This document is the Results of Bid Opening for Solicitation No. 693C73-24-B-000014, Project: NP DEWA 10(6), 218(2), which involves the replacement of Dingmans Falls Access Bridge #1 and the rehabilitation of Vancampens Glen Bridge in Delaware Water Gap National Recreation Area.
The bid totals and performance periods are provided for the three bidders - Central Southern Construction Corp., Kovilic Construction Company, Inc., and Kyle Conti Construction, LLC. The bid prices range from $4.1 million to $5.9 million, with performance periods of 323-328 calendar days. The Engineer's Estimate for the overall project is $3.5 million. The project will be split into multiple work schedules/contract options. Award of the contract is subject to the receipt of permits.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Delaware Water Gap National Recreation Area
PROJECT: NP DEWA 10(6), 218(2)
SOLICITATION NO. 693C73-24-B-000014
August 20, 2024 at 2:00 p.m. EDT
Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-24-B-000014
Project: NP DEWA 10(6), 218(2)
August 20, 2024, 2:00 p.m. EDT
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Central Southern Construction
Corp.
SCHEDULE A
$4,558,035.00
SCHEDULE B (Government Option 1)
$1,354,075.00
SCHEDULE A + SCHEDULE B =
$5,912,110.00
Kovilic Construction Company, Inc.
SCHEDULE A
$4,477,945.00
SCHEDULE B (Government Option 1)
$715,315.00
SCHEDULE A + SCHEDULE B =
$5,193,260.00
Kyle Conti Construction, LLC SCHEDULE A
$3,222,869.00
SCHEDULE B (Government Option 1)
$902,256.00
SCHEDULE A + SCHEDULE B =
$4,125,125.00
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 328 calendar days. If separate: Schedule A will be 323 calendar days, and Schedule B will be 128 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-24-B-000014
Project: NP DEWA 10(6), 218(2)
August 20, 2024, 2:00 p.m. EDT
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Engineer’s Estimate SCHEDULE A
$2,839,000.00
SCHEDULE B (Government Option 1)
$678,000.00
SCHEDULE A + SCHEDULE B =
$3,517,000.00
If the Government awards the contract as Schedules A + B, the performance period to complete all contract work will be 328 calendar days. If separate: Schedule A will be 323 calendar days, and Schedule B will be 128 calendar days.
| Slide 1 |
| Slide 2: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-24-B-000014 Project: NP DEWA 10(6), 218(2) August 20, 2024, 2:00 p.m. EDT |
| Slide 3: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-24-B-000014 Project: NP DEWA 10(6), 218(2) August 20, 2024, 2:00 p.m. EDT |
File details come from the government source that posted it. Updated .