9 - NDGPS RFP - Atth I - PWS Enclosure 4 - PM Summary a2.pdf
PDF 308 KB Posted
- Attached to
- Nationwide Differential Global Positioning System Engineering and Logistics Support (NDGPS) Federal contract opportunity
- Solicitation number
- HSCG44-12-R-P13005
About this file
RFP - HSCG44-12-R-P13005 Amendment A00001 PWS Enclosure 4 ( Revised )
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
As part of the Coast Guards Logistics Transformation Modernization
Program the preventative maintenance program will be moving to an electronic documentation system. The Coast Guard Asset Logistics
Management Information System (ALMIS) will be used to track all maintenance. Under ALMIS will be the Electronic Asset Log (EAL) that maintenance units will access to generate Maintenance Procedure
Cards (MPC). These cards will be used to guide the technicians in performing the required equipment maintenance.
Until this new system is fully implements, the following pages will be used as the guidelines for all DGPS related maintenance.
ENCLOSURE 4
PREVENTATIVE MAINTENANCE
SUMMARY
Periodicity Codes: Q = Quarterly; T = Tri-annual; S = Semi-annual; A = Annual ; O = Other
1 of 7 ENCLOSURE 4
PREVENTATIVE MAINTENANCE SUMMARY
GCF-W-1216-DGPS (Ref: MPC 42315/AHAA 02)
MAINTENANCE REQUIREMENT T S A O NOTE
1 Clean and Inspect REFSTA Receivers
2 Clean and Inspect ITMON Receivers
3 Inspect Electrical and RF connections
4 Inspect and clean interior of equipment cabinet
5 Inspect and Clean rack blower
6 Clean Filter
7 Check operation and connections on DSU
8 Inspect wiring and connections on relay and distribution panel
9 Inspect and Test UPS
10 Inspect / Repair ground connections
11 Clean and Inspect MSK, ITMON and
REFSTA antennas
12 Check for loose joints and mounting HW
13 Weatherproof connectors
14 Inspect / Replace cable clamps
2 of 7 ENCLOSURE 4
CDWP-SC1000-DGPS-USCG
1 Clean and Inspect SC1000 Transmitter 1
2 Check SC1000 operating parameters 2
3 Perform SC1000 Transmitter alignment 3 cabinet
5 Test remote sensors 4
6 Inspect / Test load center and battery charger
7 Service / Replace defective components in load center
8 Clean and Inspect Batteries 6
9 Clean / Inspect ATU 7
10 Operate / Test ATU 7
11 Perform RSIM drawer alignment 8
12 Inspect and Test transmission line to ATU
13 Inspect / Adjust spark gaps
Notes: 1. MPC 42315/AUAA
2. MPC 42315/AUAB
3. MPC 42315/AUAF
4. MPC 42315/AUAC
5. MPC 42315/AUAD
6. MPC 31311/ADAA
7. MPC 42315/AUAE
8. MPC 42315/AUAG
3 of 7 ENCLOSURE 4
RCA-MSK-5SS TRANSMITTER
1 Clean and Inspect MSK-5SS Transmitter
2 Check / Record operating parameters
3 Perform Transmitter Alignment cabinet and air filters
5 Test remote sensors
6 Test Transmitter under generator load
7 Clean / Inspect ATU
8 Operate / Test ATU
9 Perform RSIM interface alignment
10 Inspect and Test transmission line to ATU
11 Inspect / Adjust spark gaps
12 Inspect for signs of arcing, corrosion or deterioration.
13 Complete test and alignments outlined in the NDGPS Maintenance procedures
Manual
Notes: 1. Final maintenance procedures will be developed by the maintenance contractor based on reliability considerations. Procedures may be added or deleted as performance and conditions dictate.
4 of 7 ENCLOSURE 4
(1SG38), VECTOR D DGPS TRANSMITTER
1 Clean and Inspect Vector Transmitter
2 Check / Record operating parameters
3 Perform Transmitter Alignment cabinet and air filters
5 Test remote sensors
6 Test Transmitter under generator load
7 Clean / Inspect ATU
8 Operate / Test ATU
9 Inspect and Test transmission line to ATU
10 Inspect / Adjust spark gaps
11 Inspect for signs of arcing, corrosion or deterioration
12 Complete test and alignments outlined in the NDGPS Maintenance procedures
Manual
5 of 7 ENCLOSURE 4
290’ TRANSMITTING TOWER
1 Visual Inspection of tower, guys, TLEs, insulators, and anchors
2 Check vertical alignment 2
3 Inspect and clean base insulator 1
4 Check antenna ground resistance
5 Inspect / Test obstruction lighting system 2
6 Inspect ground connections 1
7 Remove weeds / grass from around tower base and coupler area; treat with weed killer
8 Check RF connections and transmission line. Clean and tighten all connections
9 Inspect ground radial system 2
Notes: 1. MPC 44111/010
2. Basic visual ground inspection
6 of 7 ENCLOSURE 4
BUPG
1 Conduct visual inspection of shelter
2 Inspect for fuel leaks or spills
3 Inspect and clean air intake filters
4 Check /Test coolant, battery and oil heaters
5 Check temperature sensor settings
6 Check ATS
7. Inspect as test timer assemblies
8 Inspect and Test the prime mover
9. Test alarm sensors
10. Change oil, oil filters and fuel filters
11. Clean and tighten electrical connections
12. Analyze oil samples
13. Check and fill all fluid levels
14. Check generator operation under load
15. Test generator start with simulated power failure
16 Clean and oil motor in compartment heater
17 Collect and analyze fuel samples (each tank)
18 Check Fuel Levels in both tanks
19 Maintain fuel levels at 80-90% (DF-2)
20 Treat fuel with appropriate conditioners
21 Inspect and Test batteries and charger
22 Inspect / Tighten/ Replace belts and hoses
23 Inspect and clean floor drain (if applicable)
24 Remove and dispose of any oil / fuel in overflow pan
25 Check and record generator run time meter
26 Inspect all meters, gauges, and indicator lamps
27 Inspect and Test ventilation, heaters and alarms
7 of 7 ENCLOSURE 4
FACILITIES / GROUNDS
1 Mow / cut grass at site 1
2 Trim along fences and around fixed structures
3 Treat / weed in gravel areas
4 Inspect for site damage and vandalism
5 Inspect shelters for corrosion and leaks
6 Replace lamps, bulbs, lights
7 Test / Service HVAC units
8 Inspect fences, gates, and barb wire
9 Replace / repair damaged fence sections
10 Inspect site for rodent and pest infiltration
11 Inspect / service locks
12 Inspect and replace safety equipment
13 Inspect GSOS equipment
14 Weatherproof GSOS external connections
15 Snow removal
16 Inspect / maintain access road and gravel areas 2
17 Inspect site for exposed ground radials
18 Inspect power and telephone service entry points for damage and vegetation
19 Inspect REFSTA masts and foundations
20 Inspect / Repair Ice Shields
21 Inspect / trim trees blocking REF STA antennas and along power lines
Notes: 1. Grass cutting requirements will vary from site to site. General requirement is to maintain grass height at less than 12 inches for operational sites.
2. Anticipate biennial grading of access road for proper drainage.