Q and A_Round 2_PORTS_(Questions 2-6).pdf

PDF 125 KB Posted

Attached to
S&RTS Port Operations and Related Transportation Services (PORTS)
Solicitation number
HTC711-23-R-R010
Issued by

About this file

This document contains a questions and answers log from a pre-solicitation conference for solicitation number HTC711-23-R-R010, which seeks proposals for S&RTS Port Operations and Related Transportation Services to be awarded by the Department of Defense United States Transportation Command.

The log details six questions received from prospective vendors and the government's responses. Questions addressed topics such as how to complete the small business subcontracting plan, whether proposals could cover multiple countries within a region, and whether corporate experience of subcontractors could be included. The government provided clarifying information on these matters and indicated the solicitation would not be amended. No pricing or products/services were specifically discussed, as the pre-solicitation conference focused on the proposal submission process rather than requirements.

View the file

Other files

File Type Posted
Q and A_Round 5_PORTS_(Questions 19-21).pdf PDF
Q and A_Round 4_PORTS_(Questions 9-18).pdf PDF
Attachment 3 - Contractor Plan for Continuation of Essential Contractor Services_Revision 01.docx DOCX document
Attachment 4 - Corporate Experience Questionnaire_Revision 02.docx DOCX document
RFP_SRTS PORTS_HTC711-23-R-R010_Amend 0003.pdf PDF
Attachment 1 - Performance Work Statement_PORTS_r1 (9 Nov 23).pdf PDF
RFP_SRTS PORTS_HTC711-23-R-R010_Amend 0002.pdf PDF
Q and A_Round 3_PORTS_(Questions 7-8).pdf PDF
Q and A_Pre-Proposal Conf_SRTS PORTS_HTC711-23-R-R010.pdf PDF
Sample Task Order RFTOP.xlsx XLSX spreadsheet
SRTS PORTS Pre-Proposal Conference Slides (Final).pdf PDF
Attachment 4 - Corporate Experience Questionnaire_Revision 01.docx DOCX document
RFP_SRTS PORTS_HTC711-23-R-R010_Amend 0001.pdf PDF
Q and A_Round 1_PORTS_HTC711-23-R-R010.pdf PDF
Attachment 2 - RFP Information and General Compliance Worksheet.xlsx XLSX spreadsheet
Attachment 1 - Performance Work Statement_PORTS.pdf PDF
Attachment 4 - Corporate Experience Questionnaire.docx DOCX document
RFP_SRTS PORTS_HTC711-23-R-R010.pdf PDF
Attachment 3 - Contractor Plan for Continuation of Essential Contractor Services.docx DOCX document
Attachment 6 - SRTS Historical Data.pdf PDF
Attachment 5 - Small Business Subcontracting Plan .docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION

DATE

RECEIVED

PROSPECTIVE VENDOR'S QUESTION DATE OF REPLY GOVERNMENT'S RESPONSE AMEND RFP?

2 26‐Oct‐23 Can you explain table 1 small business an large business in Attachment 5, page 3?

31‐Oct‐23

The table on page 3 is an example how dollar and percentage are annotated on the Subcontracting Plan. If the Total Dollars to be subcontracted is: $1,000,000, then the allocated dollars between Large Business and Small business MUST equal the Total dollars allocated. Hence, page 3 example show Large Business is $600,000 and Small Business is $400,000 equaling the $1,000,000.

Regarding the other parts of the table it shows, sample dollar amounts and based on the dollar goal will determine the percentage. Hence: Total for Veteran Owned Small Business Concerns is $20,000 then $20,000 / $1,000,000 = .02%

No

3 26‐Oct‐23 We have subcontractors in the large business category, so when entering prices should we separate between small business (our company) and large business (our subcontractor) prices? (attachment 5 pages 5 – 8)

31‐Oct‐23 The small business contracting plan (Attachment 5) is only required if you as the prime contractor are a large business and intend to compete on task orders in Region 6 (see Attachment 1, PWS, Appendix C).

No

4 26‐Oct‐23 Can we select more than 1 country but in 1 region? 31‐Oct‐23

The government is asking for proposal submissions in the six individual regions (see Attachment 1, PWS, Appendix C) in which you are able to provide services in any country within that region. Example 1: If you can provide services in Japan and Singapore then you would submit a proposal for Region 4 (USINDOPACOM).

Example 2: If you can provide services in Germany and Kuwait, then you would submit a proposal for regions 2 (USCENTCOM) and 3 (USEUCOM).

No

5 26‐Oct‐23 What is our reference or basis for calculating the proposal price? do we have to refer to the data in the "Request For Information (RFI) attachment 5"?

31‐Oct‐23

The government is not requesting or evaluating pricing as part of the IDIQ contract solicitation and award process. All pricing will be solicited and evaluated at the Task Order level per PWS, Appendix A‐Ordering, Invoicing, and Payment instructions

If you are asking about how to complete the Attachment 5, Small Business Subcontracting plan please see responses provided for Question 1 and 2 above.

No

6 26‐Oct‐23 Can we use the work experience of our subcontractors? 31‐Oct‐23

To demonstrate corporate experience, the Offeror shall address their, and/or their subcontractor(s), most relevant government and/or commercial contracts and efforts performed within the past three years by completing Attachment 4, Corporate Experience Questionnaire. The offeror shall clearly identify which efforts were performed by their company and those performed by their subcontractor(s) (see RFP Clause 52.212‐1, Instruction to Offerors).

No

SOLICITATION Q&A LOG

S&RTS Port Operations & Related Transportation Services (PORTS)

HTC711‐23‐R‐R010

UPDATED: 31 October 2023