H92222-10-R-0044 Attachment 11 - Questions and Answers Format
18 Jan 2011
SOCOM SPECIALTY SERVICES RFP
| QUESTION # |
| SECTION / PARAGRAPH / PAGE |
| Questions / Comments |
| Response |
Action
| 1 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| The Proposal will require a Transition Plan. In order to write a meaningful plan the following information will be required. Who is the current incumbent? |
| The incumbent is L3 on the EITC contract. |
| N/C |
| 2 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| Are there more than one incumbent? Who are they? |
| L3 is the only incumbent. |
| N/C |
| 3 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| How many Task Orders are currently active? |
| Approximately 20 active task orders under the EITC contract will be transitioned to the Specialty Services contract. |
N/C
| 4 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| Where are the active Task Orders being implemented? CONUS, OCONUS etc.? |
| Both CONUS and OCONUS. |
| N/C |
| 5 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| How many employees are currently being used by the incumbent/s? |
| Current EITC task orders are posted in the Bidder’s Library. |
| N/C |
| 6 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| What Task Orders by Task Order type are currently active? |
| EITC task orders are nearly all Labor Hours type tasks. A very small percentage of TOs are cost type and fixed price. |
| N/C |
| 7 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| How many employees by Task Order are currently being employed by the incumbent/s? |
| Current EITC task orders are posted in the Bidder’s Library |
| N/C |
| 8 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| In 2007, 2008, 2009 and 2010 how many Task Orders were issued? |
| The historical information for each year is not available. Approximately 20 active task orders under the EITC contract will be transitioned to the Specialty services contract |
| N/C |
| 9 |
| Section C/5.7 Transition Processes/Plan /Page 22 |
| In 2007, 2008, 2009 and 2010 what was the value of the Task Order in dollars? |
| All available information on previous task orders is posted in the SITEC library. |
| N/C |
| 10 |
| SOCPAC JSOTF-P SOO Package |
SITE R SOO Package SOCCENT SOO Package
| Can the Government provide more detailed historical labor requirements or cost information regarding the current EITC task orders that the Specialty Services task orders are intended to replace? |
| All available information on previous task orders is posted in the SITEC library. |
| N/C |
| 11 |
| SOCPAC SOO |
| Since the SOCPAC SOO requirements are significantly longer than the other two SOOs, would the Government consider increasing the page limits on the PWS to ensure that bidders have enough space to account for all of the SOO requirements in addition to contractor innovations and enhancements? |
| The government is committed to its page limitations. |
| N/C |
| 12 |
| RFP, H92222-10-R-0044, 952.225.0011 Government Furnished Contractor Support, page 16 of 74 |
| Will the Government confirm that it will provide no support to U.S. citizen contractor personnel traveling OCONUS in support of task orders awarded under this contract, including billeting, military air transport and resuscitative care? If so, would the Government reconsider and provide such support? |
| Support is described in Section H clause 952.225-0011 |
| N/C |
| 13 |
| Pricing |
| Will the Government provide a pricing template to be used for the three task orders, or should each Offeror supply its own pricing format? |
| Offerors should provide their own format that complies with Sections L&M of the RFP. |
| N/C |
| 14 |
| SOCPAC JSOTF-P SOO/ Paragraph 10/Page 22 of 32 |
SITE R SOO Package – Attachment 8/Paragraph 10/Page 5 of 15
SOCCENT SOO Package – Attachment 9/Paragraph 9/Page 10 of 20
And
Attachment 11 – Question and Answers dated November 12, 2010 , Question and Answer #10 Referenced section states: “All Positions in support of this Task Order are considered key positions. As such, Contractor shall submit Resumes for all new and replacement candidates proposed.” The requirement to provide a resume for each position puts all potential new offerors at a disadvantage in favor of the current incumbent. In addition, even if each new Offeror provides a resume for each position on each task order (for SOCPAC ~51 2 page resumes), it is unrealistic for the Government to expect that all proposed personnel will actually be available by the beginning of the TO POPs. This is disadvantageous to the Government because, due to the time delay between RFP responses (in January) and Task Order POP start (April), it creates a false expectation of the personnel who will be actually be available at task order inception. In addition, the Government will be in the position of having to evaluate a set of resumes for proposed replacement personnel, a time consuming process for the Government managers and Contracting Office. Would the Government consider redefining the key positions in each of the three initial task orders to minimize the Resume requirement to include only the Task Lead and Technical Team leads or would the Government be willing to permit the offerors to define and to justify their own key positions?
Additionally, are resumes excluded from Task Order response page count?
Key positions are revised to read for each task: the site lead, service desk lead, IA lead, networks lead, data center lead, distributed computing lead and application management lead. Critical personnel will not require a resume.
Resumes do not count against the page count.
Clause updated.
Section L updated.
| 15 |
| RFP Section L III – Past Performance/Page 65 of 74 |
Attachment 11 – Draft RFP Question and Answers dated November 12, 2010, Question and Answer 75
| A question was asked in regards to the draft RFP (question 75 in Attachment 11) if the page limit for the Past Performance Information Sheets could be increased given that the draft RFP allocated 50 pages for the Past Performance Volume. In response, it was stated that the fifty pages accounted for the Table of Contents, Summary describing the role of the Offeror and each subcontractor, teaming partner, and/or joint venture partner, Past Performance Information Sheets and the Completed SF 294s/295s. However, with the final RFP the page limit for Volume III was reduced to thirty (30) pages with the same requirements. Based on the offeror’s experience, each SF 294/295 typically takes 3-4 pages per form due to the extensive contractual information included and is typically outside of page count. If 5 past performance references are cited, the SF 294/295s will take 15-20 pages of the allotted 30 pages. This leaves 10-15 pages for the remainder of the volume, which limits the Offeror’s ability to provide substantive information on each past performance. Please confirm whether the SF 294/295s are now outside of page count due to the reduction in pages allowed for Volume III. |
| SF 294s and 295s are not included in the page limit. |
| N/C |
| 16 |
| Solicitation Document/5652.237-9001(c)/page 52 |
| The Government identified Office Chief as a key personnel requirement. However in questions 91 and 92 of the Q&A document, it is said that this requirement has been removed. Since it is in the final RFP, can the Government confirm that this is no longer a key personnel requirement? |
| Office Chief has been deleted. |
| RFP clause revised. |
| 17 |
| Solicitation Document/H.6.2/page 23 |
| Since the Government will require that successful offerors must submit a bid on every task order request, can the Government provide a forecast of the number of task order requests to be issued during the base contract period for planning purposes? |
| There will be approximately 20 task orders issued during the base contract period. |
| N/C |
| 18 |
| IDIQ PWS/Paragraph 5.7.1, Phase In-Period/Page 22 of 23 |
| The Phase in period is defined as time of Award (approximately 15 JAN 11) to 01 April 11. Given the submission of proposals is on 03 JAN 11, would the Government consider addressing a new phase in period? |
| Award of the Specialty Services basic contracts will be made a soon as possible before 31 Mar 2011 to allow for as much transition time as possible. |
| N/C |
| 19 |
| RFP H92222-10-R-0044/Section F/Page 7 of 74 |
| CLIN 1001 and 1002 have a POP of 01 JAN 2011 – 31 MAR 2016. Is it the Government’s intent to revise those dates at Contract Award? |
| Award of the Specialty Services basic contracts will be made as soon as possible before 31 Mar 2011 to allow for as much transition time as possible. |
| RFP revised to read “1 Apr 2011 – 31 Mar 2016” |
| 20 |
| Instructions to Offerors (ITO) |
SOCCENT Information systems and Deployment support/Period and Place of Performance Place of performance states that SOCCENT TO work will be performed on site at SOCCENT, which encompasses 2 geographic locations (CONUS and OCONUS)
a. Can the Govt. clarify which is the OCONUS location? (assuming CONUS is MacDill AFB in FL although not explicitly stated)?
b. Can the Govt clarify what Specific Requirements/Deliverables (SECTION 3.0) are applicable to which site (OCONUS or CONUS) in order to assist us in appropriate staffing decisions? Or do we assume that all support functions/deliverables are required in both SOCCENT locations? (duplicate staffing for both locations?)
| The OCONUS site is CFSOCC, Al Udeid, AB, Qatar. The WAVE administrator is located at HQ SOCCENT. Additionally, SOCCENT and CFSOCC no longer require UC3 support and only CFSOCC requires Spyder video hub support. All other support functions/deliverables are required in both SOCCENT locations. |
| N/C |
N/C
| 21 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.1, 3.3, 3.4, 3.5 & 3.7 |
| In order to appropriately size the effort, can the Government provide additional information regarding current staffing levels, parameters (e.g., number of devices, number of projects, number of trouble tickets etc.), or effort for each of the network and system administration subtasks? |
| The number of network devices includes approximately 20 routers, 70 switches, 2500 active ports; 100 servers; 20-25 projects, and 250 concurrent trouble tickets. |
| N/C |
| 22 |
| Section 5.7.1.2 of PWS Phase-in Period – Task Orders Page 23 |
| Does the Government have a specific timeframe to complete transition on the SOCCENT TO? |
| Transition shall be complete by 1 Apr 2011. |
| N/C |
| 23 |
| General |
| Do the incumbent contractors have transition out responsibility under their current contracts? |
| Yes the EITC contractor has a transition out responsibility. |
| N/C |
| 24 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.4 – Project Coordination Requirements |
| In order to appropriately size the task, for telecommunication projects, please provide number of telecommunication projects, vendors for those projects, and distribution by site. |
| The organization is unable to provide specific numbers, but the scope will include new circuit actions, router/switch/server installations or upgrades, network expansion into new work areas, development and implementation of new management tools, and sustainment of current systems to comply with new CYBERCOM requirements. Vendors: include, but not limited to, NAVAIR, Cisco, NetApp; Microsoft |
| N/C |
| 25 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.1- |
System Support Requirements
| Please specify the approved network performance suite of tools. |
| Current network performance suite of tools includes Solarwinds, V1, Cisco Works, and Network Analysis Module. |
| N/C |
| 26 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.2 |
| Will the Government provide an inventory of all platforms to be reviewed for compliance with NIST and USSOCOM security guidelines? |
| Available information is posted in the Bidder’s Library. |
| N/C |
| 27 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.2.2 |
| Please specify types of IDS/IPS used within the SOCCENT infrastructure. |
| CFSOCC has CSIDS provided by AFCENT |
| N/C |
| 28 |
| SOCCENT Information Systems (IS) and Deployment Support/Section 3.1.8, 3.19 & 3.2.1 |
| Please verify the desired coverage of Tier 3 support Sections 3.1.8, 3.1.9 & 3.2.1. Is any historical data available concerning volume and type of tickets? What are the core hours for Tier 3 support, and is on-call support required? |
| At HQ SOCCENT, Tier 3 support will be required 40 hrs/week, M-F, with capability of 10 hrs per week for surge. At CFSOCC, contractor personnel will work 6-7 days/72 hours per week. On average, on-call support is required for critical support 5-6 times per quarter. |
No historical data is available concerning volume and type of Tier 3 tickets.
Core hours for Tier 3 support is; Tampa, 8hr, M-F with on-call support after duty hours; for Qatar, 12 hr duty day, 6 days a week with on-call support after duty hours.
N/C
| 29 |
| SOCCENT Information Systems (IS) and Deployment Support/ Section 3.1 |
| Will the Government provide modeling and simulation tools for LAN/MAN/WAN design? Are there existing models that the Government will provide? |
| No SOCOM modeling tool exists. |
| N/C |
| 30 |
| SOCCENT Information Systems (IS) and Deployment Support - General |
| Will the Government clarify demarcation of responsibility between the SOCCENT TO and other service area provider activities, for example where the Enterprise Network |
contractor WAN/MAN/CAN/LAN responsibilities end and Specialty Services
Contractor begins, etc.)?
| At the time, the only demarcation concerns between Specialty Svc and the Unit Towers exists with Enterprise Networks. Enterprise Networks responsibility (as it relates to SSEPs and SCAMPI Nodes) terminates on the LAN side of the premise router. |
| N/C |
| Attachment 2 / Introduction and Performance Incentive Calculation |
| Attachment 2 references SLA and specific details related to Performance Incentive calculation can be found in Appendix A. Will the Government provide a copy of Appendix A? |
| The reference to Appendix A d has been removed. |
| Attachment 2 has been revised |
| 32 |
| Attachment 8 / page 6 |
| “Period and Place of Performance: … Place of Performance is onsite. The Government anticipates this work to be performed on site at Site R, which encompasses three (3) geographic locations (CONUS). … |
Travel: Travel will be required both CONUS and OCONUS (to include Hazardous Duty Locations).”
Are there generalized CONUS geographic locations that can be disclosed?
Will the Government provide a percentage of work to be done in CONUS/OCONUS locations so offerors can price appropriately (i.e., Hazard/Hardship/DBA cost for OCONUS where appropriate?
The SOO and applicable attachments have been revised to provide specific organization and CONUS geographic locations.
SOO and applicable attachments have been revised.
| 33 |
| Attachment 8, 9 and 10 |
| All three ITOs for these attachments reference Historical Labor Requirements – attachment 8 – EITC Task Order #859; attachment 9 – EITC Task Order #929; and attachment 10 – EITC Task Order #920. Will the government provide these task orders to contractors? |
| Current EITC task orders have been posted to the Bidder’s Library. |
| N/C |
| 34 |
| Attachments 8, 9 and 10 |
| The sample task period of performance is stated as I base year with 4 one-year options. Section B does not provide CLIN pricing per sample task or pricing per year. Is it the Government’s desire to receive one CPFF CLIN for one five-year period per sample task? Please clarify. |
| The task orders included in the RFP are not sample tasks - they are real tasks that the Government intends to exercise. The offerors shall provide a cost/price per task per year for the base year and each option year. After each year of performance the Government will have the option of exercising the task order option or recomplete the task among the multiple awardees. |
| N/C |
| 35 |
| Attachments 8, 9, 10 |
| Are contractors expected to propose 100% of the costs for the named categories in 5652.237-9001 in our three proposals related to attachments 8, 9 and 10? Or, can we choose to propose a portion or even no hours of their time in the pricing for the three task orders? Please clarify. |
| 100% of the personnel should be proposed in each task. PM and deputy not fully dedicated to task and shouldn’t be proposed in the task cost/price. |
| N/C |
| 36 |
| Attachments 8, 9, 10 |
| Attachment 8 - Personnel 10.0, Attachment 9 – Personnel 9.0, and Attachment 10 – Personnel 10.0 specify that all positions supporting the Task Order are considered key positions. Page 52 of 74, 5652.237-9001 Key Personnel Requirements (c) specifies the Program Manager, Assistant/Deputy Program Manager and Office Chiefs for USSOCOM Tampa, JSOC and TSOCs as key personnel |
Are we to use only the slots named in the RFP for pricing attachments 8, 9 and 10?
Are all personnel proposed (at a contractor’s discretion) for attachments 8, 9 and 10 to be included in the key personnel clause after contract award?
How many resumes does the Government expect to see in the responses to each SOO?
| See question 14 response. |
| See question 14 answer. |
| 37 |
| Attachments 8, 9, 10 |
| Efforts in OCONUS locations, especially those deemed Hazardous Duty locations, have very unique costs in order to hire and retain employees. Can the Government specify exact countries and cities where performance will occur for each of the three sample tasks? Or are these types of costs (Hazardous Duty Pay, Hardship Pay, etc.) included in the Government travel estimates in each of the three sample tasks? |
| Specific countries are not available. OCONUS travel locations may be world wide for Attachment 8. OCONUS travel for Attachment 9 is within the CENTCOM AOR. OCONUS travel for Attachment 10 is within the PACOM AOR. The Government travel estimates for each solicitation are provided for information only. The estimates include travel cost only and do not include pay. Offerors are expected to propose all cost consistent with their Cost Accounting System. |
| N/C |
| 38 |
| Attachment 10 / Materials 7.9 |
| Attachment 10, Materials 7.9 specifies that Contractors must include the cost of DBA. Attachments 8 and 9 do not mention DBA. Should contractors include this cost in the pricing for all three tasks? |
| Yes |
| N/C |
| 39 |
| Attachment 10 / 3.1.3 Table A / page 2 |
| The paragraph references in the headers appear to have no correlation to the SOO paragraphs or the Section C PWS paragraphs. What do the numbers refer to? |
| Paragraph references have been removed. |
| SOCPAC SOO has been revised and will be included in a modification |
| 40 |
| Attachment 10 / 3.1.3 |
| Attachment 10, 3.1.3 states that the contractor shall provide the capabilities articulated in Table A. Table A lists SOCPAC SITEC functions with respect to systems. Many of the systems listed do not have any functional requirements according to Table A in that they have no intersections with functions that contain an “X”. However, elsewhere in the Attachment 10 SOO, some of those systems are stated as requirements with particular functions while others are not. What is the meaning of the “X” in Table A? |
| Systems/functions with no “X” have been deleted. |
| SOCPAC SOO has been revised and will be included in a modification. |
| 41 |
| Attachment 10 / 5.0 |
| Attachment 10 paragraph 5.0 Reports references CDRLs E013, E014 and E022. Attachment 7, CDRL master list includes only CDRLs E001 - E012. Will E013, E014 and E022 be provided? Please clarify. |
| References to CDRLs E013, E014, and E022, have been removed from Attachment 10. |
| SOO has been revised and will be included in modification. |
| 42 |
| Section B / CLINs 1001 and 1002 / page 2 |
| Are Contractors to leave the Max Amounts blank, insert “TBD” or include the price for the three sample tasks into the appropriate CLIN? Please clarify. |
| The government will complete these amounts at contract award. |
| N/C |
| 43 |
| Section F / Delivery Information / page 7 |
| The RFP states the delivery period to be 1 January 2011 – 31 March 2016; Attachments 8, 9 and 10 have start dates of 1 April 2011; and section L.1.5 states contract award is 1 March. Please clarify the period of performance. |
| The ordering period for the contract will be 1 Apr 2011 – 31 March 2016. Task order performance periods will not coincide with the contract ordering period. The period of performance for each task order will be detailed in each ITO. |
| N/C |
| 44 |
| Section H / 952.225-0011 / page 16 |
| Attachment 10 requires personnel to be assigned to Manila as a permanent duty station. What type of Government-furnished contractor support will be provided for those U.S. citizens supporting overseas deployment? |
| The Clause has been revised to indicate that no Government-Furnished support will be provided. |
| RFP revised. |
| 45 |
| Section H / 6.2 / page 24 |
| Since task order workload data is not available, is it the intent of the Government to have a rate table identifying labor categories to support each task order, or labor categories with numbers of personnel to support each task order? |
If numbers of personnel are desired, when will the workload data be made available?
| Each task order will be a performance based FFP or CPFF order, The Government will not include labor rate tables in the task orders. The Government does not desire numbers of personnel. |
| N/C |
| 46 |
| Section H / 6.2 / page 24 ; |
Section M / 1.5 Factor 3/ page 72
| H.6.2 states that “during the initial task order evaluations, since current task order past performance has not yet been demonstrated, all prime offerors will be given a neutral rating,” and M.1.5 Factor 3 provides evaluation criteria for past and present performance. Please clarify how past performance will be evaluated. |
| The section M criteria will be used to determine the offeror’s eligibility for contract award. All offerors will receive a neutral rating in the evaluation to determine the task order awardees. |
| N/C |
| 47 |
| Section I / 5652.237-9001 / page 52 |
| The referenced contract clause states that “certain experienced professional and/or technical personnel are essential for successful accomplishment of the work to be performed under this contract.” Additionally, “such personnel are defined as ‘Key Personnel’ and are those whose resumes were submitted for evaluation of the proposal.” Subparagraph (c) identifies the Program Manager, Assistant/Deputy Program Manager and Office Chiefs as “Key Personnel”. Is it the intent of the Government to review and evaluate resumes for all “Key Personnel” positions with the proposal, or will the resumes be submitted for review and evaluation with subsequent task orders after the contract is awarded? If the intent is to review and evaluate key personnel with the proposal submission, will there be a CLIN assigned to capture the costs associated with these positions? |
| Offerors shall submit resumes for evaluation with their proposal. There will not be a CLIN assigned to capture the cost associated with non-task dedicated positions. |
| N/C |
| 48 |
| Section I / 5652.237-9001 (c) / page 52 |
| The RFP includes this line where Key Personnel are identified: |
“Office Chiefs for USSOCOM Tampa, JSOC and TSOCs” But in the Q&As, the answer to question 91 states, “The Office Chief has been deleted from the RFP” and the answer to question 92 states, “The Office Chief has been removed from the clause. Geographic location of the other positions should be predicated on the offeror’s proposal approach.”
Please clarify how many key personnel resumes are required in response to Volume II requirements.
| RFP has been revised to remove Office Chief, see question 14 response. |
| RFP has been revised to remove Office Chief, see question 14 action. |
| 49 |
| Section I / c. / page 52 |
| The RFP defines key personnel as the program manager, deputy program manager and office chiefs. In support of the sample task orders, many other positions will be needed. Is it the intent of the personnel description in attachments 8, 9, and 10 to identify every position as a key personnel and then hold these positions to the same requirements as described in Section I Key Personnel? |
| See question 14 response. |
| See |
See question 14 action.
| 50 |
| Section L / 1.5 / page 61 |
| In the Section L to Section M Crosswalk Table, the Section M paragraph references are confusing. For example, M.1.3.1 – Facility Clearance referenced in the table is actually Subfactor 1 – Management Organizational Structure/Teaming Arrangements/Key Personnel. Please clarify the intended crosswalk between Section L references and Section M references. |
| See question 85 response. |
| See question 85 action. |
| 51 |
| Section L / L.2 / page 63 |
| Section H requires Section K to be submitted through ORCA; section L requires section K to be completed and included within Volume 1-C. Are both submittals necessary? Please clarify. |
| ORCA submittal is required for all offerors additional certifications that are not included in ORCA will need to be completed and submitted with the offeror’s proposal. |
| N/C |
| 52 |
| Section L / L.2 / page 65 |
| Section L describes Volume III as Past Performance Information. The crosswalk matrix describes Volume III as Past and Present Performance Information, as does Section M. Section L titles the volume as Past Performance. Please clarify the Volume III title. |
| “and Present” will be deleted for consistency |
| RFP has been revised |
| 53 |
| Volume IV / IV-A / page 67 |
| Volume IV Task Order Management, Technical. – The instructions state “The basis of estimate shall be detailed sufficiently to understand the Offeror’s approach …utilized to develop the Offeror’s firm fixed price offer.” This Contractor believes that this section refers to the three sample tasks. If that is the case, can we assume that the language meant to specify CPFF rather than firm fixed price? If not, can you please clarify how Contractors are to provide basis of estimate details for a Firm Fixed Price offer? |
| The language has been revised for Clarity. |
| N/C |
| 54 |
| Section L / IV-B PWS / page 67 |
| The RFP requires the contractor to develop and include a PWS for each sample task. Is it the Government’s intention to include this PWS as part of the limit of 25 pages per sample task order response? |
If yes, can we make tables of the SOO/PWS and the SDS and have those tables excluded from the page limit?
| The government is commited to its page limits. Offerors can make tables; however, they are not excluded from page limitations. |
| N/C |
| 55 |
| Section M / 1.3.3 / page 71 |
M.1.3.3 Subfactor 3 - Transition Planning: Under this factor, the Government will evaluate the Offeror’s approach to providing sound business processes, processes, and expertise in transitioning to the SITEC Specialty Services contract and service delivery environment.
The words “sound business processes” are followed by the word “processes.” Is something missing? Please clarify.
| The second “processes” has been deleted. |
| RFP has been revised. |
| 56 |
| Contract Clauses |
| Does the U.S. Government have a Status of Forces Agreement (SOFA) with the Philippines? Will SOFA protection be granted to Contractor and Subcontractor personnel? |
| The US Government does not have a SOFA with the Philippines for US personnel stationed in the Philippines, SOFA protection will not be granted to Contractor/Subcontractor personnel. |
| N/C |
| 57 |
| Contract Clauses |
| Request addition of DFAR 252.225-7043 Antiterrorism/Force Protection Policy for Defense Contractors Outside the United States. |
| The clause is already included in the contract. See sections H and I. |
| N/C |
| 58 |
| RFP Section B. |
| There appear to be no CLINs for travel or ODCs. How will contractors invoice these items? |
| There will be no ODCs on this contract and travel will be included in the CPFF CLINs or in the offerors fixed prices for task orders issued on a FFP basis. |
| N/C |
| 59 |
| RFP Section L, Pages 67, 68, and 69. |
| Page 67 Task Order Cost/Price states “Offerors shall submit supporting information required to evaluate prices;” Page 68 includes FAR 52.215-20 Alt IV, indicating that cost and pricing data is not required; and Page 68 contains clause 5652.215-9010 Cost and Pricing Data Not Required. Are we correct in assuming that the Government does not require pricing detail, i.e. direct labor and indirect rate breakouts, from subcontractors at this time? |
| The Government is requesting other than cost and pricing data as defined by the FAR. Offeror’s should provide sufficient data to allow the government to complete a cost realism analysis on the proposed costs, at a minimum the Government will require labor hours and rates by category, overhead rates, G&A rates and proposed profit. |
| N/C |
| 60 |
| H92222-10-R-0044, Attachment 10, paragraph 5.0, CDRLS. |
Attachment 7, CDRL Master Set Background: Atachment 10, 5.0 REPORTS (CDRLs). CDRLs E001, E002, E003, E004, E005, E008, E009, E010, E013, E014, and E022 apply to this SOO.
Attachment 7, CDRL Master Set, only lists CDRLs E001 through E0012; E0013 through E0022 are missing.
Question: Could the Government please provide CDRLs E0013 through E0022?
| References to CDRLs E013, E014, and E022 have been removed from Attachment 10. |
| SOCPAC SOO has been revised. |
| 61 |
| RFP, Section L, page 66, Volume IV – Task Order Management and Performance Work Statement; |
Attachment 11, Q&A, Question #5 response.
Background: The page allocation states, "25 pages per task order ITO", confirmed by the response to quesiton #5 in Attachment 11. However, especially for Task Order 3, Attachment 10. Responding to "IV-A – Task Order Management" and "IV-B – Performance Work Statement" in 25 pages is not feasible. It will be especially difficult to develop a proper PWS for Task Order 3, "HEADQUARTERS SPECIAL OPERATIONS COMMAND-PACIFIC (SOCPAC) & JOINT SPECIAL OPERATIONS TASK FORCE-PHILIPPINES (JSOTF-P)" that is 22 pages single spaced in that the PWS is to be 1 1/2 line spacing.
Question: Will the Government consider expanding the page limit for contractor responses to Task Order 3 (Attachment 10) or, alternatively, can the PWS be submitted with single line-spacing?
| The government is committed to its page limitations, |
| N/C |
| 62 |
| RFP Attachments 8, 9, 10 |
| Background: To allow for more accurate estimate of man power/staffing required to support each task order basis of estimate for both Volume IV.A and Volume V responses sufficient data is not available. The data needed is: Historical Labor Requirements, WBS, Locations, and equipment supported for EITC Task Orders #859, #929 and #920. The EITC TOs are listed in RFP Attachments 8, 9 and 10, as follows: |
- Attachment 8: Historical Labor Requirements: This requirement was currently being accomplished via EITC Task Order #859.
- Attachment 9: Historical Labor Requirements: This requirement was currently being accomplished via EITC Task Order #929.
- Attachment 10. Historical Labor Requirements: This requirement was currently being accomplished via EITC Task Order #920.
Question: Could the Government provide the following data for EITC Task Orders #859, #929. and #920? This data is required to support each task order basis of estimate for both Volume IV.A and Volume V responses.
(1) Historical Labor Requirements, (2) WBS, (3) Locations, and (4) equipment supported with asset details (to include type, quantities, make and model to allow for more accurate estimate of man power/staffing).
| Current EITC task orders have been posted to the Bidder’s Library. |
| N/C |
| 63 |
| Volume IV, RFP Attachments 8, 9, 10 |
Volume II, Key Personnel (II.B), RFP, Section L, page 64 0f 74.
Background: Each of the Task Orders state that, "All positions in support of this Task Order are considered key positions. As such, contractor shall submit resumes for all new and replacement candidates proposed." We have estimated that 97 Key Personnel resumes are required (based on the Attachment 8. 9 and 10 Material Paragraphs, e.g., in Attachment 8 "7.0 MATERIAL. The Government will provide necessary materials to complete this Task Order. The government shall provide necessary office space for up to 14 contractor personnel".)
The Section II.B Key Personnel Resumes are limited to 2-pages each and are included in page count for Volume II.
Question: Are the resumes for the approximately 97 Volume IV Key Personnel included in Volume IV page count, or can the Task Order Key Personnel resumes be included as an attachment to Volume IV and be outside of the 25 page allocation for each ITO response.
| See question 14 response. |
| See question 14 action. |
| 64 |
| Volume IV, RFP Attachments 8, 9, 10 (e.g., for Task Order 3, Attachment 10: "10.0 PERSONNEL. All positions in support of this Task Order are considered key positions. As such, contractor shall submit resumes for all new and replacement candidates proposed." |
| Background: Without details of the incumbent Task Order Personnel positions and job discriptions, to include required qualifications; the incumbent contractor has an unfair advantage over other bidders. |
Question: Will the Government provide Task Order Personnel positions and job discriptions, to include required qualifications to allow bidders to provide compliant responses.
| Current EITC task orders have been posted to the Bidder’s Library. |
| Current EITC task orders have been posted to the Bidder’s Library. |
| 65 |
| RFP Attachment 11, Q&A, page 20, Question 92; 5652.237-9001 Key Personnel Requirements paragraph c), page 52 and 54 of 74 |
| Background: The response to question 92 states that, "The Office Chief has been removed from the clause. …." |
5652.237-9001 Key Personnel Requirements paragraph c) includes "Office Chiefs for USSOCOM Tampa, JSOC and TSOCs".
Question: Please clarify if the Office Chiefs will be removed from the RFP in an amendment to the RFP.
| The Office Chief position now has been removed. |
| Will be revised in subsequent modification to RFP. |
| 66 |
| RFP, Attachment 10, paragraph 3.12, (page 18); and DD-254 block10.a (page 27) |
| The Attachment 10 DD254 states in Block 10.a "COMSEC – NO"; Attachment 10, paragraph 3.12 requires COMSEC. |
Question: Please clarify if COMSEC should be noted as "Yes".
| Although Contractor will be maintaining COMSEC material on behalf of the government, they are not required to have a COMSEC Account |
| N/C |
| 67 |
| H/952.225-0011/pg. 16 |
| Government Furnished Contractor Support states: The following is a summary of the type of support the Government will provide the contractor, on an “as-available” basis. In the event of any discrepancy between this summary and the description of services in the Statement of Work, this clause will take precedence. The clause reflects “none” of the support items. |
Question: For contractor support to deployed/hazardous locations where medical/resuscitative care, meals and billeting are not readily available, what are the expectations for deployed contractor staff?
| Government provided support is described in Section H clause 952.225-0011 |
| See question 12 action. |
| 68 |
| Section H, 952.225-0003 (d)/pg. 15 and Attachment 10 SOCPAC and JSOTF-P |
| Section G states that routine and primary medical care is not authorized. For the SOCPAC and JSOTF-P task order, will contractor personnel that are deployed to the Philippines have access to routine medical care via Government facilities, or is it anticipated that contractor personnel will rely on the local economy for these needs? |
| Routine and Primary medical care is NOT provided or available via government facilities. Government provided support is described in Section H clause 952.225-0011. |
| N/C, see question 12 action. |
| 69 |
| Section I, 5652.237.9001 - Key Personnel Requirements/ pg. 52 of 74 |
| This section defines Key Personnel as the Program Manager; Assistant / Deputy Program Manager; and Office Chiefs for USSOCOM Tampa, JSOC, and TSOCs. However, Attachment 11, Questions and Answers, November 12, 2010, Response to Questions 91 and 92 reference that the Office Chief has been deleted from the RFP. |
Can the government please clarify the Key Personnel Requirements?
| The Office Chief position now has been removed.. |
| This has been revised in the RFP and will be included in a subsequent modification. |
| 70 |
| Attachments 8, 9, and 10 ITOs |
| The RFP provides approximate dollar estimates for annual travel for each of the three task orders. Is it the Government’s intention to use these dollar estimates as plug numbers for travel, or does the Government anticipate Offerors to submit cost builds for travel? If cost builds are desired, please provide for each task order the estimated number of annual trips, number of persons per trip, number of days per trip, and locations. |
| The travel estimates were provided for historical information purposes only. The offerors are expected to include their travel estimate for permanent proposed personnel and surge travel based on their proposed approach consistent with their accounting practices. The Government estimates 3 surge trips per task order. |
| N/C |
| 71 |
| Attachments 8, 9, and 10 |
| For estimating purposes, will the Government please provide the average number of personnel deployed OCONUS at any given time and the average deployment duration for each of the three task orders? |
| Atch 8 – Est 2 contractors deployed at any one time for an average length of 120 days. |
Atch 9 & 10 – No historical information is available.
N/C
| 72 |
| Attachments 8, 9, and 10 |
| For transition purposes, will the Government provide the number of staff currently deployed in OCONUS and hazardous duty locations under the three existing EITC task orders? |
| Atch 8 – Currently 1 deployed |
Atch 9 & 10 – No historical information is available.
N/C
| 73 |
| Attachments 8, 9, and 10 |
| Each ITO references an existing EITC task order number for historical labor requirements, yet the task orders were not provided with the procurement files and do not appear to be included in the bidder’s library. Was it the government’s intent to provide these task orders and, if so, how can we obtain them? |
| Current applicable EITC task orders have been posted in the Bidder’s Library. |
| N/C |
| 74 |
| Attachment 9 |
| Will housing be provided as GFE for OCONUS deployed personnel? |
| See question 12 response. |
| See question 12 action. |
| 75 |
| Attachment 10 SOO Paragraph 8.0 |
| The SOO states, “The Contractor shall coordinate all movement of equipment and contractor personnel between the various JSOTF-P sites and other destinations.” Is the Contractor’s role for this requirement limited to logistics coordination, or does this requirement include procurement of associated transportation/shipment materials and services to be direct charged to the contract? |
| Contractor’s roll is limited to logistics coordination. There is no CLIN available on this contract for offeror to be reimbursed for materials. |
| N/C |
| 76 |
| Attachment 10 Paragraph 1.0 |
| The SOO states services include “Other Overseas Contingency Operations” besides SOCPAC and JSOTF –P. Does the government want this addressed in management approach and/or technical approach or, should we limit response to SOCPAC and JSOTFP. If so, does the government wish to provide a notional scope/location for a basis of comparison? |
| Offerors responses shall be limited to SOCPAC garrison and JSOTF-P support. |
| N/C |
| 77 |
| Attachment 10 Para 3.1.6 states |
| “All Contractors shall fall under the provisions of the Information Assurance Workforce Improvement Program (DoD 8570) and must possess the required Information Assurance (IA) baseline certifications commensurate with their assigned duty position as determined by the government. (EX; IAT II, IAT III, IAM III, CND-SP, etc.)” In order to develop an appropriate staffing plan and adequately prepare for contract transition, request the government provide a detailed listing of the duty positions associated with this task order and their required DoD 8570 certifications. |
| Proposals need to present staffing plan and propose DoDI 8570 certification requirements for gov’t approval. |
| N/C |
| 78 |
| Attachment 10 Para 3.3.13 |
| How many users, applications, servers, desk top computers, lap top computers, printers, and peripheral devices does the Help Desk support for each network that the contractor will be required to operate and maintain in support of this effort? |
| All available information for this task is included in the Bidder’s Library. |
| N/C |
| 79 |
| Attachment 10 Para 3.5.10 (Interbase Connectivity) |
| Is the design of future communications architecture in this paragraph intended for future locations only other than SOCPAC HQ and JSOTF_P? Are there any additional locations in Japan or Guam that are currently supported? |
| No, include architecture support at SOCPAC HQ and JSOTF-P. |
| N/C |
| 80 |
| Attachment 10 Para 7.2 (Materials) – |
| The SOO states the government will provide necessary “documentation” for the contractor to accomplish tasks as needed. Will this include protection under the Visiting Forces agreement between the government of the Philippines and the US (analogous to SOFA)? |
| VFA does apply to contractors performing duties in the Philippines. |
| N/C |
| 81 |
| Attachment 9 |
| GFE is provided for a maximum of 32 contractors. How many of the 32 will be at MacDill AFB and how many at CFSOCC? |
| This will be based on individual proposals. |
| N/C |
| 82 |
| Attachment 9 |
| 3.6 OCONUS Transition Plan. Can the government specify whose rotation schedule is referenced (e.g. all, military surges, contractor team, other)? |
| For OCONUS contractors at CFSOCC. |
| N/C |
| 83 |
| Attachment 11 – Questions and Answers, November 12, 2010: Question 5. (2) Section L.2 Proposal Submission Requirements, Volume II – Past Performance Information/pg. 64 |
| Question number 5 states the Past Performance Volume is limited to 50 pages. Section L.2, pg. 64 states the Past Performance Volume is limited to 30 pages. We believe the correct limit is 50 pages based on the volume contents – Table of Contents (1 page), Summary of Roles (1-2 pages), Past Performance Citation Sheets (5 x 5 = 25 pages), and SF 294/295s (5 x 4 = 20 pages). Please clarify the page limit. |
| Vol III limit is 30 pages, see question 15 response. SF 294/295s so not count against page limits |
| See question 15 action. |
| 84 |
| Section H/Reference 952.225-0011/pg. 16 |
| Government Furnished Contractor Support states: The following is a summary of the type of support the Government will provide the contractor, on an “as-available” basis. In the event of any discrepancy between this summary and the description of services in the Statement of Work, this clause will take precedence. The clause reflects “none” of the support items. |
Question: For contractor support to deployed/hazardous locations where medical/resuscitative care, meals and billeting are not readily available, what are the expectations for deployed contractor staff?
| Government provided support is described in Section H clause 952.225-0011 |
| See question 12 action. |
| 85 |
| Section L.1/Crosswalk/ Pages 61 & 62 |
| “Section L, Volume 1 – Responsibility Criteria/Section M, M1.3 – Responsibility Criteria Overview”; There appears to be an error in the Section L/M Crosswalk, “Section L” is linked to “Section M.1.3 FACTOR 1 – Technical/Management.” Can the Government please correct this reference? |
| Section L has been revised for clarity. |
| Section L& M revised. |
| 86 |
| Section M/M.1.2/Page 70 |
| Was it the Government’s intention to exclude Volume 1 – Responsibility Criteria as an Evaluation Factor? |
| Yes, the Federal Acquisition Reg defines the requirements for determining responsibility. The language was removed to reduce redundancy and ensure the RFP does not conflict with FAR requirements. |
| N/C |
| 87 |
| Section L.1/Crosswalk/ Page 61 |
| The Section L/M Crosswalk references Section I-D as “Adequate Accounting System” while on Page 63 Section I-D is referenced as “Adequate Business Systems.” Can the Government please correct this to say “Adequate Business Systems?” |
| Adequate business systems is correct. |
| Section L revised. |
| 88 |
| L.2, Page 64; M.1.1 Page 70, M.1.2 Page 70, M.1.3 Pages 71 & 72 and Question 96 |
| These sections still reference a “Technical/Management” approach. Should this be changed to “Program Management” as in the answer to Question 96? |
| This amendment has corrected the administrative error. |
| Revised to state Program Management. |
| 89 |
| L.1/Formats/Page 62 |
| RFP states “Font size shall be Times New Roman or Arial, in no smaller than 10 point for text Spreadsheets, tables, and graphics…” Will the Government consider a font size of 8 point for graphics? This is consistent with previous SITEC RFPS and allows for more meaningful graphics presentations. |
| No, some offerors have already abused this allowance and written significant portions of their SITEC proposals as tables which rendered them nearly illegible. |
| N/C |
| 90 |
| L.1/Formats/Page 62 |
| RFP states “Font size shall be Times New Roman or Arial, in no smaller than 10 point for text Spreadsheets, tables, and graphics.” Will the Government consider a font size of 8 point for text Spreadsheets and tables? This is consistent with previous SITEC RFPS. |
| No, some offerors have already abused this allowance and written significant portions of their SITEC proposals as tables which rendered them nearly illegible. |
| N/C |
| 91 |
| Question 77 |
| Government response “Volume IV limit is 25 pages per ITO” however, the government did not address the 2-page resumes be excluded from the total volume page count. Will you please exclude the TO resumes from the TO page count? |
| The government is committed to its page limitations. However, 2 pages per each resume will not count towards the page limit. |
| Section L revised. |
| 92 |
| Question 91 (Attachment 11) and RFP Page 52 |
| In the Government response to question 91 states, “Office Chief has been removed from the RFP,” yet they still in the final RFP (Page 52). Will the government please remove the reference to Office Chiefs? |
| The Office Chief position now has been removed. |
| This has been revised and will be included in modification. |
RFP G/ G.4 / Page 10
Attachment 11, Questions and Answers /Questions 40, 70, 145 / (unpaged)
| CLIN 1003, Cost Reimbursable Travel, which was in the DRFP, is not in the final RFP. This is not consistent with the answers to the cited questions or Clause G.4 (for CPFF Task Orders). Will the Government consider providing a CLIN that permits invoicing for Cost Reimbursements without fee? |
| The CLIN 1003 reference has been removed. |
| CLIN 1003 reference remove from G4 and CPFF TOs mentioned. |
| 94 |
| RFP F / Delivery Information / Page 7, RFP L / L1.5 / Page 61 Attachment 1, PWS / 5.7.1 / Page 22 |
Attachment 1, PWS / 5.7.1.1 / Page 22
| The Period of Performance begins before proposals are due. Will the Government consider changing the POP to reflect the contract award date of March 1, 2011 and make consistent throughout H, L, M and the PWS? |
| See question 18 response. |
| See question 18 action. |
| 95 |
| RFP L / L1.5 (Section L to Section M Crosswalk Table) / Pages 61 and 62 RFP L / L.2 / Pages 63-67 RFP M / all / Pages 70-74 |
| The Section L to Section M Crosswalk table does not correspond to the factors or numbers in Sections L.2 and M. Will the Government please correct this table to reflect the proper cross references between L and M? |
| The RFP has been revised to correct the administrative error. |
| Section L & M revised. |
| 96 |
| RFP L / L.2 IV-A/Page 67 |
| Will the Government please change the reference to the “SOW” to the “ITO?” |
| SOW has been changed to SOO. |
| Revised Section L. |
| 97 |
| Attachment 1, PWS / 1.0 Paragraphs 7 and 8 / Page 4 |
| Will the Government please change the 4 instances of reference to the “SOW” to “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 98 |
| Attachment 1, PWS / 1.1 / Page 4 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 99 |
| Attachment 1, PWS / 3.1 / Page 7 |
| Will the Government please change the 2 instances of reference to the “SOW” to “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 100 |
| Attachment 1, PWS / 5.0 / Page 9 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 101 |
| Attachment 1, PWS / 5.1 / Page 9 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 102 |
| Attachment 1, PWS / 5.1.2 / Page 13 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 103 |
| Attachment 1, PWS / 5.1.3 / Page 14 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 104 |
| Attachment 1, PWS / 5.1.4 / Page 15 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 105 |
| Attachment 1, PWS / 5.1.5 / Page 16 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 106 |
| Attachment 1, PWS / 5.2.1 / Page 17 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW have been revised to PWS. |
| SOO has been revised. |
| 107 |
| Attachment 1, PWS / 5.5 / Page 21 |
| Will the Government please change the reference to the “SOW” to the “PWS?” |
| References to SOW has been revised to PWS. |
| SOO has been revised. |
| 108 |
| Attachment 1, PWS / 3.2 / Pages 7 & 8 |
| Will the Government modify this sentence, “Hiring of Contractor personnel with the requisite security clearances shall be coordinated with and approved by the Contracting Officer (COR) and Primary COR (PCOR),” so that it reads, “Hiring of Contractor personnel with the requisite security clearances shall be coordinated with and approved by the Contracting Officer Representative (COR) and/or PE leadership?” |
| Verbiage is correct as directed by Industrial Security Officer. |
| N/C |
| 109 |
| Attachment 1, PWS / 3.5-3.8 / Pages 8 & 9 |
| The title for the “Security and Classification” paragraph has been deleted. The requirement remains as the second paragraph of section 3.5. Will the Government re-insert the title and renumber the remaining paragraphs in section 3? |
| Paragraph title has been inserted |
| PWS updated with title and paragraph numbering revised. |
| 110 |
| Attachment 1, PWS / 5.3 / Page 17 Attachment 1, PWS / 5.6 / Page 21 |
| Will the Government please change the reference to “Section 5.5 Reporting Requirements” to “Section 5.6 Monthly Report Requirements?” |
| Corrected |
| PWS has been updated with corrected reference. |
| 111 |
| Attachment 2 SLAs / Introduction / (unpaged), Question 71 (Attachment 11) |
| The introduction references Appendix A and option years. No Appendix A is included and the Specialty Services RFP does not have option year POPs. For consistency, will the Government please remove the references to Appendix A and contract incentives from the Introduction of Attachment 2? |
| POP has been deleted from reference. |
| Atch 10 has been revised and will be included in modification |
| 112 |
| Attachment 2SLAs / Performance Incentive Calculation / (unpaged) |
| The Performance Incentive Calculation section does not seem to apply to the Specialty Services RFP (no CLIN permitting performance incentives is requested). It also references Appendices A and B, which are not included. For consistency, will the Government please remove this section? |
| References to Appendices A & B have been deleted. |
| Revised Atch 10. Include in modification. |