IFB Solicitation - NP DEWA 10(6) 218(2).pdf

PDF 5 MB Posted

Attached to
Delaware Water Gap National Recreation Area
Solicitation number
693C73-24-B-000014
Issued by

About this file

This document is an Invitation for Bids (IFB) for the replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge in the Delaware Water Gap National Recreation Area, Project No. NP DEWA 10(6), 218(2).

The project is located in Pike County, Pennsylvania and Warren County, New Jersey and is expected to cost between $2,000,000 and $5,000,000. The work includes replacing the existing bridge superstructure and substructure, roadway reconstruction, guardrail installation, and other miscellaneous work on the Dingmans Falls Road (NPS Route 218) and Old Mine Road (NPS Route 10). The project will be split into two schedules, with Schedule A as the base contract and Schedule B as a government option. Bids are due by August 13, 2024 and the performance period is 328 calendar days if both schedules are awarded. The contract will be awarded to the responsive, responsible bidder with the lowest evaluated total price across both schedules. Bidders must be registered in the System for Award Management (SAM) and submit required subcontracting plans if they are a large business. Bidders are encouraged to submit bids electronically.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION

IFB No. 693C73-24-B-000014

This Contract Cites

STANDARD SPECIFICATIONS (FP-14)

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

U.S. DEPARTMENT OF TRANSPORTATION

NP DEWA 10(6), 218(2)

DELAWARE WATER GAP NATIONAL RECREATION AREA

Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

Contract No.

PMIS# 222479, 222541

ADDRESS:

CONTRACTOR:

STATE

COUNTY

New Jersey, Pennsylvania

Warren, Pike

AGENCY

TYPE OF IMPROVEMENT

The Dingmans Falls Road (NPS Route 218) and Dingmans Falls Access Bridge #1 work includes the replacement of the existing bridge superstructure and substructure, roadway reconstruction, new guardrail and terminal installation, and other miscellaneous bridge work.

The Old Mine Road (NPS Route 10) and Vancampens Glen Bridge work includes removal of stream debris, riprap placement, asphalt pavement mill and overlay, and other miscellaneous bridge work.

Project Length Totals For Parking Areas, Lane Miles is calculated as SQFT/11ft (nominal) lane

0.07 0.13

Schedule Parking Area Roadway / Parking Area / Other Mileposts / SQFT Linear

Feet Route Miles

Lane Miles

A Route 218 To 199 0.04 0.08

B Route 10 To 150 0.03 0.06

TABLE OF CONTENTS

Page

Notice to Bidders 1 through 3

Checklist for Bid Submission 1 through 2

*SF-1442 Solicitation, Offer, and Award 1 through 5

Statement of Work 1 page

Bid Schedule Instructions 1 through 3

*Bid Schedule

*SF-24 Bid Bond

B-1 through B-8

C-1 through C-4

FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION

REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES

Index to Federal and Transportation Acquisition Regulations 1 through 7

Representations and Certifications (SAMs online) D-1 through D-3

Instructions to Bidders E-1

*Socioeconomic Program Requirements F-1 through F-5

Minimum Wage Schedule F-6 through F-50

*General Contract Requirements G-1 through G-10

Construction Contract Requirements H-1 through H-6

Special Contract Requirements J-1 through J-96

Section K K-1 through K-3

Permits Obtained for this Project Pending

SPECIFICATIONS ON SAM.GOV

Plans 1 through 129

Categorical Exclusion Form (NEPA) 1 through 8

DEWA_10(6)218(2) Vancampers H&H Memo 1 through 32

DEWA_10(6)218(2) Dingman Bridge H&H Report_Final 1 through 101

NP DEWA 10(6) 218(2)_4320-019P1194_Bridge_Insp_Rpts 1 through 25

NP DEWA 10(6) 218(2)_4320-041P10750_Bridge_Insp_Rpts 1 through 24

TABLE OF CONTENTS

NP DEWA 10(6), 218(2) Pavement Memo 1 through 5

* Subcontracting Plan 1 through 5

* Bidder’s Qualifications Form 1 through 7

* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5

*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE

NOTICE TO BIDDERS

CONTRACT FORMAT:

Bidders should note that the format of this contract is in accordance with Federal Acquisition

Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet.

FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Bidders are encouraged to review the documents thoroughly before submitting a bid.

PROPOSAL BOOKLET AND OFFER SUBMITTAL:

It is the responsibility of the Bidder to verify that this bid is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the bid.

Bidders should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.

CONSTRUCTION CONTRACTS:

As stated in FAR Clause 52.236-1, the Contractor shall perform on the site, and with its own organization, work equivalent to at least 50%. Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.

HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:

As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Bidder must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Bidder identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Bidder ineligible for award of contract. The apparent low Bidder should submit their MSDSs within two weeks after bid opening.

ATTENTION LARGE BUSINESSES - UTILIZATION OF SMALL BUSINESS CONCERNS:

All bidders that are large businesses should note their responsibilities in the awarding of subcontracts in accordance with FAR Clause 52.219-8, Utilization of Small Business Concerns. An awardee, if a large business concern, should note its responsibility to establish and conduct a subcontracting plan in accordance with FAR Clause 52.219-9, Alternate I, Small Business Subcontracting Plan. If the apparently successful bidder selected for award is a LARGE BUSINESS, then that bidder is required to submit a subcontracting plan prior to contract award. If the apparently successful bidder fails to submit a subcontracting plan within the time limit prescribed by the Contracting Officer, the bidder will be ineligible for award. PLEASE NOTE: A blank subcontracting plan is included in this solicitation package as a separate document for your use.

INTERNET BASED DATA BASES - REQUIRED INPUT:

According to FAR Subpart 4.1102 contractors are required to be registered in the System for

Award Management (SAM) at the time a bid is submitted. Access the following web site to register: https://www.sam.gov/.

According to FAR Subpart 4.1201 contractors are required to complete electronic annual representations and certifications in SAM accessed via https://www.sam.gov/ as a part of required registration.

https://www.sam.gov/

According to FAR Subpart 22.1302 (b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is

August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

PAYMENT:

Bidders are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.

PROGRESS PAYMENTS:

ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in SAM must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Bidders are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.

WELFARE-TO-WORK INITIATIVE:

The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.

INCREASING SEAT BELT USE IN THE UNITED STATES:

The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.

OBTAINING BID DOCUMENTS:

Invitation For Bid (IFB) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://sam.gov/. Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:

eflhd.contracts@dot.gov.

THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES

NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON

THOSE CHANGES.

http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm https://sam.gov/ mailto:eflhd.contracts@dot.gov

PLEASE NOTE: For security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to a scheduled bid opening. All visitors must sign in at the main entrance of the Quantum Park facility and wait to be escorted by a

Government employee to Eastern Federal Lands Highway Division (EFLHD) in Suite 200. Visitors must then register with the EFLHD Receptionist. A Government employee will collect all bids. Prior to the bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.

PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL

ONLY AT EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides EFLHD.Contracts@DOT.GOV will not be accepted. Bids will not be accepted via facsmile. Hand-delivered bids are not recommended unless the contractor is also attending the bid opening.

mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@DOT.GOV

CHECKLIST FOR BID SUBMISSION

The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.

PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL ONLY

AT EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides

EFLHD.Contracts@DOT.GOV will not be accepted. Bids will not be accepted via facsimile. Hand-delivered bids are not recommended.

1. Bid Envelope (If the Bidder elects not to send the bid electronically via email to

EFLHD.Contracts@dot.gov):

a. Addressed as shown in Block 7 of SF-1442

b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If bids are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration (EFLHD)

Receptionist to be contacted and an EFLHD representative will come to collect the bid. HAND-

DELIVERED BIDS ARE NOT RECOMMENDED.

2. Standard Form 1442: Solicitation, Offer and Award

a. Block 14: Name and Address of Bidder.

b. Block 15: Telephone Number of Bidder.

c. Block 16: Remittance Address if different from Block 14.

d. Block 19: All Amendments Acknowledged, with dates of Amendments.

e. Block 20: Bid is signed and dated.

3. Bid Schedule - (Pages B-1 through B-8)

a. Unit bid price and bid amount provided for each pay item in numbers.

b. Corrections initialed.

c. Price Evaluation eligibility is indicated on the Bid Summary page.

4. Standard Form 24, Bid Bond (Pages C-1 through C-4) (Required if bid guarantee is bid bond)

a. Date executed

b. Legal name and address of bidder.

c. Type of organization.

d. State of incorporation (if applicable).

e. Name and business address of Treasury approved surety.

f. Penal sum of bond (not less than 20% of bid total).

g. Bid identification.

h. Signature of Bidder

i. Seal, if corporation

j. Signature of Surety

k. Seal, if corporation

BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.

mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@DOT.GOV mailto:EFLHD.Contracts@dot.gov

CHECKLIST FOR BID SUBMISSION

5. Power of Attorney.

a. Dated on or before execution date of bond

b. Power has original signature of surety, or is embossed with surety's seal in the certification section

BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.

6. Fill-ins. The following full text Clauses and/or Provision numbers shall be checked or filled in and returned with the bid package:

a. 52.219-4 – HubZone ONLY - See Section F, Clause 52-219-4, paragraph "C", check block if wavier is applicable.

7. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).

Form completed, signed and submitted with bid

8. Subcontracting Plan - Large Businesses Only: Submittal with the bid is not mandatory, but it is encouraged, as it will speed up the award process should your firm be the apparent low bidder.

Legislated subcontracting goals: (15 USC 644 (g)(1)

• 44% - Small Businesses (SB)

• 5% - Small Disadvantaged Businesses (SDB)

• 3% - HUBZone

• 5% - Woman-Owned Small Business (WOSB)

• 5% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)

9. System for Award Management (SAM): The contractor is currently registered in the System For Award Management (SAM) database at https://www.sam.gov/ at the time the bid is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the bid.

10. Online Representations and Certifications Application: The contractor's Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.

11. VETS – 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm.

The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before

August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-

4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.

NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL

DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE

IS SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA

PRIOR TO BID SUBMISSION MAY CAUSE THE BID TO BE REJECTED.

https://www.sam.gov/ https://www.sam.gov/SAM/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212 http://www.dol.gov/vets/vets4212.htm

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

SUITE E2-3-300

693C73

ATTN: Acquisitions

ASHBURN VA 20147

See Block 7

EMILY MCCLEARY

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

EFLHD.Contracts@dot.gov

See Block 10 x

07/11/2024

693C7324B000014

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This Invitation for Bids is for the Delaware Water Gap National Recreation Area, Project No. NP DEWA 10(6), 218(2) , located in Pike County, Pennsylvania and Warren County, New Jersey in strict accordance with the Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.

FP - Standard Specification for Construction of Roads & Bridges on Federal Highway Projects.

Bid Schedule, Section B - pages B-1 through B-8.

Special Contract Requirements, Section J - pages J-1 through J-96.

Plans, Sheets 1 through 129.

Categorical Exclusion Form (NEPA), pages 1 through 8.

DEWA_10(6)218(2) Vancampers H&H Memo, pages 1 through 32.

DEWA_10(6)218(2) Dingman Bridge H&H Report_Final, pages 1 through 101.

NP DEWA 10(6) 218(2)_4320-019P1194_Bridge_Insp_Rpts, pages 1 through 25.

NP DEWA 10(6) 218(2)_4320-041P10750_Bridge_Insp_Rpts, pages 1 through 24.

NP DEWA 10(6), 218(2) Pavement Memo, pages 1 through 5.

Permits, Pending.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 328 calendar days and complete it within ________________ ________________ calendar days after receiving

Continuation Sheet, Block 11

08/13/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>

$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������

�%(��
�)��
�������
���
����� �������������������
���

�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�

0��#������ ��2�

������������
H������

������� �)4��

3�2���%����

�����"��� � ��������
�������������
��" ��������������
�������������"���

����������3 4��� '5 '6 �--����7��

3�2���%���

�����������������������
H������

������� )4������ �$���� �� �4������

���� 2 OF 5�����������������

����2�� #��0 ��2�����

�)��������� )�&4'��������������� ������������ &4'���������������

�"������&��*���G��'����, Block 26

Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Branch Quantum Park 22001 Loudoun County Parkway Suite E2-2-200 Ashburn, VA 20147

Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL

9-AMC-AMZ-EFLINVOICES@FAA.GOV

Oklahoma City, OK 73125

EFLHD-CO

peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text

CONTINUATION OF SF 1442

Block 2:

This project is UN-RESTRICTED - Bids will be accepted from ALL eligible business concerns.

This procurement falls under North American Industry Classification System (NAICS) code

237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)

The award of this project is subject to a 10% price evaluation preference for eligible HubZone

Small Business Concerns (must be on the SBA listing) (see FAR Clause 52.219-4).

Electronic bids will be accepted via email sent to EFLHD.Contracts@dot.gov. Please be sure to indicate the solicitation number, project number, and ATTN: Emily McCleary on the subject line of your email. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.

PHYSICAL DATA AVAILABLE FOR REVIEW

1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.

2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. http://flh.fhwa.dot.gov/resources/design/library.

3. Categorical Exclusion Form (NEPA)

4. DEWA_10(6)218(2) Vancampers H&H Memo

5. DEWA_10(6)218(2) Dingman Bridge H&H Report_Final

6. NP DEWA 10(6) 218(2)_4320-019P1194_Bridge_Insp_Rpts

7. NP DEWA 10(6) 218(2)_4320-041P10750_Bridge_Insp_Rpts

8. NP DEWA 10(6), 218(2) Pavement Memo

9. Permits, Pending

Block 9:

In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section

E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.

Block 11:

Maximum Time Allowed for the Contract if Schedules A and B are Awarded at the Same Time:

If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 328 calendar days.

mailto:EFLHD.Contracts@dot.gov http://flh.fhwa.dot.gov/resources/design/library

Maximum Time Allowed for Each Schedule of Work if Awarded Separately:

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 323 calendar days and will start on the effective date of

Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 128 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.

Work restrictions can be found in SCR Sections 108 and 156.

Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)

Block 12A:

Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.

Block 13:

A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision

52.228-1, Bid Guarantee. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.

Block 17:

Amounts should be completed as follows:

Schedule A - $

Schedule B (Option 1) - $

Other:

The estimated price is expected to fall within the price range of $2,000,000 to $5,000,000.

Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from the Contract Opportunities website located at http://SAM.gov. FP-14 versions can be downloaded at the FHWA web site located at http://flh.fhwa.dot.gov/resources/specs/.

Electronic bids must contain the required signatures (electronic or by hand).

http://sam.gov/ http://flh.fhwa.dot.gov/resources/specs/

Subcontracting Goals

Required from all other than Small business when the requirement is expected to exceed

$750,000 ($1,500,000 for Construction) [FAR 19.702]. The Contracting Officer, along with review and advisory comments from the Office of Small Disadvantaged Business Utilization

(OSDBU), is responsible for approving a reasonable and realistic plan [FAR 19.705-4] [TAM

1219.201(e)(6)]. The legislated subcontracting goals are as shown below. A copy of each subcontracting plan (or contractor statement that no subcontracts are to be awarded) must be provided to OSDBU prior to close of negotiations [TAM 1219.705-5 and - 6].

Legislated subcontracting goals: (15 USC 644 (g)(1)

• 44% - Small Businesses (SB)

• 5% - Small Disadvantaged Businesses (SDB)

• 3% - HUBZones

• 5% - Women-Owned Small Businesses (WOSB)

• 5% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)

STATEMENT OF WORK:

Sealed bids from all business concerns will be accepted for the Delaware Water Gap National

Recreation Area, Project NP DEWA 10(6), 218(2), Solicitation Number 693C73-24-B-000014, located in Pike County, Pennsylvania and Warren County, New Jersey. The project consists of the replacement of Dingmans Falls Access Bridge #1 and the rehabilitation of Vancampens Glen

Bridge. The Dingmans Falls Road (NPS Route 218) and Dingmans Falls Access Bridge #1 work includes the replacement of the existing bridge superstructure and substructure, roadway reconstruction, new guardrail and terminal installation, and other miscellaneous work. The Old

Mine Road (NPS Route 10) and Vancampens Glen Bridge work includes riprap placement, asphalt pavement mill and overlay, and other miscellaneous work.

The project will be split into multiple work schedules/contract options, with the cost of the entire project expected to fall within the price range of $2,000,000 to $5,000,000.

Contract Award/Notice to Proceed is subject to the receipt of permits.

The performance period to complete all contract work will be 328 calendar days after the issuance of the Notice to Proceed.

BID SCHEDULE INSTRUCTIONS

PROJECT: NP DEWA 10(6), 218(2)

BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to

Bidders. While preparing the bid, comply with the following:

COMPLETING THE BID SCHEDULE

Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit

Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual

Schedule of Work by adding the amounts of the listed items and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.

To be eligible for award, bidders must submit prices for each pay item.

Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.

Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.

The amount in Block 17 of the SF 1442 should be completed as follows:

Schedule A - $ .

Schedule B - $ .

SCHEDULES OF WORK

The Bid Schedule is comprised of the following separate schedules and options of work:

Schedule A – Pages B-1 thru B-4

Schedule B (Government Option 1) – Pages B-5 thru B-7

The Government will award the project as a Base Contract (Schedule A) with the option to award Schedule B (Government Option 1); see FAR Clauses 52.217-4 and 52.217-5.

The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the

Government may award Schedule B (Government Option 1) at that time. If additional funding is required for the award of Schedule B (Government Option 1), and is received after the award of

Schedule A (Base Contract), the Government has the right to exercise Schedule B (Government

Option 1) at the unit prices bid no later than the contract completion date of Schedule A (Base

Contract).

COMPLETION OF WORK

The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice to Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contact performance period) is shown in Block 11 of the SF-1442 and described below.

If the Government awards the contract as Schedules A + B, the performance period to complete all work will be 328 calendar days.

If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 323 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 128 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and

Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable

Government review times for those submittals (Subsection 104.03 of the FP and SCR’s).

Bidders are to assume that the award of the contract and approval of the Contractor’s

Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-

15) may result in the start of construction activities to be no earlier than October 2024. See

Subsection 108.01 of the SCR’s for additional details.

BASIS FOR AWARD

The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation

Total Price of Project, which is defined as:

Schedule A (Base Contract) Bid Total +

Schedule B (Government Option 1) Bid Total.

B - 1

Item No. Pay Item No. Description Quantity Unit Unit Price Amount

A0020 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

ALL LPSM $___LPSM_____ $____________

A0060 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

A0080 15702-4000 SOIL EROSION CONTROL, FILTER BAG

ALL LPSM $___LPSM_____ $____________

A0100 15705-0100 SOIL EROSION CONTROL, SILT FENCE

360 LNFT $____________ $____________

A0120 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

360 LNFT $____________ $____________

A0140 15705-1800 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM

220 LNFT $____________ $____________

A0160 15706-0400 SOIL EROSION CONTROL, SEDIMENT TRAP

1 EACH $____________ $____________

A0180 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

2 EACH $____________ $____________

A0200 15706-2300 SOIL EROSION CONTROL, ON-SITE CONCRETE WASHOUT STRUCTURE

1 EACH $____________ $____________

A0220 20103-0000 CLEARING AND GRUBBING

555 SQYD $____________ $____________

A0240 20220-1000 REMOVAL, INDIVIDUAL TREE

9 EACH $____________ $____________

A0260 20301-2300 REMOVAL OF SIGN/MARKER

4 EACH $____________ $____________

A0280 20302-1200 REMOVAL OF GUARDRAIL

145 LNFT $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

Project No:NP DEWA 10(6), 218(2)

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 2

A0300 20303-1600 REMOVAL OF PAVEMENT, ASPHALT

335 SQYD $____________ $____________

A0320 20304-2000 REMOVAL OF BRIDGE (EXISTING SUPERSTRUCTURE AND SUBSTRUCTURE)

ALL LPSM $___LPSM_____ $____________

A0340 20315-0000 SAWCUTTING PAVEMENT

45 LNFT $____________ $____________

A0360 20401-0000 ROADWAY EXCAVATION

245 CUYD $____________ $____________

A0380 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E

240 SQYD $____________ $____________

A0400 20801-0000 STRUCTURE EXCAVATION

1,450 CUYD $____________ $____________

A0420 20803-0000 STRUCTURAL BACKFILL

625 CUYD $____________ $____________

A0440 25102-0300 PLACED RIPRAP, METHOD A, CLASS 3

70 TON $____________ $____________

A0460 30101-4000 AGGREGATE BASE GRADING C OR D

110 TON $____________ $____________

A0480 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH

45 SQYD $____________ $____________

A0500 40101-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (TYPE IV ROUGHNESS, PG

58-28)

80 TON $____________ $____________

A0520 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 58-28)

50 TON $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 3

A0540 41202-0000 TACK COAT

70 GAL $____________ $____________

A0560 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE) (SUBSTRUCTURE AND RETAINING

WALL)

350 CUYD $____________ $____________

A0580 55201-0800 STRUCTURAL CONCRETE, CLASS D (AE) (BACKWALL AND END

DIAPHGRAM)

10 CUYD $____________ $____________

A0600 55202-2000 STRUCTURAL CONCRETE, CLASS D (AE), FOR APPROACH SLABS, TYPE 2

100 SQYD $____________ $____________

A0620 55235-0000 EXPANSION JOINTS (BACKER ROD AND HOT APPLIED JOINT SEALANT)

80 LNFT $____________ $____________

A0640 55302-3200 PRECAST, PRESTRESSED CONCRETE GIRDER (ADJACENT BOX BEAM

48-INCH)

455 LNFT $____________ $____________

A0660 55401-2000 REINFORCING STEEL, EPOXY COATED

61,500 LB $____________ $____________

A0680 55601-1300 BRIDGE RAILING, TIMBER (27-INCH, TUBULAR STEEL-BACKED)

200 LNFT $____________ $____________

A0700 55901-0000 MEMBRANE WATERPROOFING (SPRAY-APPLIED)

205 SQYD $____________ $____________

A0720 56401-1000 BEARING DEVICE, ELASTOMERIC (STEEL REINFORCED)

14 EACH $____________ $____________

A0740 58501-0000 ULTRA HIGH PERFORMANCE CONCRETE (GIRDER KEYWAY)

5 CUYD $____________ $____________

A0760 61701-4010 GUARDRAIL SYSTEM SBTB, MERRITT PARKWAY GUIDERAIL

130 LNFT $____________ $____________

Bid Schedule Schedule:A Schedule Type:Base

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 4

A0780 61702-0900 TERMINAL SECTION, TYPE BAT-MERRITT PARKWAY GUIDERAIL (TYPE II)

1 EACH $____________ $____________

A0800 61702-1000 TERMINAL SECTION, TYPE FAT-MERRITT PARKWAY GUIDERAIL (TYPE I)

2 EACH $____________ $____________

A0820 61707-2000 STRUCTURE TRANSITION RAILING, SBT SYSTEM

80 LNFT $____________ $____________

A0840 61901-0000 FENCE (TREE PROTECTION)

50 LNFT $____________ $____________

A0860 62401-0200 FURNISHING AND PLACING TOPSOIL, 3-INCH DEPTH

1,510 SQYD $____________ $____________

A0880 62501-0000 TURF ESTABLISHMENT

0.35 ACRE $____________ $____________

A0900 62901-0800 ROLLED EROSION CONTROL PRODUCT, TYPE 2.D

1,490 SQYD $____________ $____________

A0920 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID

890 LNFT $____________ $____________

A0940 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

50 LNFT $____________ $____________

A0960 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

170 SQFT $____________ $____________

A0980 63701-0000 FIELD OFFICE

1 EACH $____________ $____________

A1000 64701-3000 MITIGATION, ARCHAEOLOGICAL SITE

ALL LPSM $___LPSM_____ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:A Schedule Type:Base

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 5

Item No. Pay Item No. Description Quantity Unit Unit Price Amount

B0020 15101-0000 MOBILIZATION

ALL LPSM $___LPSM_____ $____________

B0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

ALL LPSM $___LPSM_____ $____________

B0060 15401-0000 CONTRACTOR TESTING

ALL LPSM $___LPSM_____ $____________

B0080 15705-0100 SOIL EROSION CONTROL, SILT FENCE

130 LNFT $____________ $____________

B0100 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

130 LNFT $____________ $____________

B0120 15706-2300 SOIL EROSION CONTROL, ON-SITE CONCRETE WASHOUT STRUCTURE

1 EACH $____________ $____________

B0140 20103-0000 CLEARING AND GRUBBING

210 SQYD $____________ $____________

B0160 20220-1000 REMOVAL, INDIVIDUAL TREE

10 EACH $____________ $____________

B0180 20315-0000 SAWCUTTING PAVEMENT

45 LNFT $____________ $____________

B0200 20410-0000 SELECT BORROW (#57 STONE)

60 CUYD $____________ $____________

B0220 25102-0400 PLACED RIPRAP, METHOD A, CLASS 4

55 TON $____________ $____________

B0240 25102-0700 PLACED RIPRAP, METHOD A, CLASS 7

50 TON $____________ $____________

B0260 40101-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (TYPE IV ROUGHNESS, PG

58-28)

22 TON $____________ $____________

Bid Schedule Schedule:B Schedule Type:Options

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 6

B0280 40102-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL

MAXIMUM SIZE AGGREGATE, WEDGE AND LEVELING COURSE (PG 58-28)

15 TON $____________ $____________

B0300 41202-0000 TACK COAT

65 GAL $____________ $____________

B0320 41301-0400 ASPHALT PAVEMENT MILLING, 1 1/2-INCH DEPTH

270 SQYD $____________ $____________

B0340 55220-0000 REPAIR CONCRETE (CURB AND RAILING)

10 SQYD $____________ $____________

B0360 55220-0000 REPAIR CONCRETE (TOP OF DECK)

10 SQYD $____________ $____________

B0380 55220-0000 REPAIR CONCRETE (BOTTOM OF DECK)

30 SQYD $____________ $____________

B0400 55224-0000 SEAL CONCRETE SURFACE

80 SQYD $____________ $____________

B0420 56302-2000 PAINTING, STEEL STRUCTURE

240 SQFT $____________ $____________

B0440 56320-0000 CONTAINMENT SYSTEM AND WORKER PROTECTION PLAN

ALL LPSM $___LPSM_____ $____________

B0460 57501-0000 MINOR BRIDGE WORK (REMOVE ASPHALT)

ALL LPSM $___LPSM_____ $____________

B0480 61708-1000 REMOVE AND RESET, GUARDRAIL

220 LNFT $____________ $____________

B0500 61901-0000 FENCE (TREE PROTECTION)

50 LNFT $____________ $____________

B0520 62632-0000 PLANTINGS

ALL LPSM $___LPSM_____ $____________

Bid Schedule Schedule:B Schedule Type:Options

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 7

B0540 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING (WOOD POSTS)

12 SQFT $____________ $____________

B0560 63316-1000 REMOVE AND RESET SIGN

1 EACH $____________ $____________

B0580 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID

660 LNFT $____________ $____________

B0600 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION

2 EACH $____________ $____________

B0620 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM

1 EACH $____________ $____________

B0640 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER

275 LNFT $____________ $____________

B0660 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

65 LNFT $____________ $____________

B0680 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

160 SQFT $____________ $____________

Submitted by:____________________________________ Schedule Total:____________

Bid Schedule Schedule:B Schedule Type:Options

Project Name:Replacement of the Dingmans Falls Access Bridge #1 and rehabilitation of the Vancampens Glen Bridge

B - 8

BID SUMMARY

Project NP DEWA 10(6), 218(2)

(1) Schedule A (Base Contract) Bid Total (from Page B-4) = (1) $____________________

(2) Schedule B (Government Option 1) Bid Total (from Page B-7) = (1) $____________________

Total Price of Project (for evaluation purposes only)

EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) $____________________

Maximum Time Allowed for the Contract if Schedules A and B are Awarded at the Same Time:

If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 328 calendar days.

Maximum Time Allowed for Each Schedule of Work if Awarded Separately:

If the Government awards the contract as Schedule A only, the performance period to complete all

Schedule A work will be 323 calendar days and will start on the effective date of Schedule A’s Notice to

Proceed.

If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 128 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.

Does the Bidder claim the Price Evaluation Preference for HUBZone Yes No

Small Business Concerns as defined in FAR Clause 52.219-4? ☐ ☐

Bid Bond (See Instructions on Page 3)

Date Bond Executed (Must Not Be Later Than Bid Opening Date)

OMB Control Number: 9000-0001 Expiration Date: 1/31/2027

Principal (Legal Name And Business Address) Type Of Organization ("X" One)

State Of Incorporation

Surety(ies) (Name And Business Address)

Percent Of Bid Price

Penal Sum Of Bond Amount Not To Exceed Million(s) Thousand(s) Hundred(s) Cents

Bid Identification Bid Date Invitation Number

Authorized For Local Reproduction Previous Edition Is Not Usable

STANDARD FORM 24 (REV. 10/2023)

Prescribed by GSA - FAR (48 CFR) 53.228(a)

For (Construction, Supplies Or Services)

Obligation:

We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.

Conditions:

The Principal has submitted the bid identified above.

Therefore:

The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the Principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.

Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government. Notice to the Surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.

Other (Specify) Individual Partnership Joint Venture Corporation

2.

(Seal)2.(Seal)

1.

1.

1.

1. 3.2.

Name(s) (Typed)

Signature(s)

Individual Surety(ies)

Name(s) And Title(s) (Typed)

Corporate Seal

(Seal)

3.

(Seal)

2.

(Seal) Signature(s)

Principal

2.

State Of Incorporation Liability Limit ($)

2.

2.

1.Name(s) And Title(s) (Typed)

Signature(s) 1. 2. Corporate Seal

Corporate Seal

Su re ty C

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

Name(s) And Title(s) (Typed)

Su re ty D

Signature(s)

Name And Address

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

Liability Limit ($)State Of Incorporation

1.

1.

Su re ty A

Name And Address

Su re ty B

Name(s) And Title(s) (Typed)

Signature(s)

Name And Address

Corporate Surety(ies)

Witness:

The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.

STANDARD FORM 24 (REV. 10/2023) PAGE 2

STANDARD FORM 24 (REV. 10/2023) PAGE 3

Corporate Seal

Su re ty F

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

1.

1.

State Of Incorporation

2.

2.

Liability Limit ($)

Corporate Seal

Name(s) And Title(s) (Typed)

Su re ty G

Signature(s)

Name And Address

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

State Of Incorporation Liability Limit ($)

2.

2.

1.

1.

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

Su re ty E

Instructions

1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.

2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.

3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).

4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the Liability

Limit block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.

(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "Corporate Surety(ies)." In the space designated

"Surety(ies)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.

(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond. The Government may require the surety to furnish additional substantiating information concerning its financial capability.

5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New

Hampshire, or any other jurisdiction requiring adhesive seals.

6. Type the name and title of each person signing this bond in the space provided.

7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and

"offeror."

STANDARD FORM 24 (REV. 10/2023) PAGE 4

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC §

3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0001. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General

Services Administration, Regulatory Secretariat Division (MVCB), 1800 F…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .