GRSM 14(3)121(1)ETC_BIP_STR 5460-078P.pdf

PDF 4 MB Posted

Attached to
Great Smoky Mountains National Park
Solicitation number
693C73-20-B-000021
Issued by

About this file

This federal solicitation is seeking bids for rehabilitation work on nine bridges located in the Great Smoky Mountains National Park in Tennessee. The project consists of asphalt wearing course removal, scour protection around existing abutments and wingwalls, installation of new concrete deck, replacement of nail-laminated timber decking, cleaning and repointing of masonry joints, repaving of bridge approaches, and rail repairs. The work will be split among multiple contract schedules and options, with the total cost expected to be between $1-5 million. Construction must be completed by March 26, 2022. Bids are due on or around the date specified in Block 13a of the solicitation. The soliciting agency is the Department of Transportation Federal Highway Administration. Bids for this set-aside project will be accepted only from certified Small Business Concerns.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STRUCTURE SUMMARY STRUCTURE NO. 5460-078P

HORSE STABLE BRIDGE INSPECTION DATE: 6/20/18

BRIDGE IDENTIFICATION AND DESCRIPTION

MAIN SPAN MATERIAL:

MAIN SPAN TYPE:

# OF BEAMS, MAIN SPAN: ..

DECK TYPE:

WEARING SURFACE:

ABUT. FOUNDATIONS:

PIER FOUNDATION(S):

ABUTMENT / PIER MAT'L: ...

PROJ./PLAN REF. NO:

NPS ROAD CLASS:

STRUCTURE HISTORY:

STEEL

STRINGER/MULTI-BEAM or GIRDER

WOOD OR TIMBER

NONE

UNKNOWN

N/A

CONCRETE

BRIDGE REPL. / 00000

1 - PRINCIPAL PARK ROAD

NO. OF MAIN SPANS:

NO. OF APPR. SPANS:

STRUCT. TOTAL LENGTH: ..

MAX. SPAN LENGTH:

DECK WIDTH:

CURB TO CURB WIDTH:

YEAR BUILT:

YEAR RECONSTRUCTED: ..

SKEW ANGLE:

FRACTURE CRITICAL:

29.0 FT (8.8 M)

29.0 FT (8.8 M)

24.4 FT (7.4 M)

23.2 FT (7.1 M)

N/A

10 °

NO

LOCATION

GREAT SMOKY MOUNTAINS NATIONAL PARK MILE POINT: ..................... 0.01 (KM PT 0.02)

STATE: ................................. TENNESSEE LOCATION: 0.01 MILES SOUTH FROM TN ROUTE 73.

FACILITY CARRIED: ............ HORSE STABLE ENTRANCE ROAD

FEATURE INTERSECTED: .. DUDLEY CREEK

STRUCTURE EVALUATION SUMMARY

This weathering steel beam bridge is in fair condition overall. The main problems include moderate scour with footing exposure at the abutments; and erosion of the adjacent channel banks. Additional problems include deteriorated masonry mortar joints at the abutment breastwalls and wingwalls; soil accumulation and vegetation growth between the deck timbers which is retaining moisture leading to moderate decay throughout the deck; flaking of the weathering steel protective coating with section loss to the structural steel; fallen trees blocking the upstream channel; and tree and vegetation growth against the deck, bridge rails and on the utility supports. Additionally, reflective object markers are not provided at the ends of the bridge.

Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.

INSPECTION TEAM: B. BUMPERS, T. POWELL (VOLKERT, INC.)

CONDITION ASSESSMENT:

BRITT BUMPERS, P.E., FIELD TEAM LEADER

REPORT REVIEW:

MARCUS MILLER, P.E., BRIDGE INSPECTION ENGINEER 703-404-6252

REPORT APPROVAL: DATE: 11/8/18

JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5460-078P

A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.

B (Major) - Structure exhibits severe deterioration, presents a safety hazard, or is designated a high priority due to age and/or condition.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

C226 PRIORITY OF IMPROVEMENT

ITEM

NO.

ROUTINE MAINTENANCE QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

58.6,8, 61.4 REMOVE TREE AND VEGETATION GROWTH FROM BRIDGE CORNERS, BRIDGE

RAILS, AND UTILITY SUPPORT BEAM, AND FALLEN TREES FROM UPSTREAM

CHANNEL.

1 LS

58.1,7 PERIODICALLY REMOVE SOIL AND VEGETATION GROWTH BETWEEN TIMBER

DECK PLANKS AND ALONG CURBLINES.

1 LS

222.7 INSTALL REFLECTIVE OBJECT MARKERS AT ENDS OF BRIDGE. 2 EA

PRELIM. MAINTENANCE TOTAL :

ITEM

NO.

REHABILITATION/RECONSTRUCTION

(TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. UNIT

UNIT

COST

PRELIM. COST

ESTIMATES

REHAB. RECONSTR.

60.1,6 CLEAN AND REPOINT MASONRY MORTAR JOINTS AS NECESSARY. 5 LS

60.9, 61.2 PLACE ENGINEERED RIPRAP AT ABUTMENT FOOTINGS AND ALONG

CHANNEL BANKS TO PREVENT FURTHER SCOUR AND SLOUGHING.

1 LS

58.6 REPLACE NORTHWEST RAIL POST. 1 LS

CONTRACT COSTS FOR MOBILIZATION, TRAFFIC CONTROL,

DESIGN, AND CONSTRUCTION ENGINEERING.

1 LS

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :

PRELIMINARY ESTIMATE TOTAL* :

(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)

REMARKS: Cost estimates assume that the recommended actions will be combined with similar work being performed on other structures.

The condition of the structural steel will continue to be monitored.

FIELD INSPECTION REPORT STRUCTURE NO. 5460-078P

G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)

CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS

SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.

Fatigue cracks in steel or shear cracks in concrete may be present.

CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.

“IMMINENT” FAILURE CONDITION - major deterioration or sec ion loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.

FAILED CONDITION - out of service; beyond corrective action.

CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223

NOT APPLICABLE

EXCELLENT CONDITION

VERY GOOD CONDITION - no problems noted.

GOOD CONDITION - some minor problems.

SATISFACTORY CONDITION - structural elements show some minor deterioration.

FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.

POOR CONDITION - advanced section loss, deterioration, spalling, or scour.

N

58. DECK ITEM REFERENCE AND REMARKS

OTHER

ALIGNMENT

DEFLECTION AND/OR VIBRATION

FASCIA(E)

DIAPHRAGMS AND BRACING

TRUSSES

FLOOR BEAMS AND STRINGERS

ARCH(ES) OR SLAB(S)

GIRDERS OR BEAMS

BEARING DEVICES

59. SUPERSTRUCTURE

OTHER

DEFLECTION AND/OR VIBRATION

UTILITIES

DRAINS AND DRAINAGE

PARAPETS AND/OR RAILINGS

CURBS, SIDEWALKS, AND MEDIAN

RIDEABILITY

WEARING SURFACE

EXPANSION JOINTS

DECK SLAB

OTHER

SETTLEMENT OR DEFLECTION

EROSION AND/OR SCOUR

FOUNDATIONS

CAPS AND/OR BEARING SEATS

PILE BENTS

WALLS AND/OR COLUMNS

PIER(S)

OTHER

SLOPE PROTECTION

SETTLEMENT OR DEFLECTION

EROSION AND/OR SCOUR

EXPANSION JOINTS

WEEP HOLES

WINGWALLS

FOUNDATIONS

BACKWALLS AND/OR BULKHEADS

CAPS AND/OR BEARING SEATS

PILE BENTS

BREASTWALLS OR COLUMNS

ABUTMENTS

60. SUBSTRUCTURE

1.

10.

2.

3.

4.

5.

6.

7.

8.

9.

10.

9.

8.

7.

6.

5.

4.

3.

2.

1.

PAINT

11.

(VEGETATION)

F F N N N F N N G

N G

G N F G G G N N F F N

G(TIEBACKS)

N N N N N N N

11.

10.

9.

8.

7.

6.

5.

4.

3.

2.

1.

12.

13.

14.

15.

16.

17.

18.

19.

58.1,7 2" X 8" (NOMINAL) NAIL-LAMINATED TIMBER DECK. MODERATE

ABRASION ALONG WHEEL PATHS. MINOR TO MODERATE DECAY OF

TIMBER DECK PLANKS; MINOR TO MODERATE DECAY ON DECK

TIMBER ENDS.

MINOR TO MODERATE ACCUMULATION OF SOIL AND VEGETATION

GROWTH BETWEEN DECK TIMBERS. MODERATE VEGETATION

GROWTH AND DEBRIS ACCUMULATION ALONG CURBLINES.

58.5,6,10 MINOR CHECKING OF CURB AND RAILING TIMBERS. MINOR TO

MODERATE DECAY OF TOPS OF SOME RAIL POSTS. ADVANCED

DECAY OF NORTHWEST RAIL POST. MODERATE VEGETATION

GROWTH OVERHANGING EAST BRIDGE RAIL. MINOR VEGETATION

GROWTH ON WEST BRIDGE RAIL AT NORTH END.

58.8 UTILITY PIPE ALONG WEST EXTERIOR BEAM AND ON EAST SIDE OF

STRUCTURE; NO INTERFERENCE WITH FLOW. HEAVY VEGETATION

GROWTH ON EAST SIDE UTILITY SUPPORT BEAM. FALLEN TREE

ACROSS UPSTREAM CHANNEL AND AGAINST EAST SIDE UTILITY

SUPPORT BEAM. UTILITY ON WEST SIDE SEPARATED AND OPEN AT

MULTIPLE LOCATIONS. MINOR RUST SCALE ON UTILITY BRACKET

ON WEST SIDE.

58.10 MINOR TREE GROWTH AGAINST DECK AT NORTHWEST CORNER OF

STRUCTURE.

59.1,2,6 A588 WEATHERING STEEL. MODERATE TO SEVERE RUSTING WITH

MINOR SECTION LOSS, UP TO 1/16" OF SECTION LOSS FROM

BEARING DEVICES. MODERATE FLAKING OF PROTECTIVE COAT;

5/8" THICKNESS OF BOTTOM FLANGE REMAINING. MODERATE

FLAKING WITH SECTION LOSS, UP TO 1/4", FROM DIAPHRAGMS; 1/4"

THICKNESS OF FLANGES REMAINING; ISOLATED LOCATIONS DOWN

TO A KNIFE EDGE.

MINOR ACCUMULATION OF DEBRIS ON TOP OF BOTTOM FLANGES

THROUGHOUT.

60.1,6 MINOR DETERIORATION OF MASONRY MORTAR JOINTS ON

WINGWALLS AND ABUTMENT BREASTWALLS. MINOR TO MODERATE

STEP CRACK THROUGH MORTAR JOINTS AT NORTH ABUTMENT.

MINOR EROSION ALONG SOUTHWEST WINGWALL.

N G G F G F

F

N

G

F

FIELD INSPECTION REPORT STRUCTURE NO. 5460-078P

ITEM REFERENCE AND REMARKS

61. CHANNEL 5

1. ALIGNMENT F

2. EROSION AND/OR SCOUR F

3. CHANNEL PROTECTION N

4. WATERWAY OBSTRUCTIONS F

5. OTHER N

6. ADEQUACY OF OPENING SUFF

7. NORMAL VELOCITY MED

8. AVERAGE CLEAR OPENING 6 FT.

9. STREAM BED COMPOSITION :

ROCK, SAND, STONES

222. APPROACHES 7

1. APPROACH SLABS

2. RELIEF JOINTS

3. APPROACH GUARDRAIL

4. SURFACING

5. EROSION

6. SETTLEMENT

7. SIGNS

8. ALIGNMENT

9. OTHER

N N N G G G N G N

223. RETAINING WALL N

1. WALL

2. WEEP HOLES

3. FOUNDATION

4. EROSION AND/OR SCOUR

5. SETTLEMENT OR DEFLECTION

6. OTHER

36. TRAFFIC AND SAFETY FEATURES

A. BRIDGE RAILINGS

B. TRANSITIONS

C. APPROACH GUARDRAILS

D. APPROACH GUARDRAIL ENDS

N N N

TRAFFIC SAFETY RATING CODES

0 - Does not meet standards or a safety feature is required and none is provided.

1 - Meets currently acceptable standards.

N - Not applicable or a safety feature is not required.

60.3 MINOR DEBRIS ACCUMULATION ON BEARING SEATS.

60.9 MODERATE SCOUR HAS EXPOSED 8" OF NORTH ABUTMENT

FOOTING AND UP TO 12" OF SOUTH ABUTMENT FOOTING; NO

UNDERMINING PRESENT. MODERATE EROSION AT NORTH

ABUTMENT WINGWALLS. 18" OF UNDERMINING AT NORTHEAST

WINGWALL OVER POUR APRON.

60.10 MODERATE SETTLEMENT OF FILL (UP TO 12" D X 18" W) BETWEEN

TOP OF BREASTWALL AND BEARING SEAT AT NORTH ABUTMENT

UNDER BEAM #4.

60.12 SURFACE RUST ON DEADMAN TIEBACK HARDWARE AT ABUTMENT

BREASTWALLS.

61.1 CHANNEL HAS SHIFTED AGAINST NORTH ABUTMENT.

61.2 SEE BRIDGE FILE FOR SCOUR EVALUATION.

61.2,4 MODERATE CHANNEL BANK SLOUGHING HAS PARTIALLY

UNDERMINED NUMEROUS TREES WITH SEVERAL FALLEN ALONG

CHANNEL BANKS; FALLEN TREE BLOCKING UPSTREAM CHANNEL.

222.4 ASPHALT TRANSITION AT SOUTH APPROACH.

222.6 MINOR SETTLEMENT, UP TO 2", OF SOUTH APPROACH SHOULDERS

AT ENDS OF STRUCTURE.

222.7 REFLECTIVE OBJECT MARKERS NOT PROVIDED AT BRIDGE ENDS.

STRUCTURE LOAD RATING STRUCTURE NO. 5460-078P

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 25 23 42 38

HS 43 39 73 66

TYPE 3 35 32 58 53

TYPE 3S2 52 47 88 80

TYPE 3-3 68 62 114 103

DESIGN LOADING: UNKNOWN

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

X ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION: 10/10

LOAD RATING CONTROLLED BY: GIRDER

REMARKS: SEE BRIDGE FILE FOR LOAD RATING CALCULATIONS.

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5460-078P

STRUCTURE IDENTIFICATION

(201) PARK: GREAT SMOKY MOUNTAINS NATIONAL PARK (1) STATE: ....................................... 474 - TENNESSEE (TN)

(202) STRUCTURE NAME: .......... HORSE STABLE BRIDGE (2) STATE HWY. AGENCY DIST:

(203) STRUCTURE KIND: ............1 - BRIDGE (3) COUNTY CODE: ........................ 155 - SEVIER

(204) STRUCTURE NUMBER: ..... 5460-078P (4) CITY/PLACE CODE:

(205) NPS REGION: .................... 4 - SOUTHEAST (5) INVENTORY ROUTE:

(206) ROUTE CODE NUMBER: ... 112 (6) FEATURES INTERSECTED:....... DUDLEY CREEK

(207) ROAD SECTION NO: ..........078P (7) FACILITY CARRIED: .................. HORSE STABLE ENTRANCE

(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD (8) STATE STRUCTURE NO: .......... 5460078P0000000

(209) WITHIN NPS BNDRY?: .......YES (9) LOCATION: ................................ 0.01 MILES SOUTH FROM TN

(210) OPERATING UNIT: ............. N. DIST. (10) INV. RTE. - MIN. VERT. CLR: .. 99.99 FT (99.99 M)

(211) PROJECT NO(S): ................BRIDGE REPL. (11) MILE POINT: .............................0.01 (KM PT 0.02)

(212) DRAWING NUMBERS: ....... 00000 (27) YEAR BUILT:

(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE (106) YEAR RECONSTRUCTED: .... N/A

(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE (20) TOLL: ........................................3 - FREE ROAD

(37) HISTORICAL DESIGNATION: .. 5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL: ..

(43B) MAIN STR. TYPE:

(45) NO. OF MAIN SPANS:

(48) MAX. SPAN LENGTH:

(49) STRUCTURE LENGTH:

(216A) ABUTMENT #1 FDN:

(216B) ABUTMENT #2 FDN:

(217A) PREDOM. PIER FDN.: ..

(217B) SECOND. PIER FDN: ...

(107) DECK TYPE:

3 - STEEL

02 - STRINGER/MULTI-BEAM or GIRDER

29.0 FT (8.8 M)

29.0 FT (8.8 M)

0 - UNKNOWN

0 - UNKNOWN

6 - N/A

6 - N/A

8 - WOOD OR TIMBER

(44A) APPR. STR. MATERIAL: ........ 0 - OTHER

(44B) APPR. STR. TYPE: ................ 00 - OTHER

(46) NO. OF APPROACH SPANS: .. 0

(108) WEAR SURFACE/PROTECT SYSTEM:

A) TYPE WEARING SURFACE: .. 0 - NONE

B) TYPE MEMBRANE: ................. 0 - NONE

C) TYPE PROTECTION: .............. 0 - NONE

(218) IS SALT USED?: ..................... NO

LOAD RATING AND POSTING

(31) DESIGN LOAD: ................. 0 - UNKNOWN (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION

(66) INVENTORY RATING: ...... 43.0 TONS (39.0 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED

(64) OPERATING RATING: ...... 73.0 TONS (66.2 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 6/18 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO

INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 0 - NONE

(B) UNDERWATER: .............. NO

(221) SPECIAL STUDY DATE: INSP. EVERY: MONTHS - LAST INSP. :

(C) SPECIAL INSPECTION: .. NO

INSP. EVERY: MONTHS - LAST INSP. :

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5460-078P

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE: ............................. 35°43'48.10"

(17) LONGITUDE: ......................... 83°27'10.10"

(19) DETOUR LENGTH: ............... 0 MI (0 KM)

(28A) LANES ON STRUCT:

(28B) LANES UNDER STRUCT: ... 00

(42A) SERVICE ON: ..................... 1 - HIGHWAY

(42B) SERVICE UNDER: .............. 5 - WATERWAY

(29) AVG. DAILY TRAFFIC:

(30) YEAR OF ADT:

(114) FUTURE ADT:

(115) YEAR OF FUTURE ADT:

(101) PARALLEL STRUCTURE: ... N - NONE

(38) NAVIGATION CONTROL?: ... 0

(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)

(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)

(111) ABUT. OR PIER PROT:

LATERAL UNDERCLEARANCE:

(55) RIGHT: ....................... 0.0 FT (0.0 M)

(56) LEFT: ......................... 0.0 FT (0.0 M)

(51) CURB TO CURB WIDTH:

(52) DECK WIDTH:

(32) APPR. ROADWAY WIDTH:

(213) APPR. PAVEMENT WIDTH:

LEFT SHOULDER:

RIGHT SHOULDER:

(33) BRIDGE MEDIAN:

(34) SKEW ANGLE:

(35) DECK FLARE?:

(47) TOTAL HORIZ. CLEARANCE:

(50) SIDEWALKS:

LEFT :

RIGHT :

(214) BRIDGE RAIL TYPE:

RAIL CONFIGURATION:

MATERIAL:

DESIGN TYPE:

(215) BRIDGE RAIL HEIGHT:

(53) MIN. VRT. CLEAR. OVER DECK:

(54) MIN. VRT. UNDERCLEARANCE:

23.2 FT (7.1 M)

24.4 FT (7.4 M)

29.0 FT (8.8 M)

23.0 FT (7.0 M)

3.0 FT (0.9 M)

3.0 FT (0.9 M)

0 - NO MEDIAN

10 °

NO

23.2 FT (7.1 M)

0.0 FT (0.0 M)

0.0 FT (0.0 M)

1 - FULL HEIGHT (NO PARAPE

7 - TIMBER

1 - CONTINUOUS RAIL

3.50 FT (1.07 M)

99.99 FT (99.99 M)

0.00 FT (0.00 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:

(59) SUPERSTRUCTURE:

(60) SUBSTRUCTURE:

(61) CHANNEL:

(62) CULVERT: ...........................N

(222) APPROACHES:

(223) RETAINING WALL: ........... N

(36) TRAFFIC SAFETY FEAT: ... 1NNN

(75A) TYPE OF WORK:

(75B) WORK DONE BY:

(76) IMPROVEMENT LENGTH: ..

(67) STRUCTURAL EVALUATION:

(68) DECK GEOMETRY:

(69) UNDERCLEARANCES:

(71) WATERWAY ADEQUACY:

(72) APPROACH ALIGNMENT:

(113) SCOUR CRITICAL:

(225) PURPOSE OF IMPROVEMENT:

(226) PRIORITY OF IMPROVEMENT:

(227) MAINTENANCE COST:

(228) REHAB./RECONSTR. COST: ...

(229) CONSTRUCTION COST:

N

4 - Stable; action required to pro

2 - REHAB/RECONSTRUCTION

C - MODERATE

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

(231) ADDITIONAL CONSIDERATIONS:

(330) ADDITIONAL CONFIG. INFO.:

https://83�27'10.10 https://35�43'48.10

APPENDIX STRUCTURE NO. 5460-078P

PHOTOGRAPHS STRUCTURE NO. 5460-078P

PHOTO #1 - LOOKING SOUTH TOWARD HORSE STABLES

FLOW

PHOTO #2 - EAST (UPSTREAM) SIDE

PHOTO #3 - GENERAL TOP SIDE VIEW LOOKING NORTH

PHOTO #4 - GENERAL UNDERSIDE VIEW LOOKING NORTHWEST

PHOTO #5 - ASPHALT WEDGE AT SOUTH APPROACH

PHOTO #6 - WEATHERING AND DETERIORATION OF NAIL LAMINATED

DECK; NOTE SOIL ACCUMULATION AND VEGETATION GROWTH

BETWEEN TIMBER DECK MEMBERS

PHOTO #7 - TYPICAL CHECKING OF CURBS, EAST CURB NEAR SOUTH

END SHOWN

PHOTO #8 - TYPICAL VEGETATION GROWTH OVERHANGING BRIDGE

RAILS, EAST BRIDGE RAIL SHOWN

PHOTO #9 - DECAY OF NORTH RAIL POST IN WEST BRIDGE RAIL

PHOTO #10 - GENERAL VIEW OF SOUTH ABUTMENT

PHOTO #11 - TYPICAL DETERIORATION OF MASONRY MORTAR JOINTS,

SOUTH ABUTMENT SHOWN

PHOTO #12 - TYPICAL FOOTING EXPOSURE AT ABUTMENT, SOUTH

ABUTMENT SHOWN

PHOTO #13 - EROSION ALONG SOUTHWEST WINGWALL

PHOTO #14 - TYPICAL DEBRIS ACCUMULATION ON BEARING SEATS,

BEARING #2 AT SOUTH ABUTMENT SHOWN

PHOTO #15 - TYPICAL DETERIORATION OF WEATHERING STEEL

BEAMS, BEAM #2 SHOWN

PHOTO #16 - TYPICAL FLAKING OF BEAM WEATHERING STEEL

PROTECTIVE COAT, WEST SIDE OF BEAM #3 AT MIDSPAN SHOWN

PHOTO #17 - TYPICAL SECTION LOSS FROM BEAM FLANGES, EAST

SIDE OF BEAM #3 SHOWN

PHOTO #18 - TYPICAL FLAKING WITH SECTION LOSS FROM

DIAPHRAGMS, BAY #4 DIAPHRAGM AT MIDSPAN SHOWN; NOTE

BOTTOM FLANGE DOWN TO KNIFE EDGE

PHOTO #19 - UTILITY ON WEST SIDE SEPARATED AND OPEN AT

MULTIPLE LOCATIONS

PHOTO #20 - CRACKING OF MASONRY MORTAR JOINT AT NORTHWEST

WINGWALL

PHOTO #21 - FALLEN TREES DUE TO EROSION ON SOUTH BANK OF

DOWNSTREAM CHANNEL

PHOTO #22 - UNDERMINING OF OVER POUR AT EAST END OF NORTH

ABUTMENT

PHOTO #23 - UPSTREAM CHANNEL; NOTE FALLEN TREE IN CHANNEL

AND VEGETATION GROWTH ON UTILITY SUPPORT BEAM

PHOTO #24 - DOWNSTREAM CHANNEL

File details come from the government source that posted it. Updated .