IFB Upper Hoh.pdf
PDF 10 MB Posted
- Attached to
- WA Jeff 91420(1), Upper Hoh River Road Phase 2
- Solicitation number
- 69056719B000003
About this file
This file describes a federal contract opportunity for road construction services. The solicitation number is 69056719B000003 for WA Jeff 91420(1), Upper Hoh River Road Phase 2 bid documents from the Department of Transportation Federal Highway Administration. The opportunity type is a solicitation for construction of the second phase of the Upper Hoh River Road. The bid documents provide details on required road construction services for this federally funded infrastructure project, with responses due on the date specified in the solicitation. Relevant information includes the federal agency involved, work requirements, and response deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary_Upper Hoh.pdf | ||
| QA_01-07-2021.pdf | ||
| Amendment A005.pdf | ||
| QA_01-06-2021.pdf | ||
| QA_01-05-2021.pdf | ||
| Amendment A004.pdf | ||
| QA_12-31-2020.pdf | ||
| Amendment A003.pdf | ||
| Amendment A002.pdf | ||
| QA_12-22-2020.pdf | ||
| Amendment A001.pdf | ||
| Amendment A001.pdf | ||
| A001 Tower Cr Bridge sheet pile plans.pdf | ||
| A001 Tower Cr Bridge construction plans.pdf | ||
| QA_12-10-2020.pdf | ||
| QA_12-09-2020.pdf | ||
| QA_12-07-2020.pdf | ||
| QA_12-02-2020.pdf | ||
| wa-a2013020-Final_Plans.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BIDS
Solicitation No. 69056719B000003
WA JEFF 91420(1)
Upper Hoh River Road Phase 2
Solicitation, Offer & Award, Bid Schedule, Contract Clauses, General Wage Decision, Special Contract Requirements, and Plans
This solicitation cites Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14 This project uses U.S. Customary units of measure
ISSUING OFFICE:
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
610 EAST FIFTH STREET
VANCOUVER, WA 98661-3801
Phone: (360) 619-7520 – FAX: (360) 619-7932 e-mail : wfl.contracts@dot.gov
QUICK INDEX
Page Item --- Bid Submittal Checklist --- Authority to Sign --- Bid Bond --- Table of Contents A-1 Notice to Bidders A-3 SF 1442, Solicitation, Offer and
Award A-7 Bid Schedule B-1 Solicitation Provisions C-1 Contract Clauses D-1 General Wage Decision E-1 Special Contract Requirements H-1 Permits I-1 Reserved J-1 Fire Protection and Suppression
BID REMINDERS
Electronic bids will not be accepted. Submit printed copy of bid to the address listed on the enclosed SF 1442. Before submitting your bid, please review the following:
• Have you rechecked your bid figures?
• Have you completed the bid schedule?
• Have you completed and signed the SF 1442, Solicitation, Offer & Award?
• Have you acknowledged all amendments?
• Have you completed the Representations &
Certifications (Page B-1)?
• Is your bid guarantee enclosed in proper form and amount (see FAR Clause 52.228-1), including Power of Attorney affidavit?
• Does the lower left corner of the proposal envelope state “Bid Enclosed”?
• Does the lower left corner include the Solicitation Number and the project number/name?
This solicitation is offered as full and open competition
Bid Opening Date:
See Page A-3, Block 13A
A-1 Notice to Bidders mailto:wfl.contracts@fhwa.dot.gov
PROJECT No. WA JEFF 91420(1)
PROJECT NAME Upper Hoh River Road Phase 2
BEGINNING AT See Plans
ENDING AT See Plans
LENGTH See Plans
NATIONAL Olympic National Park
COUNTY Jefferson
STATE Washington
FIXED COMPLETION DATE See FAR Clause 52.211-10 (FAR Clauses begin on page C-1)
Bid Submittal Checklist
WA JEFF 91420(1), Upper Hoh River Road Phase 2
Before submitting your bid, please review the following:
Done?
Is this in the envelope?
Bid Envelope
Did I correctly address the envelope? (See page A-3, blocks 7 & 8) Does the lower left corner of the envelope include the Solicitation Number and the project name/number?
Pages A-3 & A-4 (SF 1442, Solicitation Offer & Award) Did I include our firm name and address in block 14?
Did I include our firm’s phone number in block 15?
Did I include our firm’s remittance address in block 16?
(Use when different than block 14)
Did I include my unique entity identifier and Cage Code?
Did I include the number & date of all amendments in block 19?
Did the appropriate official sign/date in block 20A, 20B & 20C?
Bid Schedule (see page A-7) Did I insert “Unit Bid Price” and “Amount Bid” for each bid item?
Did the appropriate official initial corrections?
When applicable, did I include the totals for each schedule in the summary page? (See last page of bid schedules.)
Bid Bond (Standard Form 24) Bids received without a valid bid bond will be rejected.
Did I complete my bid bond correctly?
Did I include the original?
Did I attach the Power of Attorney to the bid bond?
Authority to Sign Did I include a completed form for each person signing the SF1442 and Bid Bond?
Representations & Certifications & FAR Clause Did I include the completed B-pages (beginning on B-1)?
Did I include the completed clause 1252.228-73 Notification of Miller Act Payment Bond Protection (See page C-128)?
System for Award Management (SAM) https://www.sam.gov/portal/public/SAM/
Do we have up-to-date data in SAM?
Veteran Reporting (FAR Clause 52.222-37) If applicable, did I ensure our firm has completed this annual report?
NOTE: The Contractor is fully responsible to verify that all data is correct each time a bid package is submitted. Failure to properly input and/or update your data may cause the bid to be rejected.
https://www.sam.gov/portal/public/SAM/
Driving Directions to our Vancouver Washington Office:
Directions to WFLHD https://www.google.com/maps/place/610+E+5th+St,+Vancouver,+WA+98661/data=!4m2!3m1!1s0x5495a8ae3f2d7083:0x5b7adcfa96ade37a?hl=en
Authority to Sign
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the corporation named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
_____________________________________ (signature) Affix Corporate Seal
_____________________________________ (title)
INSTRUCTIONS: When the offeror/principal is a limited liability company, include this certification with your offer/bid.
Limited Liability Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the limited liability company named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this company;
that the offer was duly signed for and on behalf of said company by authority and scope of its governing body, and within the scope of its powers.
_____________________________________ (signature) Affix Company Seal (as applicable) __________ _________________________ (title)
INSTRUCTIONS: When the offeror/principal is a partnership, include this
Authority to Bind Partnership
This certifies that the names and signatures of all partners are listed below, and that the person signing the proposal has the authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all partners)
INSTRUCTIONS: When the offeror/principal is a joint venture, include this
Authority to Bind Joint Venture
This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all applicable individuals)
INSTRUCTIONS: When the offeror/principal is a sole proprietorship, the signature on the offer/bid and on the bonds must be as follows:
Sole Proprietorship Requirement
An Offeror/Principal that is a sole proprietorship must submit an offer/bid and a bond signed by the sole proprietor, or by one duly authorized to sign for the sole proprietor.
If the signature is by someone other than the sole proprietor, a copy of the power of attorney authorizing the individual to sign must be provided with the offer/bid.
RESERVED
BID BOND
(See instructions on reverse)
DATE BOND EXECUTED (Must not be later than bid opening date) OMB Control Number: 9000-0045
Expiration Date: 8/31/2022 Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 25 minutes to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.
SURETY(IES) (Name and business address)
PENAL SUM OF BOND BID IDENTIFICATION
PERCENT
OF BID
PRICE
AMOUNT NOT TO EXCEED BID DATE INVITATION NUMBER 69056719B000003
MILLION(S) THOUSAND(S) HUNDRED(S) CENTS
FOR (Construction, Supplies or Services)
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
PRINCIPAL
SIGNATURE(S)
1.
(Seal)
2.
3.
Corporate Seal NAME(S) &
TITLE(S)
(Typed)
1. 2. 3.
INDIVIDUAL SURETY(IES)
SIGNATURE(S) 1.
2.
(Seal)
NAME(S)
(Typed)
1. 2.
CORPORATE SURETY(IES)
SU
R
ET
Y
A
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Seal SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is NOT usable
STANDARD FORM 24 (REV. 8/2016)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
INDIVIDUAL PARTNERSHIP JOINT VENTURE
CORPORATION OTHER (Specify)
STATE OF INCORPORATION
SU
R
ET
Y
B
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate Seal SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
SU
R
ET
Y
C
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate Seal SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
SU
R
ET
Y
D
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
Corporate Seal SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
SU
R
ET
Y
E
NAME &
Seal
SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
SU
R
ET
Y
F
NAME &
SIGNATURE(S)
1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
SU
R
ET
Y
G
NAME &
SIGNATURE(S) 1. 2.
NAME(S) &
TITLE(S)
(Typed)
1. 2.
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE
SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.
The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
STANDARD FORM 24 (REV. 8/2016) BACK
Table of Contents Project: WA JEFF 91420(1), Upper Hoh River Road Phase 2
TABLE OF CONTENTS
08/01/19–FP14
DESCRIPTION PAGE
Notice to Bidders ........................................................................................................................ A-1
Solicitation, Offer, and Award (SF 1442) ................................................................................... A-3
Bid Schedule ............................................................................................................................... A-7
Solicitation Provisions ................................................................................................................ B-1
Contract Clauses ......................................................................................................................... C-1
General Wage Decision .............................................................................................................. D-1
SCRs Table of Contents
SPECIAL CONTRACT REQUIREMENTS (SCR)
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U.S. Department of Transportation, Federal Highway Administration.
Division 100 ..................................................................................................................... E-1
Division 150 ................................................................................................................... E-27
Division 200 ..................................................................................................................... F-1
Division 250 ..................................................................................................................... F-6
Division 400 ................................................................................................................... F-12
Division 550 ................................................................................................................... F-14
Division 600 ................................................................................................................... F-24
Division 700 .................................................................................................................... G-1
Permits ........................................................................................................................................ H-1
Reserved ........................................................................................................................................ I-1
Fire Protection and Suppression Plan .......................................................................................... J-1
Table of Contents
(This page intentionally left blank)
A-1
Notice to Bidders Project: WA JEFF 91420(1), Upper Hoh River Road Phase 2
NOTICE TO BIDDERS
08/01/19–FP14
THIS PROJECT IS BEING SOLICITED AND AWARDED UNDER FP-14.
The FP-14 is FLH’s Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. To view the FP-14 electronically go to:
https://flh.fhwa.dot.gov/business/resources/specs/.
The FP-14 is a dual unit document with U.S. Customary units being the primary unit shown.
Metric equivalents are shown in parenthesis.
When submitting bids, drawings, calculations, and other construction documents, use only U.S. Customary units of measure, unless otherwise stated.
I. Project Location
General Location. The project work is located 16.7 miles SE of Forks, WA in Jefferson County.
Approximate Global Positioning System (GPS) coordinates for the beginning of the project are 47°49'20.99"N, 124°11'47.92"W.
Project Limits. Signs have not been erected to identify the project limits. No Government personnel will be available for show-me tours.
II. Pre‐ bid Information.
GENERAL AND TECHNICAL QUESTIONS REGARDING PROPOSED WORK FOR
THIS PROJECT WILL BE ACCEPTED UNTIL CLOSE-OF-BUSINESS ON
12/29/2020.
Refer to page A-5 for information on how to submit questions related to General Information and Technical Information. Answers to General and Technical Questions will be posted at https://beta.sam.gov/opp/8e56d101291d4a518c62d9096eb8ef95/view.
Every attempt to respond to questions will be made. However, response to questions received after the above posted date is not guaranteed.
Multiple Schedules. Offers for the construction of this project are being invited under four bid schedules, designated A, B, C and D. Schedule A, Schedule B, Schedule C and Schedule D are not alternate bids. Complete all schedules according to Subsection 102.02 of the special contract requirements. Award of the contract will be made according to Subsection 102.05A.
A-2
Project: WA JEFF 91420(1), Upper Hoh River Road Phase 2
Electronic Plan Sheets. This solicitation includes electronic plan sheets available at https://beta.sam.gov/opp/8e56d101291d4a518c62d9096eb8ef95/view. A paper copy of the plan sheets is available by submitting the form posted with this solicitation.
Physical Data. Physical data applicable to this project is listed in FAR Clause 52.236-4 Physical Data.
Representations & Certifications. Submit or update Representations and Certifications online at https://www.sam.gov/SAM/ before bid submittal. For more details go to FAR Provision 52.204- 8 Annual Representations and Certifications (see page B-2.). If you have previously registered on-line and the NAICS code for this solicitation is different than the code listed in your online file, please note the amended changes on the lines provided in FAR 52.204-8.
Requests for Information. Requests for technical information (Plan and Division 100 – 700 Specification questions only) about this project will only be accepted in writing (see Block 9 on page A-5).
Price Evaluation Factor. This solicitation contains a Price Evaluation Factor. In accordance with 13 CFR subsection 126.613, we will apply a factor of 10% to an apparent low bid submitted by a large business when we also receive a bid from a HUBZone small business; the 10% factor does not apply to an apparent low bid submitted by a small business.
HUBZone. If the contract is awarded after applying the price preference for HUBZone small business concerns under FAR clause 52.219-4; at least 50 percent of the cost of the contract performance incurred for personnel must be spent on the prime Contractor’s employees or the employees of other qualified HUBZone small business concerns.
SF 1442, Solicitation, Offer, and Award. Particular attention should be paid to Standard Form l442, Solicitation, Offer and Award, to assure that Blocks 14, 15, 16, 19, 20A, and 20C are completed correctly. Sign Block 20B according to the instructions in Subsection 102.02. You must submit a completed ‘Authority to Sign’ document. You must also complete the representations and certifications contained in the Contract Provisions beginning on page B-1.
Failure to furnish or complete any of the above may result in your bid being considered nonresponsive and being rejected.
Facsimile and email bids, modifications, and withdrawals. Facsimile and email bids are not authorized for this solicitation. Bids may be modified or withdrawn by email, if such notice is received by the time specified for receipt of bids. The Government will not be responsible for any failure attributable to the transmission or receipt of email data. See FAR Provision 52.214-5, Submission of Bids. EMAIL WFL.Contracts@dot.gov. To confirm receipt, call 360.619.7520.
A-2a
Project: WA JEFF 91420(1), Upper Hoh River Road Phase 2
Fraud Alert. Current and potential U.S. Department of Transportation (DOT) Contractors have recently been receiving fraudulent letters purporting to be issued by DOT. These fraudulent letters request that the Contractors resubmit their banking information to DOT. If you receive such a letter, please DO NOT complete the requested worksheet that is attached to the letters and DO NOT release any information. To register or update information, Contractors are required to go directly through the System for Award Management (SAM) website and never through a third party. You can access SAM at https://www.sam.gov/SAM/ .
Site Access Constraints. There may be access constraints related to the COVID-19 Pandemic. If you are intending to submit bids and are unable to visit the sites because of access constraints related to the COVID-19 Pandemic, please let us know.
III. Post Award Information.
Insurance. Insurance requirements are described in Subsection 107.05.
Contractor Performance Evaluations. This office posts performance evaluations in the Contractor Performance Assessment Reporting System (CPARS); for additional information, see http://www.cpars.gov/index.htm. Upon receiving an email notice of evaluation availability, you will have 14-60 days to review the evaluation online and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
IV. Specifications and Permits.
Specifications. This solicitation and subsequent contract are governed by the Federal Acquisition Regulation (FAR), agency supplemental regulations, and the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14. An electronic version may be found at http://flh.fhwa.dot.gov/business/resources/specs/. A single paper copy can also be obtained from the Research & Technology Product Distribution Center (RTPDC) by e-mail to:
report.center@dot.gov, or by phone 814-239-1160, or fax 814-239-2156.
Electronic Documentation. Requires all documents (including but not limited to correspondence, notifications, submittals, reports, and pay notes) to be submitted in a pdf format, or an approved fixed-layout electronic format. See Subsection 103.06.
Material Sources. Material sources, waste areas, and water sources have not been identified for this project. Secure all permits and clearances for Contractor-located sites and sources. See Subsection 105.02(c).
A-2b
(This page intentionally left blank)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE
SOLICITATION
(Construction, Alteration, or Repair)
3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661
690567
a. NAME
See Page A-5
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
360-619-7520 x
11/30/2020
1. SOLICITATION NO.
69056719B000003
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This solicitation is designated WA Jeff 91420(1), Upper Hoh River Road Phase 2.
IN STRICT ACCORDANCE WITH:
Bid Schedule
Federal Acquisition Regulations (FAR) and Transportation Acquisition Regulations
(TAR)
General Wage Decision
Special Contract Requirements
Standard Contract Requirements
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14, US Customary
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
* Page A-5
a. Sealed offers in original and
________________________ 01/05/2021
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
SEE BLOCK 10
A-3
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661
8. ADDRESS OFFER TO
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Federal Highway Administration
FHWA WESTERN FED LANDS DIVISION
610 E FIFTH STREET
Vancouver WA 98661
690567
31a. NAME OF CONTRACTING OFFICER (Type or print)
Dean Umathum
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Federal Highway Administration Western Federal Lands Highway Divisions 610 East Fifth Street Vancouver, WA 98661-3801 ATTN: Finance
A-4
Unique Enitity Identifier: (AKA Duns #) Cage Code:
See Page A-5
See Bid Schedule
All Items on Bid Schedule
A-5
Continuation SF 1442
Block 9 FOR GENERAL INFORMATION, call 360.619.7520 from the hours of 8:00 a.m. to 4:00 p.m. local time or e-mail us at wfl.contracts@dot.gov.
FOR TECHNICAL INFORMATION (plan and specification questions only), requests for technical information about this project will only be accepted in writing.
Submit questions via fax (360.619.7932) or e-mail at wfl.plans-spec@dot.gov.
QUESTIONS/ANSWERS POSTED ONLINE. You can view questions and answers on the Contract Opportunities Website https://beta.sam.gov/ .
• Insert the solicitation number in the search box
• Scroll to the project.
• Make sure you are on the most recent view and look in the right section of the page for the most recent Q&A document.
FOR DAVIS-BACON WAGE RATE INFORMATION call the Department of Labor at 415.625.7716 (DRBA - Western Region)
FOR PHYSICAL DATA, See FAR Contract Clause 52.236-4, Physical Data, (clauses begin on page C-1) for a listing of available data. Physical Data will be posted with the solicitation on the Federal Business Opportunities website.
FOR BID RESULTS, Bid opening summary will be posted on the Contract Opportunities Website https://beta.sam.gov/ shortly after bid opening. Bid tabulations will be available on our website approximately 3 work days after the bid opening. Our website is located at: http://flh.fhwa.dot.gov/business/construction/bids/ filter by WFL Division and applicable state.
Block 11 COMPLETION DATE: Work shall be completed on or before the date specified in
FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subject to such extensions as may be authorized by the terms of the contract and the specifications made a part thereof. Contract Clauses begin on pages C-1.
Block 12A PERFORMANCE & PAYMENT BONDS: See FAR Clause, 52.228-15, Performance and Payment Bonds - Construction (clauses begin on page C-1) and Subsection 102.06 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14, U.S. Customary Units.
Block 13B BID BOND AMOUNT: See FAR Clause 52.228-1, Bid Guarantee (clauses begin on page C-1).
ADDITIONAL INFORMATION: See Subsections 102.03 and 102.04 of Standard
Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP- 14, U.S. Customary Units.
Block 24 SUBMITTING INVOICES: See Subsection 109.08 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-14, U.S. Customary Units.
mailto:wfl.contracts@dot.gov mailto:wfl.plans-spec@dot.gov https://beta.sam.gov/ https://beta.sam.gov/ http://flh.fhwa.dot.gov/business/construction/bids/
A-6
Continuation SF 1442
ESTIMATED PRICE RANGE. The price range of the project work is between:
7,000,000 and $10,000,000 for Schedules A and B $10,000,000 and $15,000,000 for Schedule C $15,000,000 and $20,000,000 for Schedule D
SUBCONTRACTING PLAN. This invitation for bids requires a low bidder who is a LARGE business to submit an acceptable subcontracting plan prior to contract award. Do not submit this form with your bid. A large business is one whose average gross annual receipts over the past 3 years equal $36.5 million or more. For your information the subcontracting plan form is included beginning on page A-6a.
This requirement does not apply to SMALL businesses.
A-6a
ATTACHMENT 1 – FHWA SUBCONTRACTING PLAN
1. INSTRUCTIONS:
• Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid. The statement shall be signed by an official authorized to make decisions on behalf of the firm.
• The following information shall be provided in the bidder/offeror subcontracting plan submission and shall be expressed in terms of goal percentages of the total planned subcontracting dollars.
• Text lines may be added to this template as needed.
*insert and complete additional tables if the contract includes option year(s).
1.1 Rationale if establishing a goal lower than 3% for VOSB:
1.2 Rationale if establishing a goal lower than 3% for SDVOSB:
1 Percentage = (subcontracted amount in the category/total planned subcontracted amount) 2 Any dollar amount applied to SDVOSB also applies to VOSB.
3 In this document, the term WOSB includes Economically Disadvantaged WOSB (EDWOSB) concerns.
SUBCONTRACTING GOALS – BASE YEAR
Total prime contract amount – Base Year: $ Total planned subcontracted amount – Base Year: $ Total planned subcontracts to “other than small business” concerns (i.e., large, non-profit, university, etc.)
$ %1
Planned subcontracts to Small Business concerns (not elsewhere counted below):
Total planned subcontracts to Veteran Owned Small Business concerns (VOSB)2:
Total planned subcontracts to Service Disabled Veteran Owned Small Business (SDVOSB) concerns:
Total planned subcontracts to Historically Underutilized Business Zones (HUBZones):
Total planned subcontracts to Small Disadvantaged Business (SDB) concerns (includes 8(a), Alaska Native Corporations (ANC), and Indian Tribes):
Total planned subcontract awards to Women-Owned Small Business concerns (WOSB)3 concerns:
A-6b
1.3 Rationale if establishing a goal lower than 3% for HUBZone:
1.4 Rationale if establishing a goal lower than 5% for SDB:
1.5 Rationale if establishing a goal lower than 5% for WOSB:
1.6 Rationale if establishing a goal lower than the subcontracting goal in FAR 19.702(a):
2. The following principal types of supplies and/or services are planned to be subcontracted under this contract. [Add additional rows if more space is needed.]
3. The following methods were used to develop the subcontract percentage goals:
4 List all applicable size standards for each proposed subcontractor.
Type of Supply/Service to be Subcontracted
Company/Firm Name
Subcontracted Amount
Subcontractor Size Standard (Other Than
SB, SB, VOSB, SDVOSB,
HUBZone, SDB, WOSB)4
A-6c
4. The following methods were used to identify potential subcontract sources for solicitation purposes. (i.e. source lists used and organizations contacted to identify potential SB concerns, such as the System for Award Management (www.SAM.gov), Dynamic Small Business Search (www.DSBS.sba.gov), trade associations, industry conferences/fairs, etc.)
5. [Select appropriate option.] Indirect costs [were/were not] included in establishing the subcontracting goals specified in the table above.
6. If indirect costs were included, the following method was used to determine the proportionate share of indirect costs to be incurred with SB, VOSB, SDVOSB, HUBZone, SDB and WOSB subcontractors:
7. The following individual will administer the subcontracting program:
Name:
Title:
Address:
Telephone:
E-mail:
This individual's specific duties, as they relate to the subcontracting program, are as follows:
8. The following efforts will be taken to ensure that SB, SDB, VOSB, SDVOSB, HUBZone, and WOSB subcontractors will have an equitable opportunity to compete for subcontracts:
[initial] It is agreed that FAR Clause 52.219-8, Utilization of Small Business Concerns, http://www.sam.gov/ http://www.dsbs.sba.gov/
A-6d will be included in all subcontracts, which offer further subcontracting opportunities. It is further agreed that all subcontractors (except small business concerns) at all tiers below the prime contractor who receive subcontracts in excess of $700,000 ($1.5M for construction of any public facility with further subcontracting possibilities) will be required to adopt and comply with a subcontracting plan in accordance with FAR Clause 52.219-9.
9. The following types of records will be maintained concerning procedures that have been adopted to comply with the requirements and goals in the plan (i.e., establishment of source lists, guides and other data that identify SB, VOSB, SDVOSB, HUBZone, SDB and WOSB concerns; a description of the offeror’s efforts to locate SB, VOSB, SDVOSB, HUBZone, SDB and WOSB concerns and to award subcontracts to them, etc.) and shall be maintained through completion of the contract:
10. In accordance with FAR Subpart 19.704(a)(10) through (15), the Contractor further agrees to:
[Initial each line]
Cooperate in any studies or surveys as may be required;
Submit periodic reports as may be required so that the Government can determine the extent of compliance by the Contractor with the subcontracting plan;
After November 30, 2017, include subcontracting data for each order when reporting subcontracting achievements for indefinite-delivery, indefinite-quantity contracts intended for use by multiple agencies;
Submit the Individual Subcontract Report (ISR), and the Summary Subcontract Report (SSR) using the Electronic Subcontracting Reporting System (eSRS) at http://www.esrs.gov/ within the timeframes identified at FAR Subpart 19.704(a)(10)(iv);
Ensure that other than small business subcontractors with subcontracting plans agree to submit eSRS documents online as required;
Provide its prime contract number and its unique entity identifier, and the e-mail address of the offeror’s official responsible for acknowledging receipt of or rejecting the ISRs to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs;
Require that each subcontractor with a subcontracting plan provide the prime contract number, its own unique entity identifier, and the e-mail address of the subcontractor’s official responsible for acknowledging receipt of or rejecting the ISRs, to its subcontractors with subcontracting plans;
Make a good faith effort to acquire articles, equipment, supplies, services, or materials, or obtain the performance of construction work from the small business http://www.esrs.gov/
A-6e concerns that the offeror used in preparing the bid or proposal, in the same or greater scope, amount, and quality used in preparing and submitting the bid or proposal;
Provide the contracting officer with a written explanation if the contractor fails to acquire articles, equipment, supplies, services or materials or obtain the performance of construction work as described in FAR 19.704(a)(12) of this section. This written explanation will be submitted to the contracting officer within 30 days of contract completion;
Will not prohibit a subcontractor from discussing with the contracting officer any material matter pertaining to payment to or utilization of a subcontractor; and
Pay its small business subcontractors on time and in accordance with the terms and conditions of the subcontract, and notify the contracting officer if the offeror pays a reduced or an untimely payment to a small business subcontractor (see FAR 52.242-5).
Submitted by:
POC Name:
Title:
Email Address:
Company Name:
DUNS/CAGE:
Mailing Address:
Signature http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/52_237.htm#P308_50712
A-7
BID SCHEDULE
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern.
When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total all of the amounts bid for each pay item and show the total bid amount.
Bid Schedule
Project No:WA JEFF 91420(1)
Project Name:Upper Hoh River Road Phase 2
A-8
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
ALL LPSM $___LPSM_____ $____________
A0080 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0100 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0120 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
ALL LPSM $___LPSM_____ $____________
A0140 15705-0100 SOIL EROSION CONTROL, SILT FENCE
660 LNFT $____________ $____________
A0160 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FILTER ROCK)
7 EACH $____________ $____________
A0180 20101-0000 CLEARING AND GRUBBING
0.3 ACRE $____________ $____________
A0200 20301-1900 REMOVAL OF PIPE CULVERT (60 - INCH DIAMETER)
1 EACH $____________ $____________
A0220 20315-0000 SAWCUTTING PAVEMENT
42 LNFT $____________ $____________
A0240 20401-0000 ROADWAY EXCAVATION
390 CUYD $____________ $____________
A0260 20701-0300 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
100 SQYD $____________ $____________
A0280 20810-0000 SHORING AND BRACING
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:A Schedule Type:Base
A-9
A0300 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
110 CUYD $____________ $____________
A0320 25101-0600 PLACED RIPRAP, METHOD A, CLASS 6
1,740 CUYD $____________ $____________
A0340 30202-2000 ROADWAY AGGREGATE, METHOD 2
630 TON $____________ $____________
A0360 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
140 TON $____________ $____________
A0380 41201-0000 TACK COAT
0.30 TON $____________ $____________
A0400 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20-FT SPAN x 18-FT RISE)
40 LNFT $____________ $____________
A0420 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
20 HOUR $____________ $____________
A0440 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH
THUMB ATTACHMENT
20 HOUR $____________ $____________
A0460 62301-0000 GENERAL LABOR
20 HOUR $____________ $____________
A0480 62502-0000 TURF ESTABLISHMENT
1,560 SQYD $____________ $____________
A0500 62632-0000 PLANTINGS (POLE PLANTINGS)
ALL LPSM $___LPSM_____ $____________
A0520 62901-0000 ROLLED EROSION CONTROL PRODUCT
1,560 SQYD $____________ $____________
A0540 63309-0900 DELINEATOR, TYPE FLEXIBLE (BROWN)
6 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A-10
A0560 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)
1,080 LNFT $____________ $____________
A0580 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE)
1,080 LNFT $____________ $____________
A0600 63406-0400 RAISED PAVEMENT MARKER, PLOWABLE, BI-DIRECTIONAL REFLECTIVE
(YELLOW)
3 EACH $____________ $____________
A0620 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
4 EACH $____________ $____________
A0640 63502-1000 TEMPORARY TRAFFIC CONTROL, CONE, TYPE 36-INCH
45 EACH $____________ $____________
A0660 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
26 EACH $____________ $____________
A0680 63502-1500 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
4 EACH $____________ $____________
A0700 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
4 EACH $____________ $____________
A0720 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
26 EACH $____________ $____________
A0740 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
2 EACH $____________ $____________
A0760 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION
2 EACH $____________ $____________
A0780 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
2 EACH $____________ $____________
A0800 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
990 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A-11
A0820 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE (PERIMETER)
680 LNFT $____________ $____________
A0840 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
318 SQFT $____________ $____________
A0860 63504-2000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS, SYMBOLS AND
LETTERS (STOP LINE)
48 SQFT $____________ $____________
A0880 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
2,580 HOUR $____________ $____________
A0900 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
1,820 HOUR $____________ $____________
A0920 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
224 DAY $____________ $____________
A0940 64703-8000 MITIGATION, BANK STABILIZATION (WOOD BUFFER w/ DOLOSSE)
29 EACH $____________ $____________
A0960 64704-1000 MITIGATION, STREAMBED MATERIAL
630 CUYD $____________ $____________
A0980 64704-1700 MITIGATION, BANK STABILIZATION (COARSE WOODY DEBRIS)
11,600 CUYD $____________ $____________
A1000 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION (FLOW DIVERSION)
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
A-12
B0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
B0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
B0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
ALL LPSM $___LPSM_____ $____________
B0080 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B0100 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
B0120 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
ALL LPSM $___LPSM_____ $____________
B0140 15705-0100 SOIL EROSION CONTROL, SILT FENCE
660 LNFT $____________ $____________
B0160 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FILTER ROCK)
7 EACH $____________ $____________
B0180 20101-0000 CLEARING AND GRUBBING
0.3 ACRE $____________ $____________
B0200 20301-1900 REMOVAL OF PIPE CULVERT (60 - INCH DIAMETER)
1 EACH $____________ $____________
B0220 20315-0000 SAWCUTTING PAVEMENT
42 LNFT $____________ $____________
B0240 20401-0000 ROADWAY EXCAVATION
390 CUYD $____________ $____________
B0260 20701-0300 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C
100 SQYD $____________ $____________
B0280 20810-0000 SHORING AND BRACING
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:B Schedule Type:Alternate
A-13
B0300 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
110 CUYD $____________ $____________
B0320 25101-0600 PLACED RIPRAP, METHOD A, CLASS 6
1,740 CUYD $____________ $____________
B0340 30202-2000 ROADWAY AGGREGATE, METHOD 2
630 TON $____________ $____________
B0360 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
140 TON $____________ $____________
B0380 41201-0000 TACK COAT
0.30 TON $____________ $____________
B0400 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20-FT SPAN x 18-FT RISE)
40 LNFT $____________ $____________
B0420 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
20 HOUR $____________ $____________
B0440 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH
THUMB ATTACHMENT
20 HOUR $____________ $____________
B0460 62301-0000 GENERAL LABOR
20 HOUR $____________ $____________
B0480 62502-0000 TURF ESTABLISHMENT
1,560 SQYD $____________ $____________
B0500 62632-0000 PLANTINGS (WETLAND BUFFER ENHANCEMENT PLANTING MIX)
ALL LPSM $___LPSM_____ $____________
B0520 62632-0000 PLANTINGS (POLE PLANTINGS)
ALL LPSM $___LPSM_____ $____________
B0540 62632-0000 PLANTINGS (CHANNEL HABITAT PRESERVATION - POLE PLANTING)
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:B Schedule Type:Alternate
A-14
B0560 62632-0000 PLANTINGS (WETLAND CREATION PLANTING MIX)
ALL LPSM $___LPSM_____ $____________
B0580 62901-0000 ROLLED EROSION CONTROL PRODUCT
1,560 SQYD $____________ $____________
B0600 63309-0900 DELINEATOR, TYPE FLEXIBLE (BROWN)
6 EACH $____________ $____________
B0620 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)
1,080 LNFT $____________ $____________
B0640 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE)
1,080 LNFT $____________ $____________
B0660 63406-0400 RAISED PAVEMENT MARKER, PLOWABLE, BI-DIRECTIONAL REFLECTIVE
(YELLOW)
3 EACH $____________ $____________
B0680 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
4 EACH $____________ $____________
B0700 63502-1000 TEMPORARY TRAFFIC CONTROL, CONE, TYPE 36-INCH
45 EACH $____________ $____________
B0720 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
26 EACH $____________ $____________
B0740 63502-1500 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
4 EACH $____________ $____________
B0760 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
4…
This is the start of the file's text. The full file is on GovTribe.