Amendment A004.pdf

PDF 229 KB Posted

Attached to
WA Jeff 91420(1), Upper Hoh River Road Phase 2
Solicitation number
69056719B000003
Issued by

About this file

This amendment modifies a solicitation for a construction project on the Upper Hoh River Road in Washington. The project involves installing engineered log jam structures, channel plugs, and biotic soil amendments. Revisions include changing language regarding placing channel plug elements and logs, and adding testing requirements for the biotic soil amendments. The solicitation number is 69056719B000003 and was issued by the Department of Transportation Federal Highway Administration for the WA Jeff 91420(1), Upper Hoh River Road Phase 2 project. The bid due date is not extended by this amendment.

View the file

Other files

File Type Posted
Bid Opening Summary_Upper Hoh.pdf PDF
QA_01-07-2021.pdf PDF
Amendment A005.pdf PDF
QA_01-06-2021.pdf PDF
QA_01-05-2021.pdf PDF
QA_12-31-2020.pdf PDF
Amendment A003.pdf PDF
Amendment A002.pdf PDF
QA_12-22-2020.pdf PDF
Amendment A001.pdf PDF
Amendment A001.pdf PDF
A001 Tower Cr Bridge sheet pile plans.pdf PDF
A001 Tower Cr Bridge construction plans.pdf PDF
QA_12-10-2020.pdf PDF
QA_12-09-2020.pdf PDF
QA_12-07-2020.pdf PDF
QA_12-02-2020.pdf PDF
IFB Upper Hoh.pdf PDF
wa-a2013020-Final_Plans.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A004 1/5/2021 N/A See Box 14

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056719B000003

9B. DATED (SEE ITEM 11)

11/30/2020

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

WA JEFF 91420(1), Upper Hoh River Road Phase 2

Amendment A001 is issued to revise the following:

SPECIAL CONTRACT REQUIREMENTS

Page F-41, Subsection 647.11, Placing Channel Plug Unit. Revises 2nd paragraph.

Pages G-11 through G-12, Subsection 713.22, Wood Material. Revises Subsection.

ENCLOSURES: Pages F-41 / G-11 through G.12

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

F-41 DIVISION 600

Special Contract Requirements Project: WA JEFF 91420(1) Upper Hoh River Road Phase 2

Place elements to form a compact, dense mass. When placing on other logs, ensure the bottom of the log is in firm contact with underlying logs as much as possible. Use all specified elements to ensure density of ELJ unit is maximized. Do not exceed specified maximum unit dimensions of 80 feet long, 20 feet wide, and 23 feet high. Fill void spaces with coarse woody debris as elements are placed. Do not wait until ELJ unit is complete before placing coarse woody debris. Place minimum 1 foot of coarse woody debris over ELJ unit top and sides.

Each ELJ unit will get 60 cubic-yards of Class 6 riprap placed at the upstream end of the ELJ unit for keying the ELJ into the bank. Place the riprap to prevent water flowing around the bankside of the ELJ. Place 1/3 of the volume in Layer A. Place remaining 2/3 in Layer B against the bank.

Work the riprap into the log elements. Place riprap top surface at least 3 feet above the ELJ top surface.

647.11 Placing Channel Plug Unit. Construct Channel Plugs at locations shown on the plans.

Orient the elements as shown on the plans. Orientation is critical for deflecting flow away from the overbank area and achieving channel plug stability. Care must be taken to pack bundles as densely as possible and to place the bottoms in close contact with the floodplain ground surface for effectively controlling erosion under the bundles. Place the Channel Plug units in existing scour channels on the floodplain surface. Position the plugs to fill the scour channels and be perpendicular to flow in the channel. Use the existing Forest Access Road where possible for access. Construct a new 20-foot wide Temporary Access Road as needed for placing the channel plugs on the floodplain surface not accessible by the Forest Access Road. Locate the Temporary Access Road 200 feet away from Hoh River active channel edge. Active channel edge is defined as the start of the bank vegetation. Clear vegetation from the Temporary Access Road area only as needed for providing construction equipment access. Do not regrade or place aggregate on the Temporary Access Road. Do not disturb areas beyond the Forest Access Road or Temporary Access Road. Do not remove or modify the existing vegetation and large woody debris lining the Hoh River active channel edge. Scarify the Temporary Access Road surface after the Channel Plugs units are installed. Install the Doug fir and pole plantings as shown on the plans. Use low pressure tracked equipment for planting and scarification.

Each Channel Plug unit consists of 4 deflector-log bundles without dolos, 5 deflector rootwads, 8 cottonwood boles, 12 log piles, and 120 cubic-yards coarse woody debris. The log bundles are made of three logs, 20 to 22 feet long, 18 to 37 inches in DBH diameter, total log volume 110 to 150 ft3, and without attached rootwads. Wrap each log bundle with two wraps of steel chain according to Section 648. Center chain in middle of log bundles. Tighten chain to remove slack and prevent logs from rotating of sliding out of position. Each rootwad is 20 to 22 feet long, 18 to 37 inches in DBH diameter, and has an attached rootwad. Rootwads are placed on top of the log bundles with rootwad in the upstream direction. Space log piles and cottonwood boles evenly along the downstream side of the log bundles for increasing slippage resistance. Log piles are 20 feet long, 12 to 18 inches in dimeter, and 15 feet embedment. Cottonwood boles are 10 feet long, 12 to 18 inches in dimeter, and 5 feet embedment. Embed the log piles and cottonwood boles with a track hoe-mounted vibratory hammer. When placing logs on other logs, ensure the bottom of the log is in firm contact with underlying logs as much as possible. Work coarse woody debris into channel plug. Use all specified elements. Place minimum 1 foot of coarse woody debris over

Revised by Amendment A004

G-11 DIVISION 700

Project: WA JEFF 91420(1) Upper Hoh River Road Phase 2

(d) Loading equipment.

(e) Hauling equipment.

(f) Installation equipment.

(g) Installation methods.

All wood material delivered to the site will be inspected by the CO. Any wood material rejected by the CO will be immediately tagged and removed by contractor at contractor’s expense.

Deflector Log. Use non-decayed, unbroken, Douglas fir, spruce or cedar logs with no attached rootwads. Each log is 18 to 37 inches DBH, in diameter (longest dimension) measured at either of the cut ends and 20 to 22 feet long.

Deflector Rootwad. Use non-decayed, unbroken, Douglas fir, spruce, hemlock, or cedar logs with an attached rootwad. Each log is 18 to 37 inches DBH, in trunk diameter (longest dimension) measured at cut end and 20 to 22 feet long measured from base of root to trunk cut end. Minimum root length measured from base of trunk is 6 feet.

Coarse Woody Debris. Use an even mixture of non-decayed, Douglas fir, cedar, hemlock, cottonwood or alder branches, limbs, twigs, and other residue, 1 to 8 inches in diameter dbh. Use coarse woody debris generated from the harvest of the deflector logs or deflector rootwads and from general site clearing.

713.23 Biotic soil amendment. (Added Subsection).

The biotic soil amendment shall have a minimum of 90 percent organic matter (organic growth medium) and contain other materials designed to improve seed germination, vegetation establishment and overall soil health. In addition to organic growth medium BSA shall include mycorrhizal fungi and a minimum of three of the following ingredients:

(a) Biochar;

(b) Humus/Humic Acid;

(c) Porous Ceramics or Water-holding Organic Polymers;

(d) Seaweed Extract;

(e) Beneficial Bacteria; and

(f) Micronutrients.

G-12 DIVISION 700

Project: WA JEFF 91420(1) Upper Hoh River Road Phase 2

The Contractor shall provide test results dated within 3 years prior to the date of application from an independent, accredited laboratory that has been recognized by an accrediting organization to test and evaluate products to product safety standards. The independent, accredited lab shall be free from commercial, financial, and other pressures that may influence the results of the testing and evaluation process. Test results shall show that the product meets the following table requirements:

Table 1: Biotic Soil Amendment Requirements

BSA Properties Test Methods Requirements

Physical

Organic Matter ASTM D586 90% minimum pH ASTM D1293 5.0 – 8.5

C:N Ratio ASTM E1508 10:1 minimum, 100:1 maximum

Water-Holding Capacityinsert(1) ASTM D7367 400% minimum

Moisture Content ASTM 2974 10% minimum, 50% maximum

Environmental

Acute Toxicity EPA method 2021.0 Non-toxic

EPA Metal Limits SW846-6020 04.06 Pass

Performance

Growth Enhancement ASTM D7322 500% minimum

(1) Water holding capacity of the prepackaged material without the addition of ancillary amendments.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
A004
Sheets G.11 through G.12.pdf
Page G-11
Page G-12