Federal Center South B12021 Redevelopment

Exhibit 1 Draft Statement of Work

24 Sep 09

1 PROJECT DESCRIPTION

This project is a redevelopment/modernization of a portion of an existing warehouse (1202) located at Federal Center South. The primary tenant will be the U.S. Army Corps of Engineers (USACE), Seattle District. Other Federal Agencies may be included in this project if it is determined that funds are available within the established project budget. It is anticipated that approximately 150,000 to 200,000 GSF of office space will be required to meet current USACE workforce projections. The redeveloped/modernized facility should acknowledge the adjacent 1201 building (which has historical significance). The work should be accomplished through re-use of as much of the existing structural components and other building materials as possible while meeting GSA’s established standards for a ‘high performance green’ building. The office facility will also meet established GSA and Department of Defense security standards and will be NEPA compliant.

The current 1202 Warehouse is approximately 310 ft wide by 1100 feet long. It is an open bay, wood framed building constructed in 1940 by the U.S. Army. The exterior walls are poured concrete with utilitarian finishes and include clerestory windows above the interior space of the building. This project expects to redevelop the southern most half of this asset, while maintaining use of the remaining warehouse.

1.1 Project Type

Property redevelopment/modernization using a Collaborative Design Build approach that follows GSA’s design excellence guidelines.

1.2 Project Goals and Objectives

High Performing Green Building (HPGB) Sustainable Design/LEED New Construction (NC) GOLD Energy Performance is to be 30% better then ASHRAE 90.1 2007 edition Meet USACE space and operational requirements Meet USACE UFC security requirements Meet GSA P100 standard Meet GSA Design Excellence program Meet Historic Preservation Requirements pursuant to Section 106 of the NHPA Meet Accessibility Requirements

1.3 Project Delivery Approach

GSA envisions a highly collaborative design build delivery approach for this project.

The expectation is that the DB contractor will work closely with of all the stakeholders to deliver a project that meets the expectations and needs of the USACE, as well as the GSA’s requirements for a high performing green building.

During the development period from initial concept to final concept the DB team will work in close consultation with GSA, the USACE and the CMa to ensure that all of the goals are addressed.

Per the design excellence program the DB team will participate in design Peer reviews at the milestones required by the design excellence program.

1.3 Reference Materials

The following reference materials may be provided with the DB SOW issued under Phase 2 of the RFP.

1. 2009 Pile and Foundation structural study

2. 2009 Army Corps of Engineers Program of Requirements (POR)

3. 2009 Master Plan

4. 2009 Hazardous material study

5. 2009 Site Survey

2 PROJECT DELIVERY TEAM

In the performance of the requirements of this contract, the Design Build Contractor shall work in concert with all other parties on the Project Delivery Team. The Project Delivery Team will include the General Services Administration (GSA) personnel, United States Army Corp of Engineers (USACE) representatives, Construction Management Assist (CMa) to include the Commissioning Agent (Cx) and Energy Engineer (EE), and other stakeholders. The GSA will develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities. The major parties involved or to be involved in the Project Delivery Team, and their respective overall roles and general responsibilities, are as follows:

General Services Administration is the project owner and will be responsible for project management to include coordination of the parties and contract execution of the entire project.

USACE is the tenant and may provide input into the project requirements and participate in project reviews.

The CMa will be responsible for assisting GSA with requirements development, estimating, design reviews, price/cost analysis, quality assurance, construction schedule reviews, monitoring LEED process, etc.

The Cx will be part of CMa team and is responsible for developing commissioning requirements, drafting a Cx Plan, verifying that the installed systems meet objectives, functional and performance testing, seasonal/warranty testing, and submission of Cx report.

Energy Engineer/Energy Modeling will be a part of the CMa team and will collaborate with the DB team to monitor progress in achieving the target energy goal.

The Design-Build (DB) Team is required to perform two components of work: Design Stage services and Construction Stage work.

The LEED consultant will be part of the DB team and will be responsible for maintaining all LEED documentation necessary to meet the stated project LEED goal. The LEED consultant will be responsible for registering and submission of all required documents for LEED certification.

Energy Modeler of record will be a part of the DB team and will be responsible for developing the energy model that reflects achievement of energy targets.

The DB Contractor will be the Architect of Record for the project and will bear all responsibilities and liabilities attendant thereto.

The specific activities, tasks, and deliverables required of the DB Contractor will be further delineated in the DB Phase 2 RFP Scope of Work.

3 SCOPE OF WORK: (This is a representative list of expected tasks)

3.1 Design:

The D-B contractor will be responsible for design development at estimating at the following stages:

Concept Design 35% Design In progress 65% and 95% designs Final Conformed Design Set

3.1.1 Design Excellence and Peer Review

This is a Design Excellence project, which includes several concept development reviews, involving the DB Contractor, the GSA regional and national office staff, and professional private-sector peers serving on the behalf of the GSA. The broad objective f these reviews is to have discussions among professionals that focus on design, not only as it impacts issues of program requirements, function, form, and detail, but also as it affects on-time and on-budget delivery. These conversations can address general design strategies and urban context as well as more specific topics such as materials and building systems. At the Design Development Phase, a similar review is conducted to focus on the design of the HVAC system

3.1.2 Design Quality Assurance

The GSA requires that DB Contractor design submissions and construction documents submissions undergo two general types of design review: Owner’s review and codes and standards review. The GSA staff and GSA customer agencies will conduct reviews of all DB Contractor design submissions and construction documents submissions. The GSA OCA may also conduct independent quality assurance/quality control reviews of some DB Contractor design submissions. These GSA reviews will focus primarily on program goals and design objectives.

3.1.3 Constructability

Constructability of the project as designed is the sole responsibility of the DB Contractor.

DB shall ensure that the design can be constructed within schedule and budget and that the sequencing of construction is planned for optimum efficiency.

3.1.4 Building Information Modeling (BIM)

BIM for spatial program validation is a minimum BIM requirement performed by the DB contractor. Additional BIM may include:

• use of 3D geometric models for visualization

• use of 4D models for phasing analysis

• use of 3D/BIM for design and construction coordination

• use of BIM (with “smart” objects) for an array of analyses

GSA and the DB contractor will determine the level of BIM required to the project

3.2 Construction: GSA anticipates that this project will be very collaborative. During construction the Contractor shall provide all services required of a general contractor.

Specific details of the work are provided below but they shall in no way limit the Contractor's overall duty to provide DB services.

3.2.1. The Contractor shall conduct weekly progress meeting(s) and weekly subcontractor meeting(s) and maintain minutes for it. The Contractor shall also be required to attend construction oversight meetings with representatives from GSA and the Design Team on a monthly basis. The Contractor shall conduct site tours for GSA and other officials as required.

3.2.2 Develop a Construction Schedule current with the design resolution process.

Revise the construction schedule as required to reflect changes that have occurred during design or to reflect a change or more refined schedule for procurement of materials, subcontract buyout or construction. Provide updates at the design review meetings.

3.2.3 Develop Value Engineering proposals, which will provide savings to the Government.

3.2.4 Identify subcontract bid packages and material procurement packages that could be advertised prior to the completion of construction documents. If GSA concurs that the project will benefit GSA will authorize the Contractor to advertise and award subcontracts or material procurements for long lead-time items in advance of completion of construction documents.

3.2.5 Prepare construction cost estimate for the entire Work in CSI modified Uniformat (verify format with Architect) based upon the final design development submission. If the estimate exceeds the ECC, the Contractor shall take whatever actions may be necessary in conjunction with the Architect and GSA to reduce the cost of the Work to within the

ECC.

3.2.6 Prepare and process the application(s) for all necessary building permits. Monitor and expedite the permitting process as necessary to ensure that the construction permits are received in a timely fashion.

3.2.7 The Contractor shall be responsible for superintendence, providing ongoing coordination between crafts, job site safety, quality control, settling disputes between subcontractors, negotiating any Change Orders with the subcontractors (GSA expects the DB to negotiate with subcontractors, but reserves the right to reject any subcontractor proposal), negotiating Change Orders with GSA. Reviewing, coordinating and forwarding submittals and RFIs to GSA's Representative for action and for responding to all correspondence related to the effort required for any procurement activities that arise from a subcontractor's inability or unwillingness to perform.

3.2.8 The Contractor shall be responsible for general building layout, and for the coordination of layout work provided by separate trades for their own work, to insure that no conflict exists with the work of other trades. This work shall include the layout of all partitions and door openings, electrical panels, and fixed casework outlines (including knee spaces) on the floor slab prior to mechanical, plumbing, and electrical rough-in work.

3.2.9 The Contractor shall provide sufficient staff of project managers, field engineers, superintendents, engineers, CQC representatives, testing engineers, scheduling engineers, cost engineers, clerical and accounting personnel to ensure timely processing of Change Order Proposals, RFIs, submittals and general correspondence.

3.2.10 D-B shall complete all work necessary to turnover the building to GSA to include the following close-out activities:

Building Commissioning (HVAC, Fire Alarm Testing, etc) Pre-Inspection Punchlist documentation and resolution O&M Manuals Personnel Training on Systems Attic Stock Warranty/Guarantee As-builts Final Inspection and Acceptance

3.2.10.1 Construction Substantial Completion is defined as a level of construction, which allows the Government to occupy and operate the entire building or portions of the building according to a phased occupancy schedule. The only remaining work in the building shall not restrict occupancy or the normal business operations of the building tenants. Such remaining work is normally cited on a punchlist, which is included in the documentation of Substantial Completion.

3.3 Art in Architecture

The GSA Art in Architecture program involves the selection of an artist to create and install artwork within the project. Artwork should respond to the context of both the facility design and the surrounding community. The DB contractor will coordinate with the GSA Art in Architecture staff on recommendations to incorporate art as an integral component of the building, participate in the selection of the artist, and accommodate the installation of the final artwork within the building design. Structural support and utilities for the artwork installation shall be included in the construction contract and the associated cost must be accommodated within the construction funding limitation. The artwork will be procured, furnished and installed under separate contracts. The cost of separate contracts for the artwork is not included in the construction funding limitation.