This document includes statements of work for two federal contract opportunities to replace chillers at the James H. Quillen VA Medical Center in Mountain Home, Tennessee. The first opportunity involves replacing the operating room chiller with two approximately 80-ton chillers, and the second replaces the building 204 chiller with a 120-ton unit. Both projects require demolition and disposal of the existing equipment, installation of new chillers and associated components, and commissioning. The solicitations are 100% set-aside for service-disabled veteran-owned small businesses, with an estimated value between $1-2 million. The statement of work describes the scope of work, schedules, deliverables, and other requirements. The contracting period for both projects is 300 calendar days from notice to proceed.

View the file

Other files

File Type Posted
36C24922B0010 0004.docx DOCX document
621-22-126 Existing Chiller Submittal 8.15.2011.pdf PDF
621-19-125 Specifications 3.25.2022.pdf PDF
36C24922B0010 0003.docx DOCX document
621-19-125 Drawings 3.3.2022.pdf PDF
RFIs - OR B204 Chiller - Answers 3.28.2022.pdf PDF
621-22-126 Drawings 3.3.2022.pdf PDF
621-22-126 Specifications 3.16.2022.pdf PDF
36C24922B0010 0002.pdf PDF
Site Visit Sign In Sheet.pdf PDF
VHA Supplemental Contract Requirements for Combatting COVID-19 Updated 12-14-2021.docx DOCX document
621-19-125 Project Drawings 2.1.2022.pdf PDF
36C24922B0010 0001.docx DOCX document
Drawing 621-19-125 Project Area .pdf PDF
Safety Specs.pdf PDF
Drawing 621-22-126 Project Area .pdf PDF
Cast in Place Concrete Specs.pdf PDF
WD TN20220111 1-07-2022.pdf PDF
General Commissioning Specs.pdf PDF
General Requirements Specs.pdf PDF
OR and 204 Chiller Specs.pdf PDF
Contractor EMR Certification Form.docx DOCX document
Earthwork Short Form Specs.pdf PDF
HVAC Commissioning Specs.pdf PDF
Electrical Requirements Specs.pdf PDF
S02 - RFI Form - Chillers.docx DOCX document
Common Work for HVAC Specs.pdf PDF
Demolition Specs.pdf PDF
Waste Management Specs.pdf PDF
36C24922B0010_1.docx DOCX document
Shop Drawings.pdf PDF
Common Work for Plumbing Specs.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Contractor Services to

Replace Bldg. 204 Chiller James H. Quillen VA Medical Center

Mountain Home, TN 3/28/2022

1. General

The building 204 is supplied by a 115-ton chiller unit, located on the roof of building

204. The chiller has reached the end of its useful life. This project is for an exact or equal replacement chiller with quick disconnects for emergency situations. The Contractor shall provide Construction services that, at a minimum, include the demolition, purchase and installation of chiller, controls, construction services, and commissioning to create a fully functional chiller for the Building 204 area that meets all current codes and standards. This will involve complete demolition, removal, and disposal of the current chiller, modifications to the area to accommodate the required safety and service clearances for the new chiller equipment to be installed.

2. Scope of Work

2.1 The contractor shall be required to furnish all labor, materials, transportation, equipment, tools, and supervision to perform the scope of work for this project.

2.2 The contractor will be responsible for performing a site visit to determine the existing equipment details and current installation.

2.3 The new equipment will be installed in the same area as the existing equipment and the contractor will need to develop a plan to minimize the amount of down time during the demolition, installation, and commissioning of the new equipment.

2.4 The contractor will be required to demo and dispose of all the equipment being removed and re-install safety barriers, fence, etc.

2.5 The existing chiller is to be replaced with an approximately 120 ton chiller. The contractor is to correctly size the new chiller to maintain the correct temperature for building 204.

2.6 All pumps and/or motors are to be replaced with new equipment.

2.7 The chiller must maintain minimum recommended water volume in circulation to avoid frequent cycling of the compressors, which could potentially require a chilled water tank. The current chiller has an 800 gallon auxiliary tank.

2.8 The new chiller is to have quick disconnects for emergency situations

2.9 The system must include acoustic options for noise attenuation if there is a need for noise control

2.10 The contractor will provide and install a temporary chiller to keep correct temperature during the demo of the old chiller and installation of the new chillers.

2.11 The Contractor will be responsible for renting a crane for removal of old chiller and installation of new chiller to the building 204 roof. All crane work is to be scheduled after normal working hours and/or weekends.

2.12 All equipment to complete the scope of work shall be new, not used, remanufactured, or refurbished.

2.13 All OEM equipment shall be UL certified and have UL labels on the

2.14 The Chiller shall be rated and certified per AHRI conditions

2.15 The selected chiller and all components, piping, pumps, controls, etc shall be designed in compliance with applicable standards and codes described in VA program guides, design materials and construction (PG-18-1 and PG -18-2), Design manuals for HVAC (PG-18-10) specifications available in the Technical Information Library (TIL) on VA Website address: (http://www.cfm.va.gov/til/).

2.16 The contractor shall be required to develop and submit the following documentation to the COR:

a) Elevation drawings indicating the location of the new equipment.

b) Control schematics for the new equipment.

c) Wiring diagrams and cable/conduit schedules.

d) Network diagrams for metering and/or control devices internal to the new

e) Factory test reports for the equipment.

2.17 The contractor shall be responsible for the following services:

a) On-site commissioning, which includes oversight of the demolition of the existing equipment, new equipment installation and functional testing of the equipment.

b) Coordination of any subcontractors required for the demolition and installation of the new equipment, including any rework of the existing wiring and conduit to terminate the existing wiring to create a fully functional system.

c) The Contractor shall develop and provide a detailed schedule in Microsoft Project® or other approved scheduling software for completion of all Design Stage activities, tasks, and submissions required herein, leading up to and including the final design development submission(s). After the Contractor receives notice to proceed with the Construction Stage work, the Contractor shall provide and maintain a detailed schedule in Microsoft Project® for completion of all Construction Documents Phase activities, tasks, and submissions required herein. The Contractor schedules shall itemize all required submission dates and review durations and must conform to the milestones and durations provided in the COR overall schedule and the Submission, Review.

d) After construction begins, the Contractor shall conduct a weekly progress meeting(s) and weekly subcontractor meeting(s). A COR representative and/or approved delegate will attend. The Contractor shall also attend construction oversight meetings with representatives from the COR and the project team monthly.

2.18 Below is information on the existing equipment. This information is for reference only, the contractor is required to verify all information.

a) Existing Chiller is a Trane.

CGAM120F2E02AXD2A1A1A1AXXA1C1A4XXA8BXA1A3A1DXXLXX

3. Schedule and Performance

3.1 The contractor shall establish a tentative delivery date for all equipment within

60 calendar days of the notice to proceed (NTP).

3.2 The contractor shall update the COR of any changes to the delivery date bimonthly or immediately upon notification from the plant that there is a delay so to schedule the outage and resources more accurately for the demolition and installation of the equipment.

3.3 Any work that requires an electrical or HVAC shall be coordinated with the COR with a minimum of five (5) days’ notice if it affects a patient care area and a minimum of a three (3) days’ notice if it affects an administrative area.

3.4 All work requiring an energized work permit requires a minimum of three (3) days’ notice and must be approved by the Chief Engineer.

3.5 The work hours for this scope shall be planned for normal business hours except for outages and tie-ins which may require after hours and/or weekends unless otherwise directed by the COR.

3.6 The contractor is responsible for all financial costs associated with any sub-contractors required for the execution of the scope of work.

3.7 If the contractor determines a change in schedule is required, which will affect a planned outage or require an additional outage, the COR shall be notified immediately and a change in schedule shall be proposed and approved by the

COR.

3.8 Final Project Closeout shall be completed within 300 calendar days after notice to proceed (NTP). The Contractor schedule shall allow for VA review periods ending with Contractor’s receipt of VA comments for each submission no later than 15 working days after VA receives the submission.

4. Deliverables

4.1 The contractor shall submit preliminary drawings and bill of materials within 60 calendar days of the NTP to the COR. This deliverable will include at a minimum:

a) Chiller specs and shop drawings

b) Equipment layout with dimensions.

4.2 Prior to completion of the contract, the contractor shall submit final copies of all drawings, schematics, diagrams, bill of materials, and coordination study results to the COR.

4.3 The preliminary deliverables shall be submitted in electronic format only (no USB drives).

4.4 The final deliverables, other than the arc flash labels, shall be submitted in electronic format (no USB drives).

5 Accuracy of Planning Information

5.1 The contractor shall visit the project site to investigate the information shown on any Government-Furnished drawings, record (as-built) drawings, and other planning documents provided by VA. This information is the best available, but the Government does not guarantee its accuracy or completeness.

5.2 The contractor shall promptly report to the Contracting Officer in writing any discrepancies between this contract and the planning information provided by the Government. The contractor shall make no adjustments to his work due to the discrepancy before the Contracting Officer has reviewed the matter and forwarded his determination to the contractor. The contractor’s failure to report any such discovered discrepancy or to wait for the Contracting Officer's determination shall be at his risk and expense.

6 Ownership of Original Documents

All designs, drawings, specifications, notes, and other work developed in the performance of this contract shall be the sole property of the Government and may be used on any other work without additional compensation to the Contractor. The Contractor agrees not to assert any rights and not to establish any claim under the design patent or copyright laws. The Contractor, for a period of no less than 3 years after completion of the project, agrees to furnish and provide access to all retained materials (including electronic) upon request of the VA. Unless otherwise provided in this contract, the Contractor shall have the right to retain copies of all such materials beyond such period.

7 Security Requirements

7.1 Contractors, contractor personnel, subcontractors and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.

7.2 All contractor personnel shall be required to complete the “VA Privacy Training for Personnel without Access to VA Computer Systems or VA Sensitive Information” and submit to the COR prior to beginning work on site.

7.3 All contractor personnel shall be required to review the “Contractor Rules of Behavior” agreement and Acknowledge and Accept the agreement and submit to the COR prior to beginning work on site.

7.4 Due to the scope of this work, the C&A requirements do not apply, and a Security Accreditation Package is not required.

1. General
2. Scope of Work
4. Deliverables
5 Accuracy of Planning Information