AMENDMENT 1
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
HSCETC-11-R-00002
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Washington DC 20536 Mailstop 5750 - N. Maples-Remley
ICE/TC/IT SERVICES
801 I Street NW, Suite 930 Office of Acquisition Management Immigration and Customs Enforcement ICE/Info Tech Svs/IT Services
Washington DC 20536 Mailstop 5750 - N. Maples-Remley
ICE/TC/IT SERVICES
801 I Street NW, Suite 930 Office of Acquisition Management Immigration and Customs Enforcement ICE/Info Tech Svs/IT Services
01/18/2010000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/29/2010
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment:
1. Modifies the two Federal Business Opportunities (FBO) 'amendments' which uploaded readable documents to FBO only - there were no changes to the solicitation package from these two 'amendments'.
2. Revises the quantity and the period of performance on CLIN 00001 to align with CLIN 0002 and the two month Transition In Period.
3. Adds the ESTIMATED number of hours and revises the SOW paragraph references for CLINs
XX05.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Nancy J. Maples-Remley
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
4. Uploads attachment #16 - Draft QASP which was not uploaded to FBO.
5. Provide new documents - Attachment #17 - ITFO SOP Quick Guide, Attachment #18 - Hardware List and Attachment #19 - Responses to Offeror's Questions.
6. Provides and uploads to FBO - the REPLACEMENT documents listed below. Note the title on relacement documents contains (REV1) at the end of the title. Replacement documents: Addendum 52.212-1(REV1), Addendum 52.212-2(REV1), SOW(REV1), Attachment - Special Contract Requirements(REV1), Attachment 4 Labor Category Descriptions(REV1), Attachment 14 TO#1 Request for Proposal(REV1), Appendix A - Map, Attachment 15 Past performance Questionnaire(REV1) and Index(REV1) .
7. CLIN 0001 period of performance (POP) has changed TO: 1 April 2011 through 31 March 2012 and the quantity has changed TO 10 months.
8. The estimated hours for all labor categories in CLINs XX 05 is 40 hours per category per year.
The estimated period of performance, if all options are exercised, is an estimate. The period of performance will begin on the actual award date and dates will be revised as applicable.
LIST OF CHANGES:
Proposal due date : 28-JAN-11 changed to
31-JAN-11
CHANGES FOR LINE ITEM NUMBER: 1
Description changed IAW Paragraphs C.2, C.7, C.11, C.16, C.17, C.18 C.20, C.22, C.24 and C.26 of the Statement of Work (SOW) and relevant portions of Attach 1 � Special Contract Requirements. The period of performance (POP) is estimated to be 1 April 2011 through 31 March 2012 and is subject to change based on the actual award date.
Amendment 01 revised the quantity FROM 12 months TO 10 months to align with the 2 month transiton in period.
Quantity changed from 12 to 10 Start Date changed from 01-APR-11 to 01-JUN-11
CHANGES FOR LINE ITEM NUMBER: 5
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
Description changed -Amendment 01 added the
ESTIMATED NUMBER OF HOURS FOR THE POSITIONS AND
ADDED THE SOW REFERENCE C.21. NOTE THE HOURS ARE
AN ESTIMATE AND NOT GUARANTEED.
GOVERNMENT SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
CONTRACTOR SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
Estimated Hours: - 40
The POP is estimated to be 1 April 2011 through 31 March 2012.
CHANGES FOR LINE ITEM NUMBER: 1005
Description changed - Amendment 01 added the
ESTIMATED NUMBER OF HOURS FOR THE POSITIONS AND
ADDED THE SOW REFERENCE C.21. NOTE THE HOURS ARE
AN ESTIMATE AND NOT GUARANTEED.
GOVERNMENT SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
CONTRACTOR SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
5 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40 The POP is estimated to be 1 April 2012 through 31 March 2013.
CHANGES FOR LINE ITEM NUMBER: 2005
Description changed The POP is estimated to be 1 April 2013 through 31 March 2014. to Labor � Fixed Hourly Rates for Labor Categories IAW C.20.1 and C.21, relevant portions of Attachment 1 � Special Contract Requirements and Addendums to FAR 52.212-1 and 52.212-2.
Amendment 01 added the ESTIMATED NUMBER OF HOURS
FOR THE POSITIONS AND ADDED THE SOW REFERENCE
C.21. NOTE THE HOURS ARE AN ESTIMATE AND NOT
GUARANTEED.
GOVERNMENT SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
CONTRACTOR SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
6 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
The POP is estimated to be 1 April 2013 through 31 March 2014.
CHANGES FOR LINE ITEM NUMBER: 3005
Description changed The POP is estimated to be 1 April 2014 through 31 March 2015. to Labor � Fixed Hourly Rates for Labor Categories IAW C.20.1 and C.21, relevant portions of Attachment 1 � Special Contract Requirements and Addendums to FAR 52.212-1 and 52.212-2.
Amendment 01 added the ESTIMATED NUMBER OF HOURS
FOR THE POSITIONS AND ADDED THE SOW REFERENCE
C.21. NOTE THE HOURS ARE AN ESTIMATE AND NOT
GUARANTEED.
GOVERNMENT SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
7 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
CONTRACTOR SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40 The POP is estimated to be 1 April 2014 through 31 March 2015.
CHANGES FOR LINE ITEM NUMBER: 5005
Description changed The POP is estimated to be 1 April 2016 through 31 March 2017. to Labor � Fixed Hourly Rates for Labor Categories IAW C.20.1 and C.21, relevant portions of Attachment 1 � Special Contract Requirements and Addendums to FAR 52.212-1 and 52.212-2.
Amendment 01 added the ESTIMATED NUMBER OF HOURS
FOR THE POSITIONS AND ADDED THE SOW REFERENCE
C.21. NOTE THE HOURS ARE AN ESTIMATE AND NOT
GUARANTEED.
GOVERNMENT SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
8 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
HSCETC-11-R-00002/000001
$__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
CONTRACTOR SITE RATE:
Project Manager/Task Order Lead $__________________/hour Estimated Hours: - 40 Information Systems Security Officer $__________________/hour Estimated Hours: - 40 Communications/Network Engineer $__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Sr.)
$__________________/hour Estimated Hours: - 40 Computer Systems Analyst (Jr.)
$__________________/hour Estimated Hours: - 40 Systems Administrator $__________________/hour Estimated Hours: - 40 LAN/Deskside Support Technician $__________________/hour Estimated Hours: - 40
The POP is estimated to be 1 April 2016 through 31 March 2017.
FOB: Destination Period of Performance: 04/01/2011 to 03/31/2017