07 SEP 2010
| Industry Questions/Comments |
| Comments |
| 1 |
| Please clarify what GFE will be provided and shall be used by the contractor for Task Order 1 and 2. Please provide the location of GFE. |
| Refer to attachment J-7, paragraph 3.1 and 3.3 for Task Order 1 and attachment J-8 paragraph 4.b for Task 2 |
| 2 |
| If the contractor is responsible for relocating GFE, please provide the location of all GFE to be transitioned to the contractor awarded task 1 and/or 2. |
| Refer to attachment J-7, paragraph 3.1 and 4.5 for Task Order 1. There is no responsibility for relocating equipment in Task Order 2 |
| 3 |
| What is the extent of the current COOP and what time period do the exercises normally prevail over? What test plans are currently in place to verify the COOP? |
| Refer to DoD Directive 3020.26; a COOP exercise has the potential to last up to 30 days |
| 4 |
| Does the Government presently use any tool that will automatically identify assets attached to the network? |
| Refer to attachment C-3 OSD Environment Data Sheet.xlsm. |
| 5 |
| Does the Government Expect Offeror to propose pricing for COOP support see Functional Area 8 (paragraph 4.8) of Task Order 0001? |
| No |
| 6 |
| If all member companies of a JV (including the Managing Partner), and all other of the JV Team members possess current Top Secret facility clearances, is the TS facility security clearance requirement satisfied? |
| Yes |
| 7 |
| Please confirm the required response date/time |
| Refer to page 1 of Amendment 0002 |
| 8 |
| Which organization does the data provided in C-3 apply to? |
| Refer to Attachment C-4 OSD User Population List |
| 9 |
| Does attachment C-3 cover all areas the contract will be responsible for? |
| Attachment C-3 represents the current OSD environment |
| 10 |
| Will the Government issue DD254s to contract awardees? |
| Yes |
| 11 |
| Section 4.5.2.3 of Task 0001 PWS: Will the Government reimburse the cost of vans required for the transportation and delivery of IT assets throughout the NCR, as an ODC to the awardees? |
| Refer to Attachment J-7, paragraph 3.1 |
| 12 |
| “Modeling and Simulation Specialist”: CLIN 127 exists in the MAC pricing spreadsheet; however, there is no corresponding entry in the Task II Skills spreadsheet. Please explain |
| Labor categories list on the MAC Pricing spreadsheet support potential future task orders |
| 13 |
| “Documentation Specialist”: CLIN 113 of the MAC pricing spreadsheet describes two skill levels; however only one requirement, without a skill level, exists in the Task II Skills Worksheet. |
| Refer to revised Attachment J-6 |
| Industry Questions/Comments |
| Comments |
| 14 |
| B-1 lists both Modeling simulation Specialist and Network Specialist as Category #127. Please clarify. |
| Refer to revised Attachment J-6 |
| 15 |
| On Form SF33 # 15, there are 2 boxes Code and facility, what information are you requesting for each of these 2 boxes? I assume 1 box is our facility code. |
| Block 15a. In the box marked "code," please put your Cage Code and Facility code as applicable |
| 16 |
| What is a solicitation Amendment? |
| An amendment is an alteration to the solicitation. See FAR 14.208. for additional information |
| 17 |
| For bidding purposes, will the Government provide a notional dollar value for the procurement budget to be processed through this contract for Task 1 and Task 2 in the base period? |
| No |
| 18 |
| On the Attachment J-6 CLIN worksheet tab there are 85 total FTE to price; 19 called out for Surge Support CLIN 011. Please confirm it is the Government’s intent for the offeror to only price 19 surge positions and not the 42 positions specified on the Requirement tab. |
Confirmed
| 19 |
| The revised Attachment L-1, indicates task area 4.9 as IT Training Services. However, the revised Attachment J-5, CLIN X010 indicates task order 4.9 as Standardize Base Workstation Images. Please clarify. |
Attachment L-1 refers to the Statement of Objectives, which can be found in attachment C-1, whereas Attachment J-5 references the tasks for Task Order 1, which can be found in attachment J-7