the project.

○ The plan shall include workmanship standards, testing and inspection, and coordination with others

○ The plan shall also describe the quality assurance, quality control, and other technical activities that will be implemented to ensure that sampling and analyses are performed in order to meet applicable data quality objectives for the project.

○ The plan shall identify and address the special factors impacting the construction, and specify the considerations and provisions to be made by the offeror during construction of the project. Special factors impacting include, but are not limited to: work hour restrictions, construction phasing, utility outages, security and access requirements, OSHA requirements, staging and storage area space limitations, and asbestos removal and disposal procedures.

○ The plan shall be ready to submit to the GSA AHJ for approval within 7 days of award.

4. Site Specific Plan for Working with Federal, State, and Local Commissions and Entities

○ The plan shall address how the offeror will obtain permits such as, but not limited to sheeting, shoring, welding, cutting, and public space permits as required by federal,and the local DC jurisdiction.

5. Site Specific Commissioning Plan

○ The plan shall identify who is responsible and will be the third party commissioning agent.

○ The plan shall include a pre-Commissioning Checklist completion based on the AEs design recommendations

○ The plan shall address who will perform the coordination of resources to complete post construction commissioning procedures per the AEs design specifications.

Proposals that do not comply with the submission instructions will be deemed non-responsive and will not be considered for evaluation or award.

Standard for Evaluation The standard is met when the Offeror submits a comprehensive Site Specific Project Management Plan that addresses each of the five (5) required elements:

Project Specific Construction, Staffing and Administrative Plan; Site Specific Accidental Prevention Plan; Site Specific Quality Control Plan; Site Specific Plan for Working with Federal, State, and Local Commissions and Entities; and Site Specific Commissioning Plan. This includes providing all required key personnel resumes demonstrating the specified minimum experience and certifications (PMP for Project Manager, Construction Manager Certification for On-Site Superintendent).

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7 (GSA Class Deviation RFO-2025-04)). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. In accordance with FAR 52.204-90 (GSA Class Deviation RFO-2025-04), if an Offeror will not have an active Federal Government contracts registration in SAM when submitting its offer, it shall complete paragraphs (c) and (d) of FAR 52.204-90 (GSA Class Deviation RFO-2025-04) and include its responses with its offer. Offerors shall also submit with their proposal the completed provisions identified in Section IV of this solicitation.

(2) Qualifications of Offerors

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.

Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

II.F. Requirements of Joint Venture Offerors

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

https://www.sam.gov/

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.

III.B. Requests for Clarification or Interpretation

The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 15 calendar days. Prospective Offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results

This acquisition is being conducted under the provisions of FAR Part 15 (GSA Class Deviation RFO-2025-15) as a negotiated procurement. In accordance with FAR 3.104 (GSA Class Deviation RFO-2025-03) and FAR Part 15 (GSA Class Deviation RFO-2025-15), after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such http://www.sba.gov/ http://www.sba.gov/ offers will be made available until after award except as provided by FAR 15 (GSA Class Deviation RFO-2025-15).

III.E. Notice Concerning Preparation of Proposals

Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.F. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Individual Surety-Pledge of Assets.

III.G. Contractor Performance Information

(1)Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment

Completed CPARS evaluations may then be used by the Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.

(2)CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an email that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.

(3)Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.

(4)Contractor Representative (CR) Role: All evaluations will be sent to the Contractor Representative (CR) named on your award. The CR http://www.cpars.gov/ http://www.cpars.gov/ https://www.cpars.gov/cparsweb/lc will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.H. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information

Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

IV. FAR/GSAR Solicitation Provisions

FAR 52.209-7 Information Regarding Responsibility Matters. (NOV 2025) (GSA Class Deviation RFO-2025-09)

(a) Definitions. As used in this provision—

Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

Federal contracts and grants with total value greater than $10,000,000 means—

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror □ has □ does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in–

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).

(End of Provision)

FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (NOV 2025) (GSA Class Deviation RFO-2025-09)

(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial products and commercial services as defined in Federal Acquisition Regulation 2.101.

(b) Certification. [Offeror shall check either (1) or (2).]

__ (1) The Offeror certifies that–

(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international -security-affairs/bureau-of-arms-control-verification-and-compliance/; and

(ii) No entity owned or controlled by the Offeror has engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international -security-affairs/bureau-of-arms-control-verification-and-compliance/; or

__ (2) The Offeror is providing separate information with its offer in accordance with paragraph (d)(2) of this provision.

(c) Procedures for reviewing the annual unclassified report (see paragraph (b)(1) of this provision). For clarity, references to the report in this section refer to the entirety of the annual unclassified report, including any separate reports that are incorporated by reference into the annual unclassified report.

(1) Check the table of contents of the annual unclassified report and the country section headings of the reports incorporated by reference to identify the foreign countries listed there. Determine whether the Offeror or any person owned or controlled by the Offeror may have engaged in any activity related to one or more of such foreign countries.

(2) If such activity might have occurred, review all findings in the report associated with those foreign countries to determine whether or not each such foreign country was determined to be in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or to be not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. For clarity, in the annual report an explicit certification of non-compliance is equivalent to a determination of violation.

However, the following statements in the annual report are not equivalent to a determination of violation:

(i) An inability to certify compliance.

(ii) An inability to conclude compliance.

(iii) A statement about compliance concerns.

(3) If so, determine whether the Offeror or any person owned or controlled by the Offeror has engaged in any activity that contributed to or is a significant factor in the determination in the report that one or more of these foreign countries is in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. Review the narrative for any such findings reflecting a determination of violation or non-adherence related to those foreign countries in the report, including the finding itself, and to the extent necessary, the conduct giving rise to the compliance or adherence concerns, the analysis of compliance or adherence concerns, and efforts to resolve compliance or adherence concerns.

(4) The Offeror may submit any questions with regard to this report by email to NDAA1290Cert@state.gov. To the extent feasible, the Department of State will respond to such email inquiries within 3 business days.

(d) Do not submit an offer unless—

(1) A certification is provided in paragraph (b)(1) of this provision and submitted with the offer; or

(2) In accordance with paragraph (b)(2) of this provision, the Offeror provides with its offer information that the President of the United States has

(i) Waived application under 22 U.S.C. 2593e(d) or (e); or

(ii) Determined under 22 U.S.C. 2593e(g)(2) that the entity has ceased all activities for which measures were imposed under 22 U.S.C. 2593e(b).

(e) Remedies. The certification in paragraph (b)(1) of this provision is a material representation of fact upon which reliance was placed when making award. If the Government later determines that the Offeror knowingly submitted a false certification, in addition to other remedies available to the Government, such as suspension or debarment, the Contracting Officer may terminate any contract resulting from the false certification.

(End of provision)

FAR 52.216-1 Type of Contract (NOV 2025) (GSA Class Deviation RFO-2025-16)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (NOV 2025) (GSA Class Deviation RFO-2025-22)

(a)(1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

Buy American Requirements

52.225-11 Buy American-Construction Materials under Trade Agreements. (GSA Class Deviation RFO-2025-25)

(a) Definitions. As used in this clause—

Caribbean Basin country construction material means a construction material that—

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section40102(4)&num=0&edition=prelim components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the

United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Designated country means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong

Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New

Zealand, North Macedonia, Norway, Poland, Portugal, Romania, Singapore, Slovak

Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);

(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Chile, Colombia, Costa

Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the

Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

Designated country construction material means a construction material that is a WTO

GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if—

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be

65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Free Trade Agreement country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.

Least developed country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a least developed country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

United States means the 50 States, the District of Columbia, and outlying areas.

WTO GPA country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.

(b) Construction materials.(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for…