1800F Headquarters Renovation Project - Industry Outreach Presentation
This document is a GSA industry outreach presentation for the 1800F Headquarters Renovation Project, delivered on June 2, 2026. The presentation outlines a comprehensive modernization initiative to revitalize the historic 1800 F Street building in Washington, D.C., which has served as GSA headquarters since 1949. The project aims to transform the facility into a future-ready, adaptable workplace serving both GSA and the Office of Personnel Management, with a hard deadline for occupancy by December 2028.
The project scope encompasses three major work components: Core & Shell (100% design complete, priced as firm-fixed-price Early Work Package), Interior finishes (~50% design complete, priced as guaranteed maximum price), and Exterior upgrades (~35% design complete, also priced as guaranteed maximum price). The estimated construction magnitude is $275 million to $325 million. GSA will use a two-phase solicitation process with a Request for Qualifications (RFQ) issued July 2026, followed by a Request for Proposal (RFP) in October 2026, with contract award targeted for January 2027. The delivery method is Construction Manager as Constructor (CMc) under a fixed-price incentive contract structure (FAR 16.404), with the CMc providing design-phase advisory services under FFP and serving as general contractor during construction under GMP terms. Small business subcontracting goals include 24% small business participation, with additional targets of 5% for small disadvantaged businesses, women-owned small businesses, and service-disabled veteran-owned small businesses, plus 3% HUBZone participation. The project encompasses furniture solutions emphasizing flexibility and technology integration, building systems modernization, and a vision centered on hospitality-grade design, activity-based workspaces, human-centered design with biophilic elements, smart building integration with open architecture (no proprietary systems), and seamless employee experience from building entry through workspace utilization.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
June 2, 2026
1800F Reimagined Industry Outreach
Welcome to 1800F Greg Justice, Associate Administrator, Office of Small Business
Opening Remarks Ed Forst, GSA Administrator
David Shive, GSA Chief Information Officer
Andrew Heller, Acting PBS Commissioner
Today’s Agenda
Industry Presentations
● Project Overview - Hallie Futterman, Project Executive
● Acquisition Overview - James Adamo, Director, Office of Acquisition, Capital Construction Division
● Furniture Overview - Dana Wichman, Senior Interior Designer & Furniture POC/COR
● Technology Overview - Sandy Shadchehr, Director of Building Technologies Management Division
Q&A
Networking
Project Overview Hallie Futterman, Project Executive
1800F Headquarters Renovation Project 8
1800 F History
Building designed as offices for the U.S. Department of the Interior
Construction completed;
building opens for use by the
Dept. of the Interior 1917 Building becomes the headquarters for the U.S. General
Services Administration
(GSA)
Significant modernization and upgrade undertaken
2012-2013 1800 F Phase 1
1800 F Revitalization
111 Years Later TODAY
1800F Headquarters Renovation Project 9
Revitalization
1800F Headquarters Renovation Project
The objective of 1800 F is to create a future-ready, adaptable, and mission-aligned headquarters that serves as both a high-performing workplace and a civic destination, setting a new standard for federal facilities.
1800 F Revitalization
1800F Headquarters Renovation Project 11
Project Scope Wings 0 and 3: Undergoing a full renovation featuring new furnishings, updated finishes, and improved building systems.
Specialized Areas: The auditorium and library will be renovated with enhanced seating and audiovisual equipment; the fitness center will receive upgrades, including locker rooms and shower facilities.
System Upgrades: Elevators will be modernized; historic windows and cast-iron elements will be restored; roofs and plumbing will be replaced; fire safety systems will be expanded; telecommunications will be improved; and the building envelope will be refurbished.
New West Infill: A proposed infill between Wings 2 and 3 aims to add office space and a glass atrium.
Wings Refresh: Wings 1 and 2, along with the East Infill, will be updated to align with the overall construction, creating a cohesive interior throughout the building.
Courtyards: Transform courtyards into versatile spaces that integrate parking, building amenities, and innovative workspaces.
Wing 0
Wing 1Wing 3
East Infill
Wing 2
East Courtyard
New West Infill
West Courtyard
1800F Headquarters Renovation Project 12
Scope Elements
INTERIOR
DESIGN
CORE & SHELL
DESIGN
EARLY DEMO
WORK
COURTYARDS
DESIGN
DIDsCDsIn Progress DIDs
1800F Headquarters Renovation Project 13
Design Ideas for Workspaces
1800F Headquarters Renovation Project 14
Design Ideas for Amenities
1800F Headquarters Renovation Project 15
Design Ideas for Activating the Courtyards
1800F Headquarters Renovation Project 16
Project Roadmap
1800F Headquarters Renovation Project 17
Hallie Futterman, AIA, LEED AP Project Executive Capital Projects East Division
Office of Program and Project Management (OPPM) Public Buildings Service
Acquisitions Jim Adamo, Director, Office of Acquisition, Capital Construction Division
GSA Headquarters Revitalization
Current Occupancy
GSA
PBS & FAS
Future Occupancy
GSA & Office of Personnel Management
Modernization Objectives
Performance improvements and multi-tenant use optimization
1800F Headquarters Renovation Project 20
Acquisition Strategy
TWO-PHASE SOLICITATION
Phase I: Request for Qualifications
(RFQ)
Phase II: Request for Proposal
(RFP)
• Down Select to Phase II
• Best Value Trade Off Award Decision
ESTIMATED MAGNITUDE
$275M - $325M Estimated Magnitude of Construction
DELIVERY METHOD & STANDARDS
• Construction Manager as Constructor (CMc)
• Cost Accounting Standards
(CAS)
Key Project Milestones and Deadlines
Procurement Timeline
JUL 2026
RFQ DATE
Official Solicitation Issuance
OCT 2026
RFP DATE
JAN 2027
AWARD
DEC 2028
OCCUPANCY
Scheduled Project Award Date
Hard deadline for
GSA & OPM
Total duration
Up to 24 months
CONCURRENT ACTIVITIES
• A separate demolition and abatement contract will be ongoing, scheduled for completion by March 2027.
• A separate relocation contract for building tenants is currently ongoing and expected to be completed by August 2026.
1800F Headquarters Renovation Project 22
Three Main Components of Work Project Scope and Design Status Overview
WORK COMPONENT DETAILS
SCOPE
DESIGN
STATUS
PRICING
TYPE
Core & Shell (Early Work Package) 100% FFP
Interior ~50% GMP
Exterior ~35% GMP
1800F Headquarters Renovation Project 23
The CMc Delivery Method
The Construction Manager as Constructor (CMc) Delivery Method is a Fixed-Price Incentive Contract (FAR 16.404). The CMc Contractor provides advisory management services before construction and acts as a general contractor during construction.
"The CMc provides advisory professional management assistance to the owner during planning and design."
Contract Type:
• Firm-Fixed-Price (FFP)
• Services include constructability, cost estimating, and scheduling.
"The CMc acts as a general contractor during construction.“
Contract Type:
• Guaranteed Maximum Price (GMP)
• Responsible for construction options following design completion.
1. Design Phase (Base) 2. Construction Phase (Option)
CMc services are solicited during the design phase (roughly concept design) for FFP Design Phase Services and a GMP Construction Option(s). During performance of the Design Phase Services, the CMc Contractor advises the owner and the Architect-Engineer (A/E) on:
The CMc Delivery Method – Design Phase
Constructability Work Phasing & Sequencing Systems Analysis
Involvement of Trades Cost Reconciliation Market Analysis
Risk Assessments Cost Estimating Scheduling
1800F Headquarters Renovation Project 25
The CMc Delivery Method – Construction Phase
Initial GMP Option Price (Target)
Given that the CMc contractor is hired before the design is complete, the need to have a price within the available budget is met by the CMc contractor guaranteeing a maximum price (GMP), which is a ceiling on the eventual construction price.
Final GMP Option Price (Final)
At approximately 75% design, GSA requests a final GMP option price for construction.
Constraint: The Initial GMP can go down, but not up (unless there is additional scope added to the project).
1800F Headquarters Renovation Project 26
Early Work Package - Core and Shell
What is an Early Work Package?
An “Early Work Package” is a set of construction activities that can be clearly defined and separately performed from the remainder of the construction work.
Core and Shell Specifics
● Priced separately as a firm-fixed-price contract line item.
● Included in the award as an Early Work Package.
1800F Headquarters Renovation Project 27
Sample CMc Pricing Table
CLIN ITEM DESCRIPTION PRICE / VALUE
1 Design Phase Services (Firm Fixed Price) $ ___________
2 Target Estimated Cost of Work (ECW) $ ___________
3 CMc Contingency Allowance (CCA) Percentage ____3______ %
4 CCA (2x3) $ ___________
5 Fee Percentage __________ %
6 Fee (2x5) $ ___________
7 Guaranteed Maximum Price (GMP) Option (2+4+6) $ _________
8 Total Evaluated Price (1+7) $ _________
1800F Headquarters Renovation Project 28
GSA CMc Pricing Structure
Estimated Cost of the Work (ECW) The estimated cost of construction activities, excluding home office overhead.
Fee for the Construction Work The established amount for the contractor's profit and home office overhead.
CMc Contingency Allowance (CCA) Reimbursable costs for the contractor's exclusive use during construction (e.g., estimating errors). Not for change orders.
Guaranteed Maximum Price (GMP) The sum of the ECW, CCA, and the Fee for the construction work.
Furniture Solutions for 1800F Dana Wichman, Senior Interior Designer & Furniture POC/COR
1800F Headquarters Renovation Project 30
Design Ideas for Workspaces
In 15 years the next generation of federal employees will work differently again. We need furniture that evolves with them — not furniture we have to replace.
The Federal Workforce Has Changed
• Assigned workstations
• Private offices as status
• Scheduled meetings only
• One size fits all
• Paper-heavy workflows
15 Years Ago
• Fluid & fully flexible
• Strategically embedded technology
• Spaces that sense & adapt
• Wellbeing as a design mandate
• Furniture that knows the worker
In 15 Years Ago
• A different way of working - Employees distributed nationwide across multiple time zones - virtual back-to-back meetings all day
• Workstations are small, dense, and not suited for RTO efforts
• Technology is fragmented, resulting in missed integration opportunities
• One-size-fits-all environment with limited flexibility
• Furniture at the end of its lifecycle
Today
The Furniture Hasn't – Until Now.
1800F Headquarters Renovation Project 32
1800 F Vision
Furniture as Workhorse
Hardworking, purpose-built solutions for real user needs. Reliable, functional, built to perform every single day.
Flexible & Adaptive Systems
Reconfigurable furniture that moves with the mission. One space, many uses — from solo focus to team collaboration in minutes.
Bespoke Finishes & Hospitality
Breaking the federal mold. Residential warmth, hospitality character, timeless materials — spaces people are proud to work in.
Designed for Every Worker
Neurodiversity, reasonable accommodations, and all work styles built into the palette from the start.
Resilient & Serviceable Systems
Kit-of-parts construction: repair the component, not the whole piece. Built for the long federal lifecycle.
Technology Forward Integration
Furniture that accommodates emerging technology as it evolves — infrastructure built in, not bolted on.
1800F Headquarters Renovation Project 33
Beyond the workstation. Every space is a furniture opportunity.
Individual Work
Ergonomic · adjustable personalized
Team Collaboration
Reconfigurable · tech-enabled
Café & Social
Hospitality-grade · relaxed & inviting
Outdoor & Canopy
Seating, shade components · durable finishes
Soft Seating & Lounge
Biophilic · textured · residential feel
Meeting & Convening
All scales — 1:1 to all-hands
Wellbeing Zones
Quiet · restorative focused
Amenity & Art
Rugs · Art · Accessories
The unexpected details
We are not here for a catalog walkthrough. We want to talk innovation, hurdles, and what we can build together.
Let's solve the hard problems together.
Schedule innovation time
Not sales calls — real conversations. Bring R&D, product teams, thinkers. Show us what's next and what you'd do if we said yes to everything.
Co-develop solutions
From RA-integrated kit-of-parts to FSS-ready neurodiverse settings — let's prototype together before procurement begins.
Tell us your hurdles
Where does federal procurement slow innovation? What specs make the right solution impossible? Let's name them and fix them together.
Commit to the lifecycle
Future parts availability, service commitments, finish replication. We need partners who stand behind the full federal lifecycle.
Bring your boldest work
Not the catalog standards — what you'd do with full creative latitude. We want to see your vision.
Be the playbook
What we build at 1800 F travels. Your work here carries the GSA seal and becomes the model agencies nationwide will follow.
Technology Sandy Schadchehr, Director of Building Technologies
Management Division
Partnership & Requirements
Strategic Context
GSA has conducted numerous pilots in workspace design and technology.
We know what we want; we need partners for rapid implementation.
The Reality:
No one vendor can do it all.
What We Want
● Holistic, integrated solutions over one-off software/hardware.
● Proven, interoperable, and scalable technology.
● Open protocols—strictly nothing proprietary.
● Future-proof investments, not "shiny" short-term tech.
● Seamless user journey from entry to workstation.
● Tech that is present but unobtrusive.
Security & Constraints
What we are NOT looking for:
● Testing new, unproven technology.
Cybersecurity
● Must be well-versed in FedRAMP and ATO requirements at GSA.
1800F Headquarters Renovation Project 37
Future Proofing
Transforming 1800F into a flagship federal workplace that competes with the best private sector designs while showcasing what's possible in government buildings.
1800 F: Government's Flagship Workplace
THREE BIG SHIFTS
Hospitality-Grade High-end hotel lobby meets secure facility.
Activity-Based Focus zones, collaboration, and video pods.
Integrated Tech Smart systems that adapt to people.
THE VISION
From Institutional to Inspirational
Current: Sterile, cold, typical gov building.
Future: Alive, warm, human-centered, high performance.
"An employee walks in and immediately feels the difference - natural light, living walls, and varied textures."
1800F Headquarters Renovation Project 39
3 Main Themes
Human-Centered Design
● Move from "institutional" to "hospitality-grade"
● Biophilic design (living walls, natural materials, circadian lighting)
● Address #1 workplace complaint: poor acoustics
Smart Building Integration
● Open architecture
● No proprietary systems
● Real-time occupancy and environmental sensing
● Network that easily accommodates visiting agencies
● BIM model becomes operational tool
Activity-Based Everything
● Spaces designed for specific work types
● Flexible, reconfigurable furniture and layouts
● Technology embedded in the environment, not added on
1800F Headquarters Renovation Project 40
Vision: Technology as an Invisible Enabler
Employee Journey
Building Entry & Flow
● PACS frictionless building experience
● Smart reservation system
● Auto-activating workstations
● Wayfinding
● Open to public
● Retail space
Workspace Intelligence
● Tech-agnostic, plug-and-play
● Real-time space availability
● Activity-based seating
Infrastructure Smart Integration
Building Intelligence
● Unified tech dashboard
● Environmental & occupancy data
● Real-time analytics
● Open vendor architecture
● Unified systems platform
● Digital signage for behavioral change
● Controls as a Service (CaaS)
Network Foundation
● Redesigned RIC and TRs
● Redesigned Infrastructure
● Unified SD-WAN architecture
● Secure logical segmentation
● Hardware as a Service
(HaaS)
● Shared network with other agencies/OPM
● Public network
● Security Assessment Lab
Collaboration
● Seamless VTC everywhere
● Laptop integration
● Instant room scheduling
● Seamless collaboration with other tenants
Outcome: A workplace that anticipates needs, adapts to preferences, and enhances productivity—making GSA a model for smart government buildings.
Core Principle: Immersive Technology Experience: IT infrastructure that enables seamless work without being intrusive.
1800F Headquarters Renovation Project 41
Next Steps
Teaming Agreements
Evaluate your ability to provide an end to end solution
Data Security Assessment of how you secure the data
Lifetime Security Covers all solutions provided over their lifecycle
Interoperability Seamless integration of the solutions provided
Small Business Greg Justice, Associate Administrator, Office of Small Business
Subcontracting Considerations
• Subcontracting is an evaluation factor o Contracts over $900k ($2M for construction) require a subcontracting plan o All prime contractors must submit a subcontracting plan
• What GSA looks for o Meaningful small business participation o Small businesses that are prepared to perform and deliver results
• Pre-proposal conference will have additional specific details about subcontracting opportunities
GSA FY26 Small Business Goals
Category Prime Subcontracting
Small Business 33.5% 24%
Small Disadvantaged Business 5% 5%
Women-Owned Small Business 5% 5%
Service-Disabled Veteran-Owned Small Business
5% 5%
HUBZone Small Business 3% 3%
1800F Headquarters Renovation Project 44
Today is an important opportunity for potential primes and subcontractors to network.
Prime
Subcontractor
● Please keep your questions concise and preferably directed at one of the panelists.
● Questions with be gathered from virtual and in person
● In the room
○ Capture your question(s) on an index card
○ Please raise your hand and wait for the microphone before asking your question
● Any questions not addressed will be reviewed for follow up
• Hallie Futterman, Project Executive, Office of Project and Program Management
• Jim Adamo, Director, Office of Acquisition, Capital Construction Division
• Dana Wichman, Interior Designer, Project Team Design lead
• Sandy Shahchehr, Director of Building Technologies Management Division, Technology team lead
Please join us in the west lobby to continue our discussion.