Washington Headquarters Services Acquisition Directorate Pre-proposal Conference Net-Centric Integrated Enterprise Information Technology Solutions

(NIEITS)

Solicitation

HQ0034-10-R-0046

10 AUG 2010

The public areas of the hotel are completely non smoking.

WiFi is $11.95 per device; an access code can be purchased at the hotel front desk.

Restrooms are located on the Atrium level (same level as the meeting rooms) of the hotel, directly across from the pool.

Hotel shuttle picks up and drops off at the Pentagon City metro and runs every thirty minutes.

ADMINISTRATIVE NOTES

10 AUG 2010

AGENDA

Introductions
Purpose
Ground Rules
Office of the Secretary of Defense (OSD) Program Overview
Director of Administration and Management Information Technology (DA&M IT) Transformation
Contract / Orders / Ordering Period
RFP Overview
Questions

INTRODUCTIONS

Patricia Watson; Contract Specialist (WHS AD)
Ronald Bechtold; Chief Information Officer (OSD)
Emmett Webster; Acting Deputy CIO (OSD)
Duane Parsons; Chief Financial Manager (OSD)
Joletta Rankin; Contracts Manager (OSD)
John Taninecz; Acquisition Liaison Team Lead (WHS ITMD)
Duane Spriggs; Director, Enterprise Services (WHS ITMD)
Sherry Freeman; Director, Small Business Programs (WHS)
Carol Decker; Small Business Administration
Pete Zahirieh; Small Business Administration
Mary Beth Brown; Contract Specialist (WHS AD)
David Price; Contracting Officer (WHS AD)

PURPOSE

The purpose of this conference is to provide industry with an overview of the procurement process and key aspects of the solicitation to facilitate receipt of quality proposals.

The purpose of this procurement is to obtain net-centric information technology (IT) solutions to support the Office of the Secretary of Defense (OSD), the Washington Headquarters Services (WHS), and the Pentagon Force Protection Agency (PFPA) for current and future requirements.

GROUND RULES

Written terms and conditions of RFP govern over any information presented; any changes to the RFP will be incorporated via an amendment to include written responses to industry questions / comments
No audio or video recording is permitted
3X5 Cards available to submit questions
Briefing slides and attendees roster will be posted via Fed Biz Ops

DA&M IT TRANSFORMATION

Objectives of the Director of Administration and Management’s (DA&M’s) 2007-2012 Strategic Plan are to:
make secure and reliable IT systems available to DA&M IT community-supported activities;
provide the highest levels of 24/7 communications support for the Secretary and Deputy Secretary of Defense.
DA&M IT organizations continue to evaluate functional requirements that have enterprise potential, many of which are included in the scope of this acquisition

Transformation – Where We Are Phase I:

Strategic Development

Results Actions Leadership established Strategic Direction for IT in DA&M

Phase IV: Implementation

Socialize Priorities & Direction Standardize Common Services Integrated Infrastructure

Stand up new organization based on Leadership’s strategic direction and Transformation team’s design Decision Brief #1 We are Here: Phase III ended with the finalization of the initial implementation plan Phase III:

Future State Design

“As Is” Gaps “To Be” Transformation team analyzed environment and designed future state

Decision Brief #2 Phase II:

Transformation Planning

Transformation POAMs Subject matter experts & strategic partners created plan to reach Strategic Direction Governance Service Mgmt Processes IT Infrastructure Vision:

“To be a premier IT service partner providing secure, reliable, and state-of-the-art IT enterprise solutions to the Office of the Secretary of Defense, Pentagon community, and all other supported organizations while creating an unsurpassed customer experience anytime and anywhere”

Phase I: Strategic Development In response to recommendations from an IT Review that was conducted in 2007/early 2008, a ODA&M Enterprise IT Working Group was formed with leaders from ITMD, PENREN, PFPA and OSD CIO in May 2008. The working group members collaborated to develop a new ODA&M Enterprise IT Vision and five corresponding goals, as well as a way ahead for the 14 original and 2 supplemental IT Review recommendations. The group also created a high level strategic communications plan. They briefed Mr. Rhodes in August, 2008 and received a decision to move forward.

Phase II: Transformation Planning Following the DA&M’s authorization to move ahead in the integration of DA&M IT, the Working Group began developing Plans of Action and Milestones (POAMs) for executing the recommendations in the following areas: Governance, Service Management Processes and IT Infrastructure. On December 9th, 2008, the Governance Group presented a second decision brief to Mr. Rhodes and received approval to move forward in the implementation of the DA&M IT Governance Council, the DA&M IT Transformation POAMs, and the strategic communications plan.

Phase 3: Future State Design After Decision Brief 2, the sub-working groups began executing their POAMs. In the “As Is” data collection phase, sub-working group members gathered information on the current people, processes, technologies and infrastructure of their organizations. Next, they worked together to identify consistencies and differences among the different organizations. Finally, the teams conducted Rapid Improvement Events to develop “To Be” processes and functional charts for the future organization.

Phase IV: Implementation The Transformation effort is now entering Phase IV, which is the implementation of the “To Be” designs. Teams have already begun executing “Practical Next Steps” that were identified as items that can be consolidated within the next 60, 90 or 120 days and do not require organizational consolidation. For example, the Administration Management sub-working group has begun developing SOPs and standardizing processes and functions; the Portfolio Management sub-working group is working toward a standardized and automated CPIC process and a standardized POM and Budget Execution process; the Acquisitions sub-working group is collaborating on hardware, software and services acquisitions; the Telecom sub-working group is working on developing requirements for consolidating request technology; and the Information Assurance sub-working group is consolidating training and standardizing select IA processes.

Chief Information Officer Office of the Secretary of Defense

The OSD CIO / Networks Mission & Organization Relationships

OSD Customers and Products
External and Internal Drivers

OSD CIO/OSD Networks

Mission:

To provide reliable, secure, and robust information technology services to enable the mission and business processes of the organizations within the office of the Secretary of Defense across all classification levels and in all contingencies

OSD CIO Organization:

The OSD CIO is dual-hatted, also holding the position of Director, OSD Networks

As OSD CIO:

Advises the DA&M on all OSD IT and Pentagon Enterprise IT matters;

Advises OSD Principal Staff Element senior leadership on all IT matters, including IT acquisition and fiscal programming and ensures quality of service delivery to the OSD customers

As Director, OSD Networks:

Provides Information Technology operational and technical support to the Office of the Secretary of Defense, Chief Information Officer in designing, implementing, and maintaining information technology solutions for the Office of the Secretary of Defense

OSD CIO/Networks Organizational Relationships

Name Title

Team Title�

Company Name

Company Name Department Name�

Director, Administration and Management Director, Washington Headquarters Services

OSD CIO

Director, OSD Networks

Deputy Director, OSD CIO

OSD IT Board of Directors OSD CIO, rotating Board Member Co-Chair

Resources Working Group

Information Technology Management Council

Pentagon Governance Council

Pentagon Area CIO Council (PACC)

OSD Network Divisions

OSD Enterprise Configuration Control Board (ECCB)

OSD Enterprise Applications Control Board (EACB)

Operations Engineering Information Assurance Resource Management Continuity of Operations Strategic Planning, Policies & Communications Secretary of Defense Communications

Customers & Products

10 AUG 2010

Our Customers Products

The Customer Base [NCR and Beyond]

Pentagon Area

COOP Sites Pentagon (55%) Crystal City (24%) Mark Center Late 2011 ~ 6700 Employees 3 Networks

10 AUG 2010

Alexandria (7%) Arlington (5%) Rosslyn (6%)

Site 1

Site 2 Other External DoD Metro Area Office Locations (3%)

OSD IT Enterprise Customers Under Secretary of Defense (Acquisition, Technology and Logistics (AT&L)) Under Secretary of Defense for Policy Under Secretary of Defense (Comptroller) Under Secretary of Defense for Personnel & Readiness Assistant Secretary of Defense for Health Affairs Assistant Secretary of Defense for Reserve Affairs Under Secretary of Defense for Intelligence Assistant Secretary of Defense for Legislative Affairs Assistant Secretary of Defense (Networks and Information Integration/ DoD-CIO) (NII/DoD CIO) Assistant Secretary of Defense for Public Affairs DoD General Counsel Director, Operational Test & Evaluation Director, Administration and Management Director, Cost Assessment and Program Evaluation Technical Advisor- David Devries, NII/DOD CIO

The OSD Mission & Community

FOUO

OSD Supports the SECDEF!

Background

The OSD is the headquarters office for the Department of Defense (DoD) of the United States.
The OSD is the principal staff element used by the Secretary and Deputy Secretary of Defense to exercise authority, direction, and control over the Department of Defense.
Derives authority from U.S.C. Title 10

OSD’s Mission

Promulgate Policies in support of U.S. national security objectives
Provide oversight to ensure effective allocation of resources
Develop appropriate evaluation mechanisms
Participate in the U.S. Security Community

10 AUG 2010

The OSD is the headquarters office for the Department of Defense (DoD) of the United States.

The Office of the Secretary of Defense is the principal staff element used by the Secretary and Deputy Secretary of Defense to exercise authority, direction, and control over the Department of Defense. The mission of OSD as an organizational entity, in coordination with other elements of DoD, is as follows:

Develop and promulgate policies in support of United States national security objectives Provide oversight to ensure the effective allocation and efficient management of resources consistent with Secretary of Defense approved plans and programs Develop appropriate evaluation mechanisms to provide effective supervision of policy implementation and program execution at all levels of the Department Provide the focal point for departmental participation in the United States security community and other Government activities

Server hosting and storage are expected to migrate To an external provider.

Date undetermined

- Systems

Servers
Storage
Printer
Backup
Failover
Firewalls

- Staffing

Help Desk
Server Operations
Desktop
Budget / Procurement
Security
Logistics
System Architects

- Design & CIO Support

Requirements definition
Design
Development
Test and Verification
Documentation
Configuration Management
Regulatory Compliance
Policy
Infrastructure As A Service (IAAS)?
Platform As A Service (PAAS)?
Applications As A Service (AAS)?

How could we organize and procure our services differently?

10 AUG 2010

Products and Services

Firewalls are not directly managed by OSD Networks, but are instead managed by Army ITA. OSD Network personnel validate and submit FW change requests.
Servers hosting and associated services are expected to be outsourced in the 2011-2012 timeframe. Army ITA is being considered.
Storage is mostly already outsourced via the DCIN program, which is managed by Army ITA. However non-critical storage will also be considered for outsourcing.

Initiatives

10 AUG 2010

External & Internal Drivers

External Drivers

Federal Data Center Consolidation Initiative (FDCCI)
Federal-wide data center surveys and consolidation planning is in progress.
SECDEF’s ‘Savings and Efficiencies’ Memo
June 4, 2010 memo directs ‘substantive’ efficiencies department-wide.
BRAC 133
Re-shapes work locations and commute of large NCR workforce in late FY2011
FDCCI – 26 Feb 2010 Goals: Fed CIO Memo. Promote Green IT; Reduce cost of datacenter hw and sw; Increase overall IT security posture; Shift IT investments to more efficient computing platforms.
SECDEF Efficiencies Memo June 4, 2010 –
Initiatives must be specific, actionable, and measurable. Percentage and across-the-board reductions are not acceptable.
No organization, to include the Office of the Secretary of Defense (OSD), will be excluded from these efforts.
BRAC 133 – Aug – Dec 2011 moves of NCR locations to Mark Center. OSD Networks, as IT org, expects to be early mover in August 2011.

Internal Drivers

DA&M IT ‘Rationalization’
DA&M directed merge between OSD Networks Directorate and WHS IT Management Directorate
Customer Survey – Starts September
Gartner Group to conduct, ‘business efficiency’ format
Infrastructure Monitoring Effort – Started in July
ITA and OSD CIO co-sponsored effort to monitor network performance and fix problems identified.
Server & Storage Outsourcing – External provider being sought. Army ITA being considered.

10 AUG 2010

DA&M IT Rationalization – 2 year effort to consider future rightsizing, tasking, alignment of PFPA, OSD Network WHS ITMD, and PENREN. Net result is OSD Networks and WHS ITMD will be merging in the FY11 timeframe.

Customer Survey - OSD/CIO will work with Gartner to identify and schedule interviews with appropriate stakeholders including Policy, Program, Functional and Technical personnel.

Infrastructure Monitoring Effort – Program of instrumentation began in July. Data being collected. Problem fixes will be ongoing. Expected to run for several more months, as req’d. Specific desire is to attack latency concerns for network and mail servers.

Fiscal Governance Architecture Enterprise Services

COOP

Information Assurance Enterprise Network

I N T E G R A T E D Independent Enterprise A R C H I T E C T U R E Critical Infrastructure OSD IT Enterprise Modernization Effort In 2006, OSD began a modernization effort which resulted in the merger of services from separate Component networks into a single Enterprise Network Architecture.

While this effort did result in a common infrastructure and services, some work remains to reach the goal of one common network domain per classification.

10 AUG 2010

USD AT&L

ASD NII

ASD IO

USD I

USD Comptroller

ASD HA

USD P

ASD PA

DOT&E

ODA&M

CAPE

USD P&R

ASD LA

RFP Overview Overall objective of this acquisition is to combine existing legacy support contracts to obtain a full range of integrated enterprise net-centric IT supplies and services that provides all users with responsive and efficient access to common information and services on a daily basis, including timely disaster business recovery support

Office of Secretary of Defense (OSD)
Washington Headquarters Services (WHS)
Pentagon Force Protection Agency (PFPA)
Multiple Award / Indefinite Delivery Indefinite Quantity type contract (MA/IDIQ)
minimum of two (2) awards
concurrently issue two (2) Task Orders
Total small business set-a side [NAICS 541513 / $25M size standard]
Maximum (Ceiling) $495M / Guaranteed Minimum $2,500
Type of orders
firm-fixed-price
firm-fixed-price, level-of-effort term
cost-reimbursement (cost-plus-fixed-fee)
Ordering period
base period of two years
three one year options

Contract / Orders / Ordering Period

Key Dates

10 AUG 2010

Issue RFP02-AUG
Close RFP / receive proposals07-SEP
Commence oral proposals / presentations14-SEP
Conclude oral proposal / presentations04-OCT
Conclude evaluation of initial proposals22-OCT
Award on initial offers12-NOV

Section A

Standard Form (SF) 33
Offerors shall complete Blocks 12-18
Proposal Due Date
2:00 PM local time 07 SEP 2010
Offer acceptance period: 180 calendar days
Task Order Monitor (TOM)
Project Kickoff Meeting
Firm Fixed Price Level-of-Effort (FFP-LOE) Provision / Contractor Report of Work (CRW) (G.18)

Section G – Contract Administration Data

10 AUG 2010

FFP-LOE Provision/CRW

The contractor shall submit a Contractor Report of Work (CRW) in MS Excel with each invoice to WAWF that recapitulates the work performed during that month

Invoicing instructions (G.19)
Report format
Deductions
Key Personnel
Contractor Clothing Contractor Personnel Dress/Affiliations
Continual Process Improvement Initiative (PIP) (H.17)

Section H – Special Contract Requirements

10 AUG 2010

Continual Process Improvement Initiative

I. Process Improvement Proposal (PIP):

a deliverable under each Task Order
due 180 days after award
the Government reserves the right to reject the PIP if the PIP does not satisfy the requirements

Share-In-Savings:

The Contractor shall share in the cost savings

Continual Process Improvement Initiative

% of Cost Savings to the GovernmentTimeline to Exercise Option (s)% of Contractor Share in the Cost Savings to the Government
Between 10-20%90 days prior to Task Order Expiration20%
Between 21-30%120 days prior to Task Order Expiration30%
Above 31%120 days prior to Task Order ExpirationTo be mutually agreed on Not to Exceed 50%

Section L– Instructions, Conditions and Notices

Proposal Identification/Mailing:

RFP No. HQ0034-10-R-0046 Washington Headquarters Services Acquisition Directorate Attn: Ms. Patricia Watson 1777 North Kent St., Suite 12063 Arlington, VA 22209

10 AUG 2010

Proposal Cover Letter shall:

be signed by an individual authorized to commit the company to the proposal provide a statement that supports why you believe you are the best value to the Government for award

10 AUG 2010

Questions:

must be received no later than 15 calendar days prior to the RFP Close (…but please get them in early)
received after that date may not be addressed

Written Material shall be submitted in two (2) separate volumes:

Volume I - Solicitation and Price Documents

Volume II – Quality/Capability & Past Performance data

Section L – Volume I

DocumentsPage Limit
Proposal Cover Letter3
Contract Forms ( e.g., SF 33, and documentation of facilities clearance, and Accounting system)No Limit
Representations, Certifications & Other StatementsNo Limit
Organizational Conflict of Interest DocumentationNo Limit
Contractor Team Arrangement DocumentationNo Limit
Pricing Worksheets and supporting information Section J (attachments B-1, J-5 and J-6)No Limit

Section L – Volume II

DocumentsPage Limit
Organizational Structure Matrix3
Resume of Program Manager3
Corporate Experience Matrix, (Fill-in)4
Past Performance Data (complete data sheet)3

Section L– Volume II (continued)

Task 1- IT Operations ServicesPage Limit
Task Order 1 Experience Matrix, (Fill-in)6
Past Performance Matrix3
Past Performance QuestionnairesNo Limit
Past Performance Data (complete data sheet)3
Transition Plan10

Section L– Volume II (continued)

Task 2 - IT Engineering Support ServicesPage Limit
Task Order 2 Experience Matrix, (Fill-in)6
Past Performance Matrix3
Past Performance QuestionnairesNo Limit
Past Performance Data (complete data sheet)3
Transition Plan5

Section L– Oral Proposals

Offerors determined “eligible” for award shall:

conduct a real-time oral proposal
limit presentation to 90 minutes
provide at least one copy 48 hours prior
there is no limitation on number of slides

10 AUG 2010

Section L – Price Proposal

Fill-in Attachments B-1,J-5 and J-6
Provide the basis of your pricing

Section M - Evaluation Factors for Award

A proposal is eligible for award only if:

The offeror unconditionally accepts the terms and conditions of the RFP

The offeror submits all required information specified in the RFP by the closing date/time

All members of the offeror’s team (prime, subcontractors, joint venture partners, etc.) shall have an active Top-Secret facilities clearance on the date the proposal is submitted

All Offerors shall propose on all three of the following:

The Basic Contract
Task 1, IT Operations Services
Task 2, IT Engineering Support Services

Eligible offers will be evaluated for a Basic Contract award:

inclusive of both the written submission and oral proposal presentation

Inclusive of evaluation of past performance and pricing of Task Orders 1 and 2

10 AUG 2010

Section M - Evaluation Factors for Award (Basic Contract Award)

(Basic Contract Award)

Factor 1: Quality/Capability
Factor 2: Past Performance
Factor 3: Price

Order of Importance:

Factor 1 is more important than Factor 2; Factors 1 and 2 combined, are more important than Factor 3. The importance of Factor 3 will increase as the non-price factors become equal.

Factor 1: Quality/Capability

Subfactor 1: Program Management
Subfactor 2: Corporate Commitment
Subfactor 3: Resources
Subfactor 4: Corporate Experience
Subfactor 5: Subcontractor Management

All Subfactors are of equal weight

Section M - Evaluation Factors for Award (Basic Contract Award)

Factor 2: Past Performance

Subfactor 1: Basic Contract
Subfactor 2: Task Order 1
Subfactor 3: Task Order 2

All Subfactors are of equal weight

10 AUG 2010

Section M - Evaluation Factors for Award (Basic Contract Award)

Factor 3: Price

Total evaluated amount of the Basic Contract (B-1) and Task Orders 1 (J-5) and 2 (J-6), combined

(Basic Contract Award)

Offers determined to represent the best value to the Government for award of a basic contract will then be further evaluated for award of each task order on its own merit

Evaluation for each task order is inclusive of both the written submission and oral proposal presentation

10 AUG 2010

Factor 1: Quality/Capability
Subfactor 1: Corporate Experience
Subfactor 2: Transition Plan
Subfactor 3: Responses to Q&A
Factor 2: Past Performance
Factor 3: Price

(Task Order Award)

The Government will determine if the offeror's proposed price reflects the offeror's understanding of the requirements and if the proposed price is consistent with the offeror's proposal for the Basic Contract

Price will not be scored or receive an adjectival rating

(Task Order Award)

The offeror determined to represent the best value to the Government for Task Order 1 will be awarded that order. The offeror determined to represent the best value to the Government for Task Order 2 will be awarded that order. The remaining offerors that were determined to represent the best value to the Government will then be awarded a basic contract (and no concurrent task orders)

Section M - Evaluation Factors for Award (Task Order Award)

Questions

Thank you for attending!

BACK UP

H.17 Continual Process Improvement Initiative Continual Process Improvement Initiative. In order to maintain the NIEITS acquisition as a viable and efficient contract vehicle which fosters Acquisition Streamlining, facilitates cost optimization, promotes innovation and provides Information Technology net-centricity, the Contractor shall participate in a Continual Process Improvement Initiative.

I. Process Improvement Proposal (PIP):

a deliverable under each Task Order
due 180 days after award
the Government reserves the right to reject the PIP if the PIP does not satisfy the requirements

Share-In-Savings:

The Contractor shall share in the cost savings realized from an approved and implemented PIP (See following table)

10 AUG 2010

Other files

File Type Posted
Amendment 0002.pdf PDF
New Attachment L-9 Responses to Industry Questions 7 SEP 2010.docx DOCX document
Replacement Attachment J-5 - 7 Sep 2010.xls XLS spreadsheet
Replacement Page 63 - 7 Sep 2010.pdf PDF
Replacement Attachment J-6 - 7 Sep 2010.xls XLS spreadsheet
Replacement Attachment B-1 -07 Sep 2010.xls XLS spreadsheet
Replacement Attachment B-1 - 25 Aug 2010.xls XLS spreadsheet
Replacement Attachment L-1 - 25 Aug 2010.doc DOC document
Replacement Page 63 - 25 Aug 2010.doc DOC document
New Attachment L-7 - 25 Aug 2010.pdf PDF
Replacement Attachment L-4 - 25 Aug 2010.doc DOC document
Amendment 0001.pdf PDF
Replacement Attachment J-1- 25 Aug 2010.pdf PDF
New Attachment L-8 Response to industry questions and comments.pdf PDF
Replacement Attachment L-3 - 25 Aug 2010.doc DOC document
Replacement pages 44 through 46 - 25 Aug 2010.doc DOC document
Replacement Attachment L-2 - 25 Aug 2010.doc DOC document
New Attachment L-6 - 25 Aug 2010.doc DOC document
Replacement page 3 - 25 Aug 2010.doc DOC document
Replacement Attachment J-6 - 25 Aug 2010.xls XLS spreadsheet
Replacement pages 73 - 95 - 25 Aug 2010.doc DOC document
Replacement Attachment J-5 - 25 Aug 2010.xls XLS spreadsheet
Attendees List.pdf PDF
PartneringforContractingSuccess_2009.ppt PPT presentation
J-10 QASP Task Order 0002.pdf PDF
L-5 Responses to Industry Q A.xls XLS spreadsheet
C-3 OSD Environment Data Sheet.xlsm XLSM spreadsheet
C-5 OSD SOPs.pdf PDF
L-4 Task Order Level Experience Matrix.pdf PDF
J-8 PWS Task Order 0002.pdf PDF
J-3 MAC Labor Category Descriptions.pdf PDF
J-4 Definitions.pdf PDF
C-1 Statement of Objectives.pdf PDF
L-2 Past Performance Questionnaire.pdf PDF
J-5 Task 0001 - Schedule of Prices.xls XLS spreadsheet
C-4 OSD User Population List.xls XLS spreadsheet
J-9 QASP Task Order 0001.pdf PDF
J-2 Wage Determination —
J-1 DD-254.pdf PDF
HQ0034-10-R-0046 - 02 AUG.pdf PDF
C-2 OSD Environment Document.pdf PDF
J-7 PWS Task Order 0001.pdf PDF
L-1 Coporate Level Experience Matrix _SOO_.pdf PDF
J-6 Task 0002 Schedule of Prices.xls XLS spreadsheet
L-3 Past Performance Data Sheet.pdf PDF
Environment Data.xlsx XLSX spreadsheet
SOPs.pdf PDF
Draft Task 2 - Schedule of Prices - 09 JUN 2010.xls XLS spreadsheet
Draft Task 2 PWS - 09 JUN 2010.doc DOC document
Definitions.doc DOC document
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .