Summary: 1800 Forward Construction Manager as Constructor Preproposal Conference

This document is a preproposal conference presentation for the 1800 Forward federal building revitalization project in Washington, DC, conducted by the U.S. General Services Administration (GSA). The project is a comprehensive modernization of a historic 111-year-old building to serve as a shared headquarters for GSA and the U.S. Office of Personnel Management (OPM). The solicitation number is 47PB5426R0007, issued July 23, 2026, with an RFI deadline of August 18, 2026, and Phase I proposal due date of August 28, 2026. Phase II solicitation is estimated for November 2026, with Construction Manager as Constructor (CMc) award targeted for January 2027. The estimated construction cost ranges from $275,000,000 to $325,000,000, with liquidated damages of $30,046 per day. The contract uses a Best Value evaluation approach under FAR Part 15 with a GSA Class Deviation for a two-step CMc process. All employees have been relocated to alternative locations, and early demolition/abatement of Phases 0 and 3 will be completed before the CMc contractor period begins.

Phase I evaluation factors include Key Personnel (resumes and reference questionnaires required), Past Performance (utilizing Past Performance Questionnaires), and Prior Technical Experience (federal building construction, major modernization, historic register work, projects exceeding $100 million, façade/window restoration, CMc delivery method, buildings over 300,000 square feet, and constrained urban sites). Phase II will evaluate Management and Technical Approach for design and construction phases, Small Business Utilization Plans, and Project Price Proposals. The project follows a Construction Ceiling Price at Award/Construction Firm-Fixed-Price at Option model under GSAR Individual Deviation, applying GAAP rather than CAS. A mandatory Project Labor Agreement (PLA) paired-proposal procedure requires all offerors to submit a PLA Price Proposal; non-PLA proposals are optional. The Phase II solicitation will include three design packages: Core and Shell (95% CD at solicitation, 100% CD before award), Interiors (100% DIDs at solicitation, 65% CD before award), and Courtyards (final concepts at solicitation, 100% DID before award).

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1800 Forward Construction Manager as Constructor Preproposal

August 11, 2026

Today’s Agenda

● Introductions

● Project Background

● Procurement Overview

● Design Overview

● Question and Answer

● Site Tour

Introductions

Jared Price GSA Sr. Project Manager Hallie Futterman GSA Project Executive Robert Jackson GSA Contracting Officer Oliver Chang GSA Contract Specialist David Cantrell GSA Project Manager Jason Sherrer GSA COR Jacobs Project Management CMa and CXa Partner Shalom Baranes Associates AE Partner Perkins and Will AE Partner

Project Objective

The project seeks to transform the historic building into a long-term, adaptable federal asset that will provide the opportunity for two agencies, GSA and the U.S. Office of Personnel Management (OPM), to co-locate and reimagine what is possible in a shared headquarters.

The primary objective is to complete the reimagination, enhance building performance, and ensure the space can adapt to future workforce and multi-tenant requirements. This project will set a new standard for a modern, adaptable federal workplace.

1800 F History

Building designed as offices for the U.S. Department of the Interior

Construction completed; building opens for use by the Dept. of the Interior

Building becomes the headquarters for the U.S. General Services

Administration

(GSA)

Significant modernization and upgrade undertaken

2012-2013 1800 F Phase 1

1800 F Revitalization

111 Years Later TODAY

Project Overview Wing 0

Wing 1Wing 3

East Infill

Wing 2

Wings 0 and 3: Undergoing a full renovation featuring new furnishings, updated finishes, and improved building systems.

Specialized Areas: The auditorium and library will be renovated with enhanced seating and audiovisual equipment; the fitness center will receive upgrades, including locker rooms and shower facilities.

System Upgrades: Elevators will be modernized; historic windows and cast-iron elements will be restored; roofs and plumbing will be replaced;

fire safety systems will be expanded; telecommunications will be improved; and the building envelope will be refurbished.

New West Infill: A proposed infill between Wings 2 and 3 aims to add office space and a glass atrium.

Wings Refresh: Wings 1 and 2, along with the East Infill, will be updated to align with the overall construction, creating a cohesive interior throughout the building.

Courtyards: Transform courtyards into versatile spaces that integrate parking, building amenities, and innovative workspaces.

East Courtyard

New West Infill

West Courtyard

Project Overview To facilitate the successful delivery of this project:

● All employees have been swung out to alternative locations for the duration of the project allowing work to proceed in a fully unoccupied building.

● Early demolition and abatement of wings 0 and 3 will be completed ahead of the CMc contractor period of performance allowing the work to begin from empty abated shell space.

● Three design packages to allow early construction of portions of work prior to final design completion.

○ Core and Shell, Interiors, Courtyards

Procurement Overview

Base your proposals on the Solicitation and Amendments to the solicitation as issued. Nothing said at this conference can be interpreted as a modification to this solicitation unless it is issued as a formal amendment.

Procurement Overview

● Solicitation #47PB5426R0007

● Phase 1 solicitation issued issued July 23, 2026

● Delivery Method - Construction Manager as Constructor

● Method of Award - Best Value

● Liquidated Damages - $30,046 per day

● Estimated cost of construction - $275,000,000 to $325,000,000

Procurement Schedule

● Phase I solicitation issued July 23, 2026

● RFI deadline August 18th, 2026

● Phase I proposal due date August 28th, 2026

● Phase II solicitation issued November 2026 (est)

● CMc award January 2027 (est)

Two Step CMc Solicitation

● Process in accordance with FAR Part 15 (GSA Class Deviation

RFO-2025-15)

● Offerors shall respond to the Phase I solicitation by submitting a Phase I Technical Proposal

● Offerors will be notified of their general evaluation results, including information addressing whether the offeror appears competitive or viable for Phase II.

● The results of Phase I shall not preclude Offerors from submitting a Phase II Proposal, unless an Offeror is found to be technically unacceptable

Two Step CMc Solicitation Phase I Evaluation Factors:

● Factor 1: Key Personnel

● Factor 2: Past Performance

● Factor 3: Prior Technical Experience

Phase II Evaluation Factors:

● Factor 4: Management and Technical Approach – Design Phase Services and

Construction Phase Services

● Factor 5: Small Business Utilization Plan

● Project Price Proposal

Technical factors are listed in order of descending importance by phase. For the overall best value tradeoff evaluation, Factor 4 is significantly more important than Factors 1, 2, 3, and 5.

Factor 1: Key Personnel

This factor will assess the qualifications and experience of the Offeror’s proposed Key Personnel for this project

● Project Executive

● Project Manager

● Design Assist Manager

● Superintendent

● Quality Control Manager

Each key personnel shall submit one resume and up to three Key Personnel Similar Project Experience Reference Questionnaires.

Factor 2: Past Performance This factor will assess the past performance of the Offeror on projects deemed relevant under Factor #3 Prior Technical Experience. The Offeror’s past performance information will be evaluated utilizing the completed Past Performance Questionnaire (PPQ)

The past performance evaluation may include assessment of:

● Overall quality of past performance

● Record of conforming to contract requirements

● Construction quality performance

● Adherence to contract schedules

● Responsiveness of management

● History of behavior and commitment to customer satisfaction

Factor 3: Prior Technical Experience This factor assesses the experience of the Offeror in providing services necessary for successful delivery of the 1800 Forward Project.

● Construction in or of a Federal building;

● Major (significant work across multiple building systems) building modernization;

● Work in a building on the historic register;

● Construction cost greater than $100,000,000;

● Major (at least 50% of facade and windows included) façade and window restoration;

● CMc delivery method;

● Building size greater than 300,000 square feet; and

● An urban location with a constrained site with limited laydown and work area.

Cost Accounting Standards

● GSA GSAR Individual Deviation issued for the 1800 Forward Project

● This deviation replaces the previous CMc approach with a

Construction Ceiling Price at Award / Construction Firm-Fixed-Price at Option model.

● During the design phase, the CMc collaborates with the architect-engineer contractor on constructability and cost estimating. At option exercise, the construction phase is performed at a firm-fixed price.

● As a result, this contract is firm fixed price and Generally Accepted Accounting Principles (GAAP) rather than CAS apply.

Project Labor Agreement

● 1800 Forward Project will follow the new Project Labor Agreement

(PLA) Paired-Proposal Procedure.

● Each Offeror must submit a PLA Price Proposal with a completed

Contract Price Form.

● Offerors may, but are not required to, submit a Non-PLA Price Proposal for the same scope of work.

● The two proposals must be identical except for the PLA and its direct effects on cost, schedule, or technical approach.

● Offerors that do not submit a PLA Price Proposal are ineligible for award

Phase II Solicitation The phase II solicitation will include design packages necessary to submit a phase II technical and price proposal.

● Core and shell design

○ FFP early construction package

○ 95% CD at solicitation and 100% CD prior to CMc award

● Interiors

○ Design assist with construction ceiling price option

○ 100% DIDs at solicitation and 65% CD prior to CMc award

● Courtyards

○ Design assist with construction ceiling price option

○ Final concepts at solicitation and 100% DID prior to CMc award

Design Overview

Shalom Baranes Associates

● Core and Shell

Perkins and Will

● Interiors and Courtyards

1800 FORWARD– Phase 2B Core and Shell Scope Overview

August 11, 2026

1800 FORWARD

WASHINGTON DC PHASE 2B – Core and Shell

PHASE 2B – Core and Shell1800 FORWARD

WASHINGTON DC

PHASE 2B – Core and Shell

Wing 0

Wing 3 Wing 2 Wing 1

Wing 4 Wing 4

West Infill East Infill

Library Building

Auditorium

Auditorium Building

General Objectives

• Second step of Phase 2 modernization of 1800 F

• Referred to as Phase 2B

• Alignment with the historic preservation approach

• Build out Core and Shell elements including extension of MEP systems

• Build new ‘West Infill’ building in west courtyard

• Restore Phase 2 area windows and paint ALL windows

• Repair and restore masonry façade

• Replace the existing roofing

Existing Conditions

Existing Conditions

Demolition and Abatement:

• Hazardous Materials in the building:

• Lead paint

• ACM (asbestos containing material – mostly plaster)

• Phase 2A – already awarded and proceeding shortly:

• Majority of interior demolition work

• Hazardous materials are to be abated and removed when they are part of elements to be removed

• Phase 2B –some demo and abatement to be included:

• The larger structural openings in the existing building

• The Basement level slab on grade and underslab piping will be removed

• The existing roofing material will be removed

Historic Preservation Approach

Building Structure:

• Original building designed and constructed between 1914 - 1918

• The structure has informed the demolition and new construction strategy

• Steel frame with terra cotta tile flat arch system for floors

• Note that the interior non-load bearing partitions are built from 4” wide terra cotta tile block

• First round of demolition does not include larger openings that would require additional structural support

Building Structure (Sheet GI 0 25):

Building Structure (Sheet GI 0 25):

Core and Shell (detail from Sheet AE 4 76)

(detail from Sheet AE 6 40)

PHASE 2B – Core and Shell

• Terracotta block with plaster to remain at interior of exterior wall

• New insulation and drywall furring with piping for fan coil units located at every window

• Sashes to be replaced at most existing wood windows

• Cast iron window elements and wood window frames to be fully stripped and repainted

• New Cable Catchment System for blast at all street-facing windows

(detail from Sheets AE 5 04 and AE 6 40)

Historic Preservation - Interior

• Historic Lobby – Level 1 Wing 0

• Stone floors and wall – repairing cracks, cleaning

• Plaster – some repair and repainting

• New custom aluminum entrance doors replacing the modern aluminum doors

• Corridors

• Terrazzo – repair cracks, add control joints

• Some areas of new terrazzo to match existing

• Restoring the wood office suite doors

Building Envelope – Exterior Stone Restoration

• Transitional Masonry Façade

• Typical Exterior Wall:

• 4” limestone facing with larger limestone sill, water tables and cornices

• Multi-wythe brick masonry wall backup

• 2-1/2” thick terra cotta clay tile

• Interior plaster finish

• Extensive deterioration due to water infiltration, particularly at lower levels and Level 6 cornice, and level 7 facade

• Corrosion of embedded steel anchorage is producing rust jacking in some locations

• Deterioration of mortar joints, sealants, and flashings;

biological and metallic staining

Building Envelope – Exterior Stone Restoration

• Repair Protocol Under Development with a range of repair options

• Full scaffolding of building exterior will be required, with shoring of main cornice at street facing facades

• Early Contractor work once scaffolding in place will inform refinement and selection of repair methods

• Exposed corroded steel elements to be repaired or replaced and stone restored/replaced as required

• Full parapet reconstruction may be required in locations

• Repairing building movement cracks at façade corners and returns

Building Envelope – Window Restoration Phase 1 Area Windows

• Due to inadequate surface preparation, the paint is failing on the historic elements.

• Protocol to restore wood frames and sills, cast iron mullions and spandrels is being developed.

• Fully stripping original paint and repainting

Phase 2 Area Windows

• Replace sashes with insulated glass (typ)

• Restore wood frames and sills, cast iron mullions and spandrels.

New ‘West Infill’ Building

• Concrete structure with deep foundations

• Atrium with smoke removal system

• Steel trusses support glass curtainwall and skylight

Elevator Scope

• Unification of Elevator Controller

Platform

• Rehabilitation of Elevators 1/2 and 5/6

• New Service Elevator. Requires modification to the machine room of Elevators 11/12, and will include new penthouse extending above the adjacent roofs

MEP Core and Shell Overview:

• MEP fully demolished in Phase 2A, with the exception of some plumbing elements

• Phase 2B MEP will be full scope full installation from the connection points at the Phase boundary

• Mechanical system consists of:

• Chilled water and hot water distribution throughout

• DOAS units located at 7th with heat recovery for ventilation serving all floors vertically

• 4-pipe fan coil units at perimeter

• Telecomm closets heat rejection via condenser water

Mechanical Core and Shell Overview:

• Phase 1 areas contain the mechanical central plant, consisting of cooling tower, chilled water and boilers

• Condenser water, chilled water and hot water loop is located in the basement, serving vertical risers at each column

Electrical Core and Shell Overview:

•Phase 1 areas served by

Substations 1, 2 and 4

•Phase 2 area to be served by Future Substation 3

1800 Forward Interiors and Courtyards

Reimagined F Street

Entry Lobby

Reimagined Promenade

The Stacks Food Hall

Exterior

Interior

Interior

Town Hall Feature Stair

Access To

DOI

Access To Parking + Bike Storage

Open Access to The Commons

Secured Entry To Tenant Office

Space

L002 – Connection to workspace

Secured Entry To Tenant Office

Space

Secured Access to Staffed Coffee Bar

Stair – Extension B001 – Level 02

*not egress stair

Town Hall, Pre-Function

& WIL

Workplace – Open Office

Carry similar signage materials to upper floors, expressing information with lighter, more timeless typefaces and bolder proportions.

Workplace – Historic Corridors

Strategic placement of mural photography/wallcovering, using GSA/OPM assets. Curated, uniform artwork.

Reimagined Tunnel to

DOI

E Street Tunnel *Wayfinding + Graphics

Reimagined Tunnel to

DOI

E Street Tunnel

Question & Answer

Site Tour

● Photos are allowed

● Start at 7th floor. Walk sampling of floors down to basement. End in the courtyards.

● Materials can be left in the auditorium during the tour.

● Nothing said during the walk constitutes a change to any of the documents issued. All questions shall be formalized in a RFI.