About this file

This document includes two federal contract opportunities for HVAC commissioning services at the James H. Quillen VA Medical Center in Mountain Home, Tennessee. The opportunities involve replacing the OR chiller under project 621-19-125 and replacing the building 204 chiller under project 621-22-126. Both projects will be worked on concurrently for a total of 300 calendar days. The solicitations are set aside for Service-Disabled Veteran Owned Small Businesses and have an estimated value between $1-2 million. Offerors must submit bids by the deadline of January 21, 2022. The scope of work for both projects involves demolishing existing chillers, purchasing and installing new chillers, and commissioning the systems. The contractor must provide drawings, equipment specifications, and commissioning documentation. The contractor will also be responsible for coordination, scheduling, training, and ensuring all work meets applicable codes and standards.

View the file

Other files

File Type Posted
36C24922B0010 0004.docx DOCX document
621-22-126 Existing Chiller Submittal 8.15.2011.pdf PDF
621-22-126 Scope of work 3.28.2022.pdf PDF
621-19-125 Specifications 3.25.2022.pdf PDF
36C24922B0010 0003.docx DOCX document
621-19-125 Drawings 3.3.2022.pdf PDF
RFIs - OR B204 Chiller - Answers 3.28.2022.pdf PDF
621-22-126 Drawings 3.3.2022.pdf PDF
621-22-126 Specifications 3.16.2022.pdf PDF
36C24922B0010 0002.pdf PDF
Site Visit Sign In Sheet.pdf PDF
VHA Supplemental Contract Requirements for Combatting COVID-19 Updated 12-14-2021.docx DOCX document
621-19-125 Project Drawings 2.1.2022.pdf PDF
36C24922B0010 0001.docx DOCX document
Drawing 621-19-125 Project Area .pdf PDF
Safety Specs.pdf PDF
Drawing 621-22-126 Project Area .pdf PDF
Cast in Place Concrete Specs.pdf PDF
WD TN20220111 1-07-2022.pdf PDF
General Commissioning Specs.pdf PDF
General Requirements Specs.pdf PDF
OR and 204 Chiller Specs.pdf PDF
Contractor EMR Certification Form.docx DOCX document
Earthwork Short Form Specs.pdf PDF
Electrical Requirements Specs.pdf PDF
S02 - RFI Form - Chillers.docx DOCX document
Common Work for HVAC Specs.pdf PDF
Demolition Specs.pdf PDF
Waste Management Specs.pdf PDF
36C24922B0010_1.docx DOCX document
Shop Drawings.pdf PDF
Common Work for Plumbing Specs.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

02-01-20

23 08 00 - 1

SECTION 23 08 00

COMMISSIONING OF HVAC SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 23.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 33 00 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

C. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

D. Section 23 05 41 NOISE AND VIBRATION CONTROL for HVAC PIPING AND

EQUIPMENT.

E. Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

F. Section 23 09 23 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.

1.3 SUMMARY

A. This Section includes requirements for commissioning the HVAC systems of the related subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 23 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00

23 08 00 - 2

GENERAL COMMISSIONING REQUIREMENTS and of Division 23, is required in cooperation with the VA and the Commissioning Agent.

B. The Facility HVAC systems commissioning will include the systems listed in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals that pertain to the systems to be commissioned. The Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS.

1.7 APPLICABLE PUBLICATIONS

A. The following publications form a part of this specification to the extent indicated by the reference thereto. In text the publications are referenced to by the acronym of the organization.

B. Department of Veterans Affairs (VA):

PG 18-10 2007 ......... Mission Critical Facilities - DRAFT

PG 18-10 2007 ......... Life-Safety Protected Facilities - DRAFT

C. American Society of Heating, Refrigerating and Air Conditioning

Engineers, Inc. (ASHRAE):

HANDBOOK 2019 ......... HVAC Applications ASHRAE Handbook, Chapter 39, Testing, Adjusting, and Balancing, Chapter 44, HVAC Commissioning and Chapter 49, Sound and

Vibration Control

HANDBOOK 2017 ......... HVAC Fundamentals ASHRAE Handbook, Chapter 8, Sound and Vibration

D. Associated Air Balance Council (AABC):

7th Edition 2016 ....... AABC National Standards for Total System

Balance

E. National Environmental Balancing Bureau (NEBB):

9th Edition 2019 ....... Procedural Standards for Testing, Adjusting, Balancing of Environmental Systems

3rd Edition 2015 ...... Procedural Standards for the Measurement of

Sound and Vibration

23 08 00 - 3

2rd Edition 2019 ... Standard for Whole Building Technical

Commissioning of New Construction

F. Sheet Metal and Air Conditioning Contractors National Association

(SMACNA):

006 2006... ........... HVAC Duct Construction Standard – Metal and

Flexible Duct

3rd Edition 2005 ... HVAC Systems Testing, Adjusting and Balancing

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of HVAC systems will require inspection of individual elements of the HVAC systems construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and the Commissioning plan to schedule HVAC systems inspections as required to support the Commissioning Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The

Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. Refer to Sections 23 05 41 NOISE

AND VIBRATION CONTROL for HVAC PIPING AND EQUIPMENT, Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC and Section 23 09 23 DIRECT-

DIGITAL CONTROL SYSTEM FOR HVAC requirements. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning

Agent may spot check a sample of completed checklists. If the

Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission.

If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the

Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL

23 08 00 - 4

COMMISSIONING REQUIREMENTS for submittal requirements for Pre-

Functional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 23 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected

Contractor tests at the sole discretion of the Commissioning Agent.

Contractor tests shall be completed prior to scheduling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING:

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the

Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS, for additional requirements.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent.

Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS. The instruction shall be scheduled in coordination with the VA Resident Engineer after submission and approval of formal training plans. Refer to Section 01 91 00 GENERAL COMMISSIONING

23 08 00 - 5

REQUIREMENTS and Division 23 Sections for additional Contractor training requirements.

----- END -----