DEWA_10(6)218(2) Vancampers H and H Memo.pdf
PDF 7 MB Posted
- Attached to
- Delaware Water Gap National Recreation Area
- Solicitation number
- 693C73-24-B-000014
About this file
This document is a solicitation for a federal contract opportunity from the Department of Transportation Federal Highway Administration for the Delaware Water Gap National Recreation Area. The project involves the replacement of Dingmans Falls Access Bridge #1 and the rehabilitation of Vancampens Glen Bridge. The work includes bridge superstructure and substructure replacement, roadway reconstruction, guardrail installation, riprap placement, and asphalt paving. The estimated cost range for the overall project is $2,000,000 to $5,000,000, and it will be split into multiple work schedules/contract options. Bid documents are expected to be issued around June 13, 2024, with the bid due date and location to be specified. The contract award and notice to proceed are subject to receiving the necessary permits. The solicitation includes subcontracting plan requirements for "other than small businesses", with legislated small business goals. Prospective contractors must be registered in the System for Award Management (SAM) database prior to submitting an offer.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FHWA:I. Rosado:6257: KB: M:\PROJECTS\dewa\10(6)_218(2)\Techserv\Hydra\Reports\ Vancampers\DEWA_10(6)218(2) Vancampens Glen Bridge H&H Memo.pdf CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge
Form FHWA-201 U.S. DEPARTMENT OF TRANSPORTATION (Rev. 11-87) FEDERAL HIGHWAY ADMINISTRATION
MINUTE - MEMO
Use this form in lieu of transmittal slips within Dept. of Trans. when message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA-121 for informal correspondence.
SUBJECT: NP DEWA 10(6)218(2), Vancampens Glen Bridge H&H Memo
TO MESSAGE/COMMENT FROM/DATE
Ramesh Kotadia Project Manager
Carlos Pena Bridge Team Leader
Shoukat Nawaz Highway Design Manager
We have updated this memo to remove any reference of the Dingmans Falls Access Bridge to meet permitting requirements. Hydrology and hydraulic analysis for Dingmans will be provided in a separate memo.
No additional design revisions have been performed for the Vancampens Glen Bridge in the Delaware Water Gap National Recreational Area since our previous memo dated 11/19/20.
As described in our previous memo dated 11/19/20, the Vancampens Glen Bridge analysis was revised due to the NPS and EFL Environmental team's request during the PIH PS&E review to reduce the limits of disturbance to ease the environmental permit process.
Vancampens Glen Bridge (Structure No. 4320-041P) is located on Old Mine Road in the Warren County, New Jersey.
The existing bridge is a 42-ft. long single span concrete encased steel beam structure in fair condition. Moderate sloughing along the south upstream channel bank, severe sloughing (10-in drop) behind the southeast wingwall and moderate erosion at the northeast wingwall were identified on the last Bridge Inspection Report (BIP) dated November 15, 2017. The BIP profile measurements log table shows the north abutment has experienced a long degradation of 5-in upstream of the bridge, and an aggradation of 2.5-inch downstream of the bridge during a 11-year period (October 1998 - November 2017). Based on this information and field observations, EFL consider the structure to be stable and scour is not a threat to the existing bridge. No work on the abutments is proposed, they would remain in place.
The Vancampens Glen Bridge drainage area was evaluated to be 7.62 square miles using USGS Streamstats® online automated hydrologic module that automates drainage area delineation from digital terrain models and computes peak flow discharges with standard regional regression. Hydrology is based on the National Streamflow Statistic Program V6.1, which uses regression equations to calculate the peak flow.
Vancampers Brook is not in Federal Emergency Management Agency (FEMA) mapped floodplains.
Isis Rosado Hydraulics Senior Technical Specialist
11/19/20 07/01/24(updated)
Vancampers\DEWA_10(6)218(2) Vancampens Glen Bridge H&H Memo.pdf CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge
The hydraulic modeling was performed using the two-dimensional software Sedimentation and River Hydraulics – Two Dimensional (SRH-2D) to obtain the water surface elevations (WSELs).
Based on the BIP report the existing low steel elevation (LSEL) seems to be 2.33 ft. below the top of bridge, which place the exiting LSEL approximately at 365.43 ft. Per our analysis, the existing bridge has a freeboard of 2.56 ft., which meet our PDDM Chapter 7 design standard of 2 ft freeboard for a 50-year storm event. Please refer to Table 3 for a summary of the flow rates along with their corresponding WSEL, and freeboards.
Table 3: Water Surface Elevation Summary
Event Flow (cfs)
WSEL
(ft)
Freeboard (ft)
25-year 1160 362.12 3.31 50-year 1450 362.87 2.56 100-year 1790 363.67 1.76
Bank Stabilization Analysis:
Bank Stabilization analysis for a 25-year storm event was performed based on the Standards for Soil Erosion and Sediment Control in New Jersey (NJ SESC), 7th Edition, January 2014, Chapter 22, per NJ DEP guidance. Riprap was designed using the Hydraulic Toolbox v4.4.
software and it was based on the Federal Highway Administration, Hydraulic Engineering Circular No.11 Design of Riprap Revetment (1989) design criteria, which is one of the approved methodologies listed on Table 16-2, Chapter 16, of the NRCS Engineering Field Manual, Streambank and Shoreline Protection.
The natural channel has a profile gradient of 0.0136. Site velocities and flow depths shown in Table 4 were computed using SMS Version 13.0.8’s (SRH-2D) and a manning’s value of 0.025.
USGS Web Soil Survey indicates the type of soil at the site is a combination of high organic soils (PT) and lean clay (CL). Per NJ SESC Chapter 26, the use of bioengineering is not a feasible alternative when the streambank velocity is greater than the allowable soil velocity shown in Table 26-2. Therefore, the use of bioengineering is not feasible at this site and a structure measurement such as riprap is required.
Table 4: Velocities and Water Depth Summary
Location Flow depth
(ft)
Velocity (ft/s)
NE Wingwall 4.9 9 South upstream channel bank
4.9 9
South downstream channel bank
4.0 10
SW Wingwall 4.0 10
CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge
During the pre-application meeting, NJDEP expressed their preference of using river rock over riprap due aesthetic reasons. In addition, NPS also prefers to use native stone to complements the landscape because they consider quarried rock tends to be white or light gray. However, based on the NPS input after the pre-application meeting, angular native stones do not exist in the area.
EFL will be open to the use of river rocks as long as the materials quality and gradation requirements in FHWA HEC 11, Section 4.2 Gradation, and Section 4.5 Material Quality are met.
EFL also considers that angular material has the best performance for streambanks stabilization.
FHWA HEC 11 Section 4.5 states round material can be used as riprap if placed on slopes flatter than 3:1. However, based on the mapping the existing banks slopes are 1:1 at the NE Wingwall, 1.5:1 at the south upstream channel bank, 1.2:1 at the SW Wingwall, and 0.2:1 at the south downstream channel bank. Grading the banks to a slope 3:1 to use round material would result in a greater disturbance than the NJDEP consider to be acceptable based on the Flood Hazard rule of only 10 square feet of riparian zone vegetation disturbance per linear foot. Therefore, the use of round material is not recommended at this site.
During the 70% PIH site visit, NPS expressed concerns on the extend of riprap and their desire to combine riprap with bioengineering methods at the SW Wingwall and south downstream channel bank. However, as previously mentioned, bioengineering is not a feasible alternative. Our EFL Environment team also expressed permitting concerns and desire to reduce the amount of fill at this location. As a result, stream stabilization is no longer recommended at the downstream channel bank since based on existing topography, and steep slopes proposing riprap at a maximum slope of 1.5:1 cannot be achieved without fill or significant disturbance beyond the existing top of bank. Therefore, we will only recommend riprap behind the SW wingwall to reduce potential erosion due roadway runoff.
NPS also expressed their concerns on the extend of riprap at the south upstream channel bank and NE Wingwall. During the site visit, it was agreed based on field observations not to provide stream stabilization along the south upstream bank and to reduce the end of riprap limits at the NE Wingwall. Since there is existing riprap in place in front of the SE wingwall and abutment, we will only recommend riprap behind the SE wingwall to address the severe sloughing due roadway runoff.
For the reasons mentioned previously, we recommend placing angular riprap class 4 behind the southeast and southwest wingwall and riprap class 7 at the northeast wingwall. Please refer to table 5 for the riprap summary. A 6-in thickness course of AASHTO No. 57 stone should be place under all riprap and over the geotextile, per NJ DEP design criteria. The cross-sectional flow area will not be reduced. Please refer to Attachment 9 for the riprap typical section and Attachment 10 for the plan view of the riprap layout.
CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge
Table 5: Riprap Summary
Location Riprap Class
Riprap thickness
(in)
Maximum slope V:H
NE Wingwall 7 48 1.5:1 SE Wingwall 4 30 1.5:1 SW Wingwall 4 30 1.5:1
Please contact us if you should have any questions or concerns.
Attachments:
Vancampens Glen Bridge
1. USGS Streamstats:
M:\PROJECTS\dewa\10(6)_218(2)\Techserv\Hydra\Reports\Scour\Rev2\Attachmen ts\Attachment 6 Vancampers StreamStats.pdf
2. NSS Results:
ts\Attachment 7 Vancampers NSS.pdf
3. USGS Web Soil Survey:
ts\Attachment 8_Vancampers_Unified_Soil_Classification.pdf
4. SMS WSEL’s Cross Section:
ts\Attachment 9 Existing Vancampens Glen WSELs.pdf
5. Drainage Areas:
M:\PROJECTS\dewa\10(6)_218(2)\Techserv\Hydra\Reports\Scour\Rev2\Attachments\Attac hments\Attachment 10 Vancampers Drainage Areas.pdf
6. NE Riprap Analysis Hydraulic Toolbox v4.4 Results:
ts\Attachments\Attachment 11 NE Wingwall Toolbox Results.pdf
7. SE Riprap Analysis Hydraulic Toolbox v4.4 Results:
ts\Attachments\Attachment 12 SE Wingwall Hyd Toolbox Report.pdf
8. SW Riprap Analysis Hydraulic Toolbox v4.4 Results:
ts\Attachments\Attachment 13 SW Wingwall Hyd Toolbox Report.pdf
CC: Hydraulics, Geotech, Env, HD Engineer, TS Engineer, Bridge
9. Riprap Typical Sections:
ts\Attachment 14_Vancampers_Riprap_Typical Sections.pdf
10. Riprap Plan View:
ts\Attachment 15 Vancampers_Riprap Layout.pdf
11. Riprap Dimensions:
ts\Attachment 16 Vancampers Riprap Dimensions.pdf
12. Prop Contours:
ts\Attachment 17 Vancampers Prop Contours.pdf
13. CADD (Prop Contours and Riprap Layout):
ts\Attachment 18 02-dewa10(6)_map_Vancampers Bridge.dgn
Vancampens Glen Bridge StreamStats Report
Vancampens Glen Bridge 4320-041P Rte 10,Old Mine Road 41.058039, -75.000997
Basin Characteristics
Parameter Code Parameter Description Value Unit
DRNAREA Area that drains to a point on a stream 7.62 square miles
STORAGE Percentage of area of storage (lakes ponds reservoirs wetlands) 2.79 percent
CSL10_85 Change in elevation divided by length between points 10 and 85 percent of distance along main channel to basin divide - main channel method not known
140 feet per mi
POPDENS Basin Population Density 28.3 persons per square mile
APRAVPRE Mean April Precipitation 4.09 inches
FOREST Percentage of area covered by forest 77.3 percent
JUNAVPRE Mean June Precipitation 4.54 inches
LC11DEV Percentage of developed (urban) land from NLCD 2011 classes 21-24 1.63 percent
LC11IMP Average percentage of impervious area determined from NLCD 2011 impervious dataset 0.0345 percent
PERMSSUR Area-weighted average soil permeability from NRCS SSURGO database 0.65 inches per hour
Peak-Flow Statistics Parameters [Peak Valley and Ridge Region 2009 5167]
Parameter Code Parameter Name Value Units Min Limit Max Limit
DRNAREA Drainage Area 7.62 square miles 0.87 763
STORAGE Percent Storage 2.79 percent 2.36 30.1
CSL10_85 Stream Slope 10 and 85 Method 140 feet per mi 2.56 268
POPDENS Basin Population Density 28.3 persons per square mile 35 1493
Region ID: NJ Workspace ID: NJ20190201203239639000 Clicked Point (Latitude, Longitude): 41.05808, -75.00087 Time: 2019-02-01 15:32:53 -0500
Page 2 of 3StreamStats
2/1/2019https://streamstats.usgs.gov/ss/
Attachment 1: StreamStats Results DEWA 10(6) 218(2) Vancampers Glen Bridge
Peak-Flow Statistics Disclaimers [Peak Valley and Ridge Region 2009 5167]
One or more of the parameters is outside the suggested range. Estimates were extrapolated with unknown errors
Peak-Flow Statistics Flow Report [Peak Valley and Ridge Region 2009 5167]
Statistic Value Unit
2 Year Peak Flood 315 ft^3/s
5 Year Peak Flood 572 ft^3/s
10 Year Peak Flood 796 ft^3/s
25 Year Peak Flood 1140 ft^3/s
50 Year Peak Flood 1430 ft^3/s
100 Year Peak Flood 1770 ft^3/s
500 Year Peak Flood 2720 ft^3/s
Peak-Flow Statistics Citations
Watson, K.M.,and Schopp, R.D.,2009, Methodology for estimation of flood magnitude and frequency for New Jersey streams, U.S. Geological Survey Scientific Investigations Report 2009-5167, 51 p. (http://pubs.usgs.gov/sir/2009/5167/)
USGS Data Disclaimer: Unless otherwise stated, all data, metadata and related materials are considered to satisfy the quality standards relative to the purpose for which the data were collected. Although these data and associated metadata have been reviewed for accuracy and completeness and approved for release by the U.S.
Geological Survey (USGS), no warranty expressed or implied is made regarding the display or utility of the data for other purposes, nor on all computer systems, nor shall the act of distribution constitute any such warranty.
USGS Software Disclaimer: This software has been approved for release by the U.S. Geological Survey (USGS). Although the software has been subjected to rigorous review, the USGS reserves the right to update the software as needed pursuant to further analysis and review. No warranty, expressed or implied, is made by the
USGS or the U.S. Government as to the functionality of the software and related material nor shall the fact of release constitute any such warranty. Furthermore, the software is released on condition that neither the USGS nor the U.S. Government shall be held liable for any damages resulting from its authorized or unauthorized use.
USGS Product Names Disclaimer: Any use of trade, firm, or product names is for descriptive purposes only and does not imply endorsement by the U.S. Government.
Application Version: 4.3.0
Page 3 of 3StreamStats
2/1/2019https://streamstats.usgs.gov/ss/
NSS Vancampens Glen Bridge.txt National Streamflow Statistics Program Version 6.1 Based on Techniques and Methods Book 4-A6 Equations from database H:\Team_Folders\Tech_Services\Hydro\NSS_v6.mdb Updated by tkoenig 5/9/2014 1:49:13 PM Add new StatLabels for NJ 2014_5012, KS
2004_5032, MT, RI 2014_5010
Site: Vancampens Glen Bridge, New_Jersey User: FC Date: Friday, February 01, 2019 04:10 PM
Equations for New_Jersey developed using English units
Rural Estimate: Rural 1 Basin Drainage Area: 7.62 square miles 1 Region
Region: Peak_Valley_and_Ridge_Region_2009_5167 (none) Drainage_Area = 7.62 square miles Percent_Storage = 2.79 percent Stream_Slope_10_and_85_Method = 140 feet per mi Basin_Population_Density = 35 persons per square mile
Crippen & Bue Region 4
Results for: Rural 1
Equations used:
PK2 = 13.8*DRNAREA^0.753*(STORAGE+1)^(-0.054)*CSL10_85^0.251*(POPDENS+1)^0.127
PK5 = 28.5*DRNAREA^0.741*(STORAGE+1)^(-0.084)*CSL10_85^0.254*(POPDENS+1)^0.104
PK10 = 42*DRNAREA^0.736*(STORAGE+1)^(-0.104)*CSL10_85^0.258*(POPDENS+1)^0.092
PK25 = 63.6*DRNAREA^0.732*(STORAGE+1)^(-0.127)*CSL10_85^0.263*(POPDENS+1)^0.079
PK50 = 83.2*DRNAREA^0.729*(STORAGE+1)^(-0.144)*CSL10_85^0.267*(POPDENS+1)^0.07
PK100 = 106*DRNAREA^0.728*(STORAGE+1)^(-0.158)*CSL10_85^0.271*(POPDENS+1)^0.062
PK500 = 176*DRNAREA^0.725*(STORAGE+1)^(-0.189)*CSL10_85^0.278*(POPDENS+1)^0.043
Value, Standard Equivalent Statistic cfs Error, % Years
PK2 323 50 1
PK5 584 51 2
PK10 811 52 3
PK25 1160 55 4
PK50 1450 57 5
PK100 1790 60 5
PK500 2750 66 6
maximum: 18900 (for C&B region 4)
Attachment 2: NSS Results
DEWA 10(6) 218(2)
Vancampers Glen Bridge isis.rosado-vazquez Highlight isis.rosado-vazquez Highlight isis.rosado-vazquez Highlight isis.rosado-vazquez Rectangle
Unified Soil Classification (Surface)—Warren County, New Jersey (DEWA 10(6) 218(2) Vancampers Soil Map)
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
3/13/2020
499890 499900 499910 499920 499930 499940 499950 499960 499970 499980 499990
499890 499900 499910 499920 499930 499940 499950 499960 499970 499980 499990
41° 3' 30'' N
' 5 '' W
41° 3' 30'' N
' 0 '' W
41° 3' 28'' N
' 5 '' W
41° 3' 28'' N
' 0 '' W
N
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 18N WGS84 0 20 40 80 120
Feet 0 5 10 20 30
Meters Map Scale: 1:505 if printed on A landscape (11" x 8.5") sheet.
Soil Map may not be valid at this scale.
Attachment 3: USGS Web Soil Survey
DEWA 10(6) 218(2)
Vancampers Glen Bridge
MAP LEGEND
Area of Interest (AOI)
Area of Interest (AOI)
Soils Soil Rating Polygons
CH
CL
CL-A (proposed)
CL-K (proposed)
CL-ML
CL-O (proposed)
CL-T (proposed)
GC
GC-GM
GM
GP
GP-GC
GP-GM
GW
GW-GC
GW-GM
MH
MH-A (proposed)
MH-K (proposed)
MH-O (proposed)
MH-T (proposed)
ML
ML-A (proposed)
ML-K (proposed)
ML-O (proposed)
ML-T (proposed)
OH
OH-T (proposed)
OL
PT
SC
SC-SM
SM
SP
SP-SC
SP-SM
SW
SW-SC
SW-SM
Not rated or not available
Soil Rating Lines
CH
CL
CL-A (proposed)
CL-K (proposed)
CL-ML
CL-O (proposed)
CL-T (proposed)
GC
GC-GM
GM
GP
GP-GC
GP-GM
GW
GW-GC
GW-GM
MH
MH-A (proposed)
MH-K (proposed)
MH-O (proposed)
MH-T (proposed)
ML
ML-A (proposed)
ML-K (proposed)
ML-O (proposed)
ML-T (proposed)
OH
OH-T (proposed)
OL
PT
SC
SC-SM
SM
SP
SP-SC
SP-SM
SW
SW-SC
SW-SM
Not rated or not available
Soil Rating Points
CH
CL
CL-A (proposed)
CL-K (proposed)
CL-ML
CL-O (proposed)
CL-T (proposed)
GC
GC-GM
GM
GP
GP-GC
GP-GM
GW
GW-GC
GW-GM
MH
MH-A (proposed)
MH-K (proposed)
MH-O (proposed)
MH-T (proposed)
ML
ML-A (proposed)
ML-K (proposed)
ML-O (proposed)
ML-T (proposed)
OH
OH-T (proposed)
OL
PT
SC
SC-SM
SM
SP
SP-SC
SP-SM
SW
SW-SC
SW-SM
Not rated or not available
Water Features Streams and Canals
Transportation Rails
Unified Soil Classification (Surface)—Warren County, New Jersey (DEWA 10(6) 218(2) Vancampers Soil Map)
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
3/13/2020
MAP INFORMATION
Interstate Highways
US Routes
Major Roads
Local Roads
Background Aerial Photography
The soil surveys that comprise your AOI were mapped at 1:12,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale.
Please rely on the bar scale on each map sheet for map measurements.
Source of Map: Natural Resources Conservation Service Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as of the version date(s) listed below.
Soil Survey Area: Warren County, New Jersey Survey Area Data: Version 14, Sep 16, 2019
Soil map units are labeled (as space allows) for map scales 1:50,000 or larger.
Date(s) aerial images were photographed: Feb 5, 2014—Oct 15, The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident.
Unified Soil Classification (Surface)—Warren County, New Jersey (DEWA 10(6) 218(2) Vancampers Soil Map)
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
Unified Soil Classification (Surface)
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
PduoEb Paulins Kill-Otisville complex, 25 to 60 percent slopes, very stony
PT 0.2 44.8%
ScoA Scio silt loam, 0 to 3 percent slopes
CL 0.3 55.2%
Totals for Area of Interest 0.5 100.0%
Description
The Unified soil classification system classifies mineral and organic mineral soils for engineering purposes on the basis of particle-size characteristics, liquid limit, and plasticity index. It identifies three major soil divisions: (i) coarse-grained soils having less than 50 percent, by weight, particles smaller than 0.074 mm in diameter; (ii) fine-grained soils having 50 percent or more, by weight, particles smaller than 0.074 mm in diameter; and (iii) highly organic soils that demonstrate certain organic characteristics. These divisions are further subdivided into a total of 15 basic soil groups. The major soil divisions and basic soil groups are determined on the basis of estimated or measured values for grain-size distribution and Atterberg limits. ASTM D 2487 shows the criteria chart used for classifying soil in the Unified system and the 15 basic soil groups of the system and the plasticity chart for the Unified system.
The various groupings of this classification correlate in a general way with the engineering behavior of soils. This correlation provides a useful first step in any field or laboratory investigation for engineering purposes. It can serve to make some general interpretations relating to probable performance of the soil for engineering uses.
For each soil horizon in the database one or more Unified soil classifications may be listed. One is marked as the representative or most commonly occurring. The representative classification is shown here for the surface layer of the soil.
Rating Options
Aggregation Method: Dominant Condition
Component Percent Cutoff: None Specified
Tie-break Rule: Lower
Layer Options (Horizon Aggregation Method): Surface Layer (Not applicable)
Unified Soil Classification (Surface)—Warren County, New Jersey DEWA 10(6) 218(2) Vancampers Soil Map
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
Attachment 4:
Line
Attachment 5 : Draina e Areas
Vancampens Glen Bridge n i?
SW Wing
SE Wingwa/1 DA=0.12 ac
No scale
Hydraulic Analysis Report Project Data
Project Title: DEWA 10(6) 218(2) Site: Vancampers Bridge Project Date: Tuesday, February 18, 2020 Project Units: U.S. Customary Units Notes:
Riprap Analysis: NE Wingwall Notes:
Input Parameters Riprap Type: Revetment The channel is a natural channel Local Depth of Flow: 5.31 ft Riprap Shape is Rounded Stability Coefficient: 0.375 This value is updated by the selected Riprap Shape Blanket Thickness Coefficient: 1 Channel Cross-sectional Average Velocity: 9 ft/s Which is the Average Velocity with Spurs Centerline Radius of Curvature of Channel Bend: 150 ft Width of Water Surface at Upstream End of Channel Bend: 32.2814 ft Bank Angle: 1.5 :1 (H:V) .966 < Bank Angle < 4.011 The location of the revetment protection is on the inside of a bend Specific Gravity of Riprap: 2.65 Safety Factor: 1.1
Result Parameters Side slope Correction Factor: 0.717953 Velocity Distribution Coefficient: 1 Design Velocity: 12.5378 ft/s Design velocity never less than average channel velocity Computed D30: 19.1658 in Computed D50: 22.999 in isis.rosado-vazquez Text Box Attachment 6: NE Wingwall
Riprap Class Riprap Name: CLASS VII Riprap Class: VII The following values are an 'average' of the size fraction range for the selected riprap class.
d100: 49.5 in d85: 35 in d50: 25.5 in d15: 17.5 in
Project Title: DEWA 10(6) 218 (1) Site: Vancampers Glen Bridge
Project Date: Tuesday, October 27, 2020
Project Units: U.S. Customary Units
Notes:
Rational Analysis: Rational Method Analysis US Wingwall
Notes:
Rational Method Input Parameters
Runoff Coefficient: 0.95
Basin Area: 0.1200 acres
Rainfall Intensity: 7.36 in/hr
Time of Concentration: 5.00 minutes
Recurrence Year: 25 year
Rational Method Results
Flowrate: 0.8 cfs
IDF Input Parameters
User Supplied Data
IDF Results
25 year IDF equation: i = 32.6386 / (Tc + 5.29083)^0.638898
Intensity: 7.3600 in/hr
Time of Concentration Input Parameters
Minimum Time of Concentration: 5.00 min
Computed Time of Concentration
Time of Concentration: 5.00 min
Sheet Flow Input Parameters
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft
Recommended length not to exceed 30 m. Maximum length is 90 m
Manning's n: 0.0000
See HDS-2 Table 2.1 isis.rosado-vazquez
Attachment 7: SE Wingwall
2 yr, 24 hr precip: 0.0000 in
Sheet Flow Results
Slope: 0.0000 ft/ft
Time of Concentration: 0.00 min
Shallow Concentrated Flow Input Parameters
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft k: 0.0000
See HDS-2 Table 2.2
Shallow Concentrated Flow Results
Slope: 0.0000 ft/ft
Velocity: 0.0000 ft/s
HDS-2 equation 2.7
Time of Concentration: 0.00 min
Channel Flow Input Parameters
Define as: Channel Calculation
Channel Name: Local Channel Data
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft
Manning's n: 0.0000
Channel Flow Results
Slope: 0.0000 ft/ft
Velocity: 0.0000 ft/s
Determined by Channel or Curb & Gutter Calculator
Time of Concentration: 0.00 min
Total Time of Concentration
Time of Concentration: 0.00 min
Final Iterated Solution
Report for channel used in Time of Concentration calculations
Channel Analysis: Channel Analysis
Notes:
Channel Analysis: Channel Analysis US Wingwall
Input Parameters
Channel Type: Triangular
Side Slope 1 (Z1): 6.4000 ft/ft
Side Slope 2 (Z2): 0.3300 ft/ft
Longitudinal Slope: 0.3700 ft/ft
Manning's n: 0.0499
Lining Type: Rock Riprap - 300 mm (12-inch)
Flow: 1.0000 cfs
Result Parameters
Depth: 0.2619 ft
Area of Flow: 0.2309 ft^2
Wetted Perimeter: 1.9725 ft
Hydraulic Radius: 0.1170 ft
Average Velocity: 4.3317 ft/s
Top Width: 1.7628 ft
Froude Number: 2.1094
Critical Depth: 0.4940 ft
Critical Velocity: 1.2179 ft/s
Critical Slope: 0.0126 ft/ft
Critical Top Width: 17.82 ft
Calculated Max Shear Stress: 6.0474 lb/ft^2
Calculated Avg Shear Stress: 2.7022 lb/ft^2
Channel Lining Analysis: Channel Lining Design US Analysis
Lining Input Parameters
Channel Lining Type: Riprap, Cobble, or Gravel
D50: 1 ft
Riprap Specific Weight: 165 lb/ft^3
Water Specific Weight: 62.4 lb/ft^3
Riprap Shape is Rounded
Safety Factor: 1
Calculated Safety Factor: 1.32876
Lining Results
Angle of Repose: 39.25 degrees
Relative Flow Depth: 0.130963
Manning's n method: Bathurst
Manning's n: 0.0508023
Channel Bottom Shear Results
V*: 1.76652
Reynold's Number: 145154
Shield's Parameter: 0.114693 shear stress on channel bottom: 6.04736 lb/ft^2
Permissible shear stress for channel bottom: 10.0123 lb/ft^2 channel bottom is stable
Stable D50: 0.802566 ft
Channel Side Shear Results
K1: 1
K2: 1
Kb: 0 shear stress on side of channel: 6.04736 lb/ft^2
Permissible shear stress for side of channel: 10.0123 lb/ft^2
Stable Side D50: 0.802566 lb/ft^2 side of channel is stable
Channel Lining Stability Results the channel is stable
Channel Summary
Name of Selected Channel: Channel Analysis US Wingwall
Project Title: DEWA 10(6) 218(1) Site: Vancampers Glen Bridge
Project Date: Tuesday, October 27, 2020
Project Units: U.S. Customary Units
Notes:
Rational Analysis: Rational Method Analysis DS Wingwall
Notes:
Rational Method Input Parameters
Runoff Coefficient: 0.95
Basin Area: 0.0900 acres
Rainfall Intensity: 7.36 in/hr
Time of Concentration: 5.00 minutes
Recurrence Year: 25 year
Rational Method Results
Flowrate: 0.6 cfs
IDF Input Parameters
User Supplied Data
IDF Results
25 year IDF equation: i = 32.6386 / (Tc + 5.29083)^0.638898
Intensity: 7.3600 in/hr
Time of Concentration Input Parameters
Minimum Time of Concentration: 5.00 min
Computed Time of Concentration
Time of Concentration: 5.00 min
Sheet Flow Input Parameters
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft
Recommended length not to exceed 30 m. Maximum length is 90 m
Manning's n: 0.0000
See HDS-2 Table 2.1
Attachment 8: SW Wingwall
2 yr, 24 hr precip: 0.0000 in
Sheet Flow Results
Slope: 0.0000 ft/ft
Time of Concentration: 0.00 min
Shallow Concentrated Flow Input Parameters
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft k: 0.0000
See HDS-2 Table 2.2
Shallow Concentrated Flow Results
Slope: 0.0000 ft/ft
Velocity: 0.0000 ft/s
HDS-2 equation 2.7
Time of Concentration: 0.00 min
Channel Flow Input Parameters
Define as: Channel Calculation
Channel Name: Local Channel Data
Top Elevation: 0.00 ft
Bottom Elevation: 0.00 ft
Length: 0.00 ft
Manning's n: 0.0000
Channel Flow Results
Slope: 0.0000 ft/ft
Velocity: 0.0000 ft/s
Determined by Channel or Curb & Gutter Calculator
Time of Concentration: 0.00 min
Total Time of Concentration
Time of Concentration: 0.00 min
Final Iterated Solution
Report for channel used in Time of Concentration calculations
Channel Analysis: Channel Analysis
Channel Analysis: Channel Analysis DS Wingwall
Input Parameters
Channel Type: Trapezoidal
Side Slope 1 (Z1): 1.0800 ft/ft
Side Slope 2 (Z2): 4.5700 ft/ft
Channel Width: 0.0270 ft
Longitudinal Slope: 0.6600 ft/ft
Manning's n: 0.0344
Lining Type: Rock Riprap - 300 mm (12-inch)
Flow: 1.0000 cfs
Result Parameters
Depth: 0.2116 ft
Area of Flow: 0.1322 ft^2
Wetted Perimeter: 1.3283 ft
Hydraulic Radius: 0.0995 ft
Average Velocity: 7.5652 ft/s
Top Width: 1.2225 ft
Froude Number: 4.0544
Critical Depth: 0.3740 ft
Critical Velocity: 2.4678 ft/s
Critical Slope: 0.0335 ft/ft
Critical Top Width: 2.14 ft
Calculated Max Shear Stress: 8.7139 lb/ft^2
Calculated Avg Shear Stress: 4.0985 lb/ft^2
Channel Lining Analysis: Channel Lining Design Analysis DS Wingwall Class 4
Notes:
Lining Input Parameters
Channel Lining Type: Riprap, Cobble, or Gravel
D50: 1.25 ft
Riprap Specific Weight: 165 lb/ft^3
Water Specific Weight: 62.4 lb/ft^3
Riprap Shape is Rounded
Safety Factor: 1
Calculated Safety Factor: 1.50016
Lining Results
Angle of Repose: 39.6 degrees
Relative Flow Depth: 0.0865035
Manning's n method: Bathurst
Manning's n: 0.0343818
Channel Bottom Shear Results
V*: 2.12052
Reynold's Number: 217802
Shield's Parameter: 0.15 shear stress on channel bottom: 8.71394 lb/ft^2
Permissible shear stress for channel bottom: 13.3736 lb/ft^2 channel bottom is stable
Stable D50: 1.22184 ft
Channel Side Shear Results
K1: 0.97162
K2: 1
Kb: 0 shear stress on side of channel: 8.71394 lb/ft^2
Permissible shear stress for side of channel: 13.3736 lb/ft^2
Stable Side D50: 1.18716 lb/ft^2 side of channel is stable
Channel Lining Stability Results the channel is stable
Channel Summary
Name of Selected Channel: Channel Analysis DS Wingwall
Attachment 9a: NE Wingwall DEWA 10(6) 218(2) Vancampers Glen Bridge
Toe of the bank
Varies ±0 - ±5.5'
Varies ±6.8 - ±7.5'
I
I
Coarse Aggregate #57, 6" depth
Geotextile filter, class 1, type C
I
I
I
I
I
I
I r
I
Class 7 Riprap, 48" depth
Attachment 9b: SE Wingwall
Vancampers Glen Bridge
-◄ 7.5' ►
Class 4 Riprap, D50=15" 30" depth
13. a r-� I f \
Coarse Aggregate #57, 6" depth
Geotextile filter, class 1, type C
I
I
I
I
I
I
I
I
I
Wingwall
Note:
Place ri{lrap at a longitudinal slope of 1.5: 1 or flatter.
I-
I
I
I
I
I
I
I
I
I
I
I
_j
I
I I
Attach ment 9c: SW Wingwall
Vancampers Glen Bridge
CV')
V) -H
QJ I
Class 4 Riprap,D50=15" 30" depth
Varies ±6
- ±11
Coarse Aggregate #57, 6" depth (typ.)
Geotextile filter, class 1, type C
Toe of the bank
SW Wingwa/1 \Y. isturbance, L=32� Area '306 sqft
'·,. R • rap Class 4, L=20� AreaT 120 sqft Rip rian, L,max=23� W,ma..; = 7� Area=73 sqft '-, xisting __ -----rip,:ifl-p-
�o��----
• .r,.e --,, o�o. ---
Legend:
I
Disturbance Area
Proposed Riprap Area
Riprarian Area
�£?, L= ' 32 sqft ��C,..._'f ..... a = tJz-5 a-FtF, •·· 1 ······ .. -isis.rosado-vazquez
A tfacb men t 16 : Ri rap Dimensions DEWA 'lQl6) 218(2 Vancampens_ Glen ridge
----�-:,._; \' �i , ',-,":::-----..... '---._ '----- /
'--..._ I '.Zo�� � "', / 7, ,, i '--- /
/4
0,\ ,'Y \,_--.........._, / '
::: "-==---r-;,""'4! \ - >-,-:?.,,..____, // /4 '" ,, • ' /4 '"
-c,,a,,,_x-,,,,.. '--.........._ ' " ...., "c----ff':>'-1
2'-4 1 716 - 49" w N89° 28'Jfi'.!-W----
Existing riprap
/1/ ,, // "',,, 1/" \ I "'-
�\ _f_-(.1�;7•�··1.\�.,>--.-_�,, \ !f !i \
/ /� /------� \�:> o �<L_,"_ \
/ u'
SE Wingwa/1
__,...--r tr__,.
__,...--r
__,...--r-
Vancampens Brook
\ No Scale isis.rosado-vazquez
| DEWA_10(6)218(2) Vancampers H&H Memo |
| Attachments |
| Attachment 1 Vancampers StreamStats |
| Attachment 2 Vancampers NSS |
| Attachment 3_Vancampers_Unified_Soil_Classification |
| Attachment 4 Existing Vancampens Glen WSELs |
| Attachment 5 Vancampers Drainage Areas |
| Attachment 6 NE Wingwall Toolbox Results |
| Riprap Analysis-NE Wingwall-Inside |
| Attachment 7 SE Wingwall Hyd Toolbox Report |
| Attachment 8 SW Wingwall Hyd Toolbox Report |
| Attachment 9_Vancampers_Riprap_Typical Sections |
| Attachment 14a NE Wingwall |
| Attachment 14b SE Wingwall |
| Attachment 14c SW Wingwall |
| Attachment 10 Vancampers_Riprap Layout |
| Attachment 11 Vancampers Riprap Dimensions |
| Attachment 12 Vancampers Prop Contours |