Atch 3 Figure 6 2 Implementation&Transition Gantt-Rev1 Amend 0002-20200223.pdf

PDF 720 KB Posted

Attached to
Defense Research Engineering Network - DREN4
Solicitation number
HC101319R0006
Issued by

About this file

This document contains a Gantt chart outlining the implementation and transition plan for the Defense Research Engineering Network (DREN4) federal contract opportunity. Key details include: the contractor will develop the Initial Performance Capability over 318 days from contract award, with demonstrations and testing occurring between September and November 2021 and government acceptance by mid-November; the Contractor Integrated Technical Plan will be developed over 304 days and finalized by early November 2021; and Transition Phase II will execute the CITP over 365 days from mid-November 2021 through mid-November 2022, with the SDREN network node to be operational at the DREN4 Network Operations Center by mid-May 2022. The opportunity is for the DREN4 network and related support services, with the solicitation response due by January 27, 2020 and questions due by December 16, 2019. The Defense Information Systems Agency is the contracting agency.

View the file

Other files

File Type Posted
HC101319R0006A0009 RFP Amend 0009.pdf PDF
HC101319R0006A0009 RFP Conformed Copy.pdf PDF
L1 - Solicitation Question and Answer - Round 2 Late Questions - 20200430 .xlsx XLSX spreadsheet
HC101319R0006A0008 RFP Amend 0008.pdf PDF
L1 - Solicitation Question and Answer - Round 2 Late Question - 20200428.xlsx XLSX spreadsheet
HC101319R0006A0008 RFP Conformed Copy.pdf PDF
L1 - Solicitation Question and Answer - Round 2 Government Response - Additional Late Question 20200331.xlsx XLSX spreadsheet
Atch 2 DREN4-PWS-Rev 3-Amend 0007-20200401.pdf PDF
HC101319R0006A0007 RFP Conformed Copy.pdf PDF
HC101319R0006A0007 RFP Amend 0007.pdf PDF
L1 - Solicitation Question and Answer - Round 2 Government Response - 2 Late Questions 20200319.xlsx XLSX spreadsheet
HC101319R0006A0006 RFP Amend 0006.pdf PDF
HC101319R0006A0006 RFP Conformed Copy.pdf PDF
HC101319R0006A0005 RFP Conformed Copy.pdf PDF
HC101319R0006A0005 RFP Amend 0005.pdf PDF
L1 - Solicitation Question and Answer - Round 2 Government Response - Late Questions 20200309.xlsx XLSX spreadsheet
HC101319R0006A0004 RFP Amend 0004.pdf PDF
HC101319R0006A0004 RFP Conformed Copy.pdf PDF
HC101319R0006A0003 RFP Amend 0003.pdf PDF
HC101319R0006A0003 RFP Conformed Copy.pdf PDF
Atch 2 DREN4-PWS-Rev 2-Amend 0002-20200224.pdf PDF
HC101319R0006A0002 RFP Conformed Copy.pdf PDF
Atch 4 Figure 6 3 Implementation&Transition Timeline-Rev 1-Amend 0002-20200225.pdf PDF
L1 - Solicitation Questions and Answers - Round 2 Government Response.xlsx XLSX spreadsheet
Atch 1 Section B Pricing Schedule CLIN Pricing Worksheet-Rev 2-Amend 0002.xlsx XLSX spreadsheet
Atch 8 DREN4-QASP-Rev 2-Amend 0002-20200224.pdf PDF
HC101319R0006A0002 RFP Amend 0002.pdf PDF
Atch 1 Section B Pricing Schedule CLIN Pricing Worksheet Amendment 0001 20200128.xlsx XLSX spreadsheet
L1 - Solicitation Question and Answer Template.xlsx XLSX spreadsheet
L1 - Solicitation Questions and Answers - Round 1 Government Response.xlsx XLSX spreadsheet
Atch 2 DREN4 Performance Work Statement (PWS) Amend 0001.pdf PDF
Atch 1 Section B Pricing Schedule CLIN Pricing Worksheet Amend 0001.xlsx XLSX spreadsheet
Atch 7 DD Form 254 Amend 0001.pdf PDF
Atch 8 DREN4 QASP Amend 0001.pdf PDF
Atch 4 Figure 6 3 Implementation & Transition Timeline.pdf PDF
HC101319R0006A0001 RFP Conformed Copy.pdf PDF
Atch 5 DREN Node Master Plan (Template).docx DOCX document
Atch 3 Figure 6 2 Implementation & Transition Gantt.pdf PDF
HC101319R0006A0001 RFP Amend 0001.pdf PDF
HC101319R0006 RFP.pdf PDF
Figure 6 3 ImplementationTransitionTimeline (PWS Reference Document).pdf PDF
Performance Work Statement (PWS).pdf PDF
L1 - Solicitation Question and Answer Template.xlsx XLSX spreadsheet
DD Form 254.pdf PDF
Quality Assurance Surveillance Plan (QASP).pdf PDF
Section B Pricing Schedule CLIN Spreadsheet.xlsx XLSX spreadsheet
Figure 6 2 ImplementationTransitionGantt (PWS Reference Document).pdf PDF
DREN Node Master Plan (PWS Reference Document).docx DOCX document
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Resource Names

Duration Start Finish Predecessors

1 CONTRACT AWARD 0 days Fri 1/1/21 Fri 1/1/21 2 Approvals/Direction 224 days Mon 4/5/21 Mon 11/15/21 3 KO Direction to Proceed with IPC Plan Execution 0 days Mon 4/5/21 Mon 4/5/21 22,27 4 KO Direction to Proceed with CITP Execution 0 days Mon 11/15/21 Mon 11/15/21 9,44,51 5 Assess and Authorization Process 318 days Fri 1/1/21 Mon 11/15/21 6 Obtain IATT 241 days Fri 1/1/21 Mon 8/30/21 1 7 Develop IATT RMF Artifacts Contractor 220 days Fri 1/1/21 Mon 8/9/21 8 SCA Review & AO Approve IATT 21 days Mon 8/9/21 Mon 8/30/21 7 9 Obtain ATO 318 days Fri 1/1/21 Mon 11/15/21 1 10 Develop ATO RMF Artifacts Contractor 243 days Fri 1/1/21 Wed 9/1/21 11 SCA-V 45 days Wed 9/1/21 Sat 10/16/21 10 12 ISSM POAM Review 15 days Sat 10/16/21 Sun 10/31/21 11 13 AO Approve ATO 15 days Sun 10/31/21 Mon 11/15/21 12 14 Transition Phase I 318 days Fri 1/1/21 Mon 11/15/21 1 15 IPC - Initial Performance Capability 318 days Fri 1/1/21 Mon 11/15/21 16 IPC Plan Development 94 days Fri 1/1/21 Mon 4/5/21 17 Develop IPC Plan Contractor 60 days Fri 1/1/21 Tue 3/2/21 1 18 DRAFT IPC Plan Submitted Contractor 0 days Tue 3/2/21 Tue 3/2/21 17 19 Work with Government to Finalize IPC Plan Contractor 20 days Tue 3/2/21 Mon 3/22/21 18 20 FINAL IPC Plan Submitted Contractor 0 days Mon 3/22/21 Mon 3/22/21 19 21 Government Review 14 days Mon 3/22/21 Mon 4/5/21 20 22 Government Accept FINAL IPC Plan 0 days Mon 4/5/21 Mon 4/5/21 21 23 RTM - Requirements Traceability Matrix 74 days Fri 1/1/21 Tue 3/16/21 24 Develop RTM Contractor 60 days Fri 1/1/21 Tue 3/2/21 25 RTM Submitted Contractor 0 days Tue 3/2/21 Tue 3/2/21 24 26 Government Review 14 days Tue 3/2/21 Tue 3/16/21 25 27 Government Accept RTM 0 days Tue 3/16/21 Tue 3/16/21 26 28 Government Orders IPC Services 64 days Sun 1/31/21 Mon 4/5/21 17SS+50% 29 IPC Plan Execution / Implement IPC Contractor 150 days Mon 4/5/21 Thu 9/2/21 3 30 IPCDP - IPC Demonstration Plan 145 days Mon 3/22/21 Sat 8/14/21 31 Develop IPCDP & IPTs Contractor 120 days Mon 3/22/21 Tue 7/20/21 20 32 Work with Government to Finalize IPCDP Contractor 20 days Tue 7/20/21 Mon 8/9/21 31 33 IPCDP Submitted Contractor 0 days Mon 8/9/21 Mon 8/9/21 32 34 Government Acceptance of IPCDP 5 days Mon 8/9/21 Sat 8/14/21 33 35 IPC T&D - IPC Test & Demonstration 53 days Thu 9/2/21 Mon 10/25/21 36 Requirements Tests Contractor 30 days Thu 9/2/21 Sat 10/2/21 6,29,34 37 Individual SDP Tests Contractor 21 days Sat 10/2/21 Sat 10/23/21 36 38 Aggregate SDP Test Contractor 1 day Sat 10/23/21 Sun 10/24/21 37 39 Coast to Coast Performance Test Contractor 1 day Sun 10/24/21 Mon 10/25/21 38 40 IPCDR - IPC Demonstration Report 21 days Mon 10/25/21 Mon 11/15/21 41 Update IPCDP & IPTs w/ IPC T&D Results Contractor 7 days Mon 10/25/21 Mon 11/1/21 35 42 IPCDR Submitted Contractor 0 days Mon 11/1/21 Mon 11/1/21 41 43 Government Review 14 days Mon 11/1/21 Mon 11/15/21 42 44 Government Acceptance of IPCDR 0 days Mon 11/15/21 Mon 11/15/21 43 45 CITP Development 304 days Fri 1/1/21 Mon 11/1/21 46 Develop DRAFT CITP Contractor 200 days Fri 1/1/21 Tue 7/20/21 1 47 DRAFT CITP Submitted Contractor 0 days Tue 7/20/21 Tue 7/20/21 46 48 Work with Government to Finalize CITP Contractor 90 days Tue 7/20/21 Mon 10/18/21 46 49 FINAL CITP Submitted Contractor 0 days Mon 10/18/21 Mon 10/18/21 48 50 Government Review 14 days Mon 10/18/21 Mon 11/1/21 49 51 Government Acceptance of CITP 0 days Mon 11/1/21 Mon 11/1/21 50 52 Transition Phase II 365 days Mon 11/15/21 Tue 11/15/22 51 53 Execute CITP Contractor 365 days Mon 11/15/21 Tue 11/15/22 4,51 54 SDREN Node Operational at DREN4 NOC Contractor 0 days Sat 5/14/22 Sat 5/14/22 53SS+180 days 55 Cutover Contractor 365 days Mon 11/15/21 Tue 11/15/22 4,51

1/1

4/5

11/15

Contractor

Contractor

Contractor

3/2

Contractor

3/22

4/5

Contractor

3/2

3/16

Contractor

Contractor

Contractor

8/9

Contractor

Contractor

Contractor

Contractor

Contractor

11/1

11/15

Contractor

7/20

Contractor

10/18

11/1

Contractor

5/14

Contractor

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023

File details come from the government source that posted it. Updated .