ISC_Question_ _Answer_3_Nov_15.docx
DOCX document 20 KB Posted
- Attached to
- Instrumentation Test Support Federal contract opportunity
- Solicitation number
- HDTRA2-15-R-0005
- Issued by
- Defense Threat Reduction Agency
About this file
ISC Question Answer dated 3 Nov 15
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation HDTRA2-15-R-0005 “Instrumentation Test Support”
Question and Answer dated, 3 November 2015
Question 1: The SOW for Sample Task 1, in paragraph 3.14, states “All CDRLs incorporated with the contract award shall be reported under this task order.” The SOW for Sample Task 2, in paragraph 3.8, states “The contractor shall provide the following CDRLs in executing Task Order: A001, A002, A003, A007, A008, A009, A010, A011.” CDRL items A007 (Fielding Plan Report), A008 (Safety Plan), A010 (Technical Results Report), and A011 (Final Task Order Report) are specific to Sample Task 2 and would be prepared by those working Sample Task 2, and thus priced under Sample Task 2. What does it mean to “report” these under Sample Task 1?
Answer 1: Reference revised Sample Task Order 1, paragraph 3.14, dated 3 November 2015.
Solicitation HDTRA2-15-R-0005 Page 1