5. H92276-23-R-0029 Request for Information II.pdf
PDF 81 KB Posted
- Attached to
- Body Armor Federal contract opportunity
- Solicitation number
- H92276-23-R-0029
- Issued by
- United States Special Operations Command
About this file
This document contains questions and answers regarding Request for Information II for solicitation number H92276-23-R-0029 for body armor from the United States Special Operations Command. The questions and answers provide details on samples not being required if specifications can be demonstrated, acceptance of subcontractor past performance under certain conditions, no extension being issued for the proposal due date given applicability of the Berry Amendment, helmet size and color requirements of 25% small, 25% medium, 50% large and coyote/tan, acceptance of cuts other than mid-cut such as high cut or low cut on helmets, and night vision goggle rails being required but no other attachments on helmets.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 11. H92276-23-R-0029 Request for Information V.pdf | ||
| 10. H92276-23-R-0029 Request for Information IV.pdf | ||
| 7. H92276-23-R-0029 SF 30 Amendment 0001.pdf | ||
| 8. H92276-23-R-0029 Updated Solicitation.pdf | ||
| 6. H92276-23-R-0029 Request for Information III.pdf | ||
| 4. H92276-23-R-0029 Request for Information.pdf | ||
| 1. H92276-23-R-0029 Request for Quote.pdf | ||
| 2. H92276-23-R-0029 Item Specification Sheet.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information II
For
H9227623R0029: Body Armor
29 August 2023
Q1: Will any samples be necessary?
A1: Samples will not be required, as long it can be clearly demonstrated that the items provided meet the specifications stated.
Q2: May we include a subcontractor's past performance as part of our past performance submission?
A2: It would be preferrable to have your own past performance, however, sub-contractor past performance is acceptable as long as you can clearly demonstrate that you performed as the
Prime Contractor on your subcontractors’ contracts. You are not permitted to submit your subcontractor past performance as your own. In such case, you as the prime contractor will have to clearly demonstrate effective management of the sub-contractor performance on your contractor.
Q3: Given the Berry Amendment and other clarifications provided in your answers from earlier today, do you plan to issue an extension on the contract?
A3: No, the applicability of the Berry Amendment should not impact the proposal due date, therefore, it has been determined that there will be not extension at this time.
Q4: What are the sizes and color requirements for the helmets?
A4: 25% Small, 25% Med, 50% Large, all Coyote/Tan
Q5: Will other cuts besides mid-cut be accepted on the helmets, such as high cut/low-cut?
A5: Yes.
Q6: Are there any attachments such as NVG rails that need to be on the helmets?
A6: NVG rails should be on the helmet. No other attachments are required.