GLAC_307440_Final_CD_Permit_List.pdf
PDF 60 KB Posted
- Attached to
- GLAC 307440 - Replace Headquarters Wastewater and Federal contract opportunity
- Solicitation number
- 140P2023R0072
About this file
This document contains a permit list for the GLAC 307440 Headquarters Wastewater System project. The list identifies permits required by March 16, 2023 for the project, which includes replacing the headquarters wastewater system and backup power generation at Glacier National Park. The permits include an incidental take concurrence letter from the U.S. Fish and Wildlife Service, which will be provided by the government, and a construction stormwater general permit from the Montana Department of Environmental Quality, which must be obtained by the contractor. The document notes an update removing a wastewater permit from the list following discussion with the state agency and that consultation with the wildlife service may result in a concurrence letter rather than an incidental take permit.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Permit List:
GLAC 307440, Headquarters Wastewater System
PROJECT TITLE: HQ Wastewater System & Backup Power System PMIS #: 307440 PEPC#
PARK: GLAC REGION: IntermountainPROGRAM: Design/Const
PARK CONTACT: Jim Foster A\E: HDR
Dates of Assessment:
updated
1/20/2023 A\E CONTACT: Rickey Schultz, PE
Permits to Contracting no later than:
Permit Agency
Government Furnished
(GF) or Contractor
Provided (CP) USF&WS Incidental Take/ Concurrence Letter U.S. Fish & Wildlife Service GF
Construction Stormwater General Permit Montana Department of Environmental Quality CP
Project Meta Data
Notes: Update 1/20/23: Schedule 1.A. wastewater permit removed from list following discussion with MDEQ on 1/18/23.
Permit listed was upated on 11/09/22 to reflect all permits identified as part of the project in the PAF that do not fall within 'Construction Topics
(Based on Means and Methods) are Government Furnished (GF). The Permit Plan will be subsequently updated to reflect this change, as well as permit aquisition services.
USF&WS permit was updated to note that a concurrence letter may be the outcome of the consultation process rather than an incidental take permit.
DSC PM: Matt Jagunic