SSM Addendum No. 1 Page 1 of 2 8/24/20

Seismic Safety and Modernization (SSM) and Transit Hub and Utility Project (THUP)

RFP No. GKO21120

Addendum No. 1

September 01, 2020

1. The bid due date has been extended to Monday, 28 September 2020, at 12:00 PM.

Questions concerning this RFP are due no later than Wednesday, 16 September 2020, at

12:00 PM.

2. Replace Part 1.2.a, b and c of the SSM RFP GKO21120 (page 2) as follows:

a. Demolition Package: SSM and THUP “A” work (Option), generally described as follows to include:

o Demolition o Excavation, Backfill and Rough Grading at Building and Site.

o New Retaining Walls at Building and Site.

o Utilities relocation as required.

o All associated General Requirements.

b. SSM and B48: “B” work, generally described as follows to include:

o Main Building.

o Final Grading at Building.

o Utilities within 5 feet of building footprint.

o Site Paving including asphalt, concrete and pavers.

o Seismic upgrade to second floor of B48.

c. THUP: “B” work, generally described as follows to include:

o Transit Hub, or bus stop.

o Final grading at site.

o Utilities beyond 5 feet of the building footprint.

o Landscaping.

3. Replace specification section 019113 - General Commissioning Requirements dated 3/4/20 with specification section 019113 – General Commissioning Requirements dated 8/21/20.

4. Add specification section 019113A – General Commissioning Plan dated 8/21/20.

5. For clarification of project scopes reference the following attached HDR highlighted site plans:

o Demolition THUP “A” scope drawing AD-001 o Demolition THUP “A” scope drawing AS-050

SSM Addendum No. 1 Page 2 of 2 8/24/20 o SSM THUP “B” scope drawing AS-100

6. Attached for reference is a summary project schedule, dated 8/21/20, that is based on the project schedule, dated 6/10/20, distributed with RFP GK021120.

7. Add to specification section 015111 Temporary Utilities:

3.4 TRAILER AND CONSTRUCTION SITE LAYOUT

A. Provide trailers and site layout per attached 015111-4 site plan dated 8/21/20.

B. Trailers to be furnished, maintained and cleaned weekly by the CM-GC.

C. 24 x 60 trailer to include a reception desk, two enclosed offices, restroom and 12 half height partition offices and a plan review area. LBNL to occupy up to 3 of the 12 half height partition offices. One 12 x 60 trailer to be a conference room with table and seating to accommodate up to 30 attendees, a plan review area and restroom.

One 24 x 60 trailer to contain 8 half height partition offices with a plan review area and restroom.

D. Temporary power location for trailers and construction noted on sheet 015111-4 at the south west corner of the parking lot near B70.

E. LBNL IT to bring telecom and data lines to project construction trailers. CM-GC to run telecom and IT lines within trailers to all offices, reception desk and plan review areas and provide phone(s) at these locations.

8. The selected CM-GC to perform RFP GK021120 Phase 1 work is to also perform Phase 2 work, unless the CM-GC does not meet contract requirements in Phase 1.

9. A3GEO preliminary geotechnical report dated December 28, 2018.

10. Terraphase historical assessment of B54 dated June 2020.

11. All CM-GC and Subcontractor parking to be offsite and CM-GC is responsible to transport personnel to and from the jobsite. The cost of offsite parking is excluded from this proposal and will be addressed at a later date.

12. CM-GC to be prepared to provide separate pricing for SSM and THUP A work and SSM and THUP B work for implementation of COVID 19 requirements per LBNL and Alameda County.

LBNL COVID 19 requirements attached. The cost for implementation of COVID 19 requirements is excluded from this proposal and will be addressed at a later date.

Seismic Safety and Modernization (SSM) LBNL RFP No. GK021120

Last revised: 02/06/2020 Page 1 of 41 Updated August 21, 2020

SECTION 019113 – GENERAL COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Related Documents:

1. Drawings and general provisions of the Subcontract apply to this Section.

2. Review these documents for coordination with additional requirements and information that apply to work under this Section.

B. It is of primary concern that all systems and assemblies in the project perform in accordance with the design intent and the University's operational needs. The process of assuring that such performance is achieved is referred to as "commissioning."

C. Commissioning requires cooperation and direct involvement by all parties throughout the construction process. Successful commissioning requires that installation of all building systems and assemblies not only comply with subcontract requirements but also that it is achieved early enough in the construction phase to provide full operational check-out, testing and adjustments prior to Substantial Completion. In addition to fulfilling scheduling and planning requirements, the Trade Subcontractors are further responsible for documenting the equipment and system installation and operational verification for all systems and assemblies.

D. The CM-GC and Trade Subcontractors are solely responsible for the commissioning responsibilities given in the Specifications. If the CM-GC elects to outsource commissioning responsibilities, the University must approve the agent via review of résumé and references.

E. This Section includes a description of the commissioning process to be used for this Project and applies to all commissioned systems and assemblies.

F. Overall Quality Assurance/Quality Control (QA/QC): Quality assurance and quality control on this Project shall be accomplished by the following, as specified. Not all elements are monitored by the commissioning process.

1. Submittal reviews of Shop Drawings and material descriptions and certifications.

2. Qualifications and approvals of certain specified Lower-tier Subcontractors and testing agencies or laboratories.

3. Inspection, testing and certifications by agencies provided by the University, including on-site and laboratory testing.

4. Inspection, testing and certifications by agencies provided by the Trade Subcontractors, including on-site and laboratory testing.

5. Inspection and testing by regulatory agencies.

6. CM-GC and Trade Subcontractor and University checks, inspections, tests and certifications.

7. Mock-ups and evaluations.

8. Commissioning: Commissioning enhances installation and setup and verifies the functional performance of the more dynamic systems through observation and testing as specified in this Section. Commissioning also may cover the QA/QC of certain static building elements or assemblies. Some QA/QC activities will be overseen by the commissioning process, while other QA/QC activities will be overseen by the CMGC, the Registered Design Professional (RDP), or University representative. Generally, the QA/QC activities that have traditionally been conducted in the past remain outside the formal commissioning umbrella, such as concrete testing, inspection of static building elements, and regulatory or code inspections. However, compiling the documentation of some of these traditional activities may be within the commissioning scope, as specified herein.

G. Commissioning Process Overview: The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur.

1. Commissioning during construction begins with a planning meeting followed by a kick-off meeting conducted by the Commissioning Authority where the commissioning process is planned and reviewed with the commissioning team members.

Last revised: 02/06/2020 Page 2 of 41 Updated August 21, 2020

2. Attendance at commissioning meetings will be required throughout construction, scheduled by the PM for the Commissioning Authority with the CM-GC MEPF Commissioning Coordinator and Subcontractor MEPF designated commissioning representatives attending, to plan, scope, coordinate, schedule future activities and resolve problems.

3. Equipment and assembly documentation is submitted to the University and their Commissioning Authority during normal submittals, including detailed start-up procedures and early copies of Operation and Maintenance (O&M) data, upon receipt of equipment to be installed on the project.

4. The Trade Subcontractor develops start-up plans for selected equipment with review by the Commissioning Authority. The Commissioning Authority reviews the Trade Subcontractor developed construction checklists that are completed by the Trade Subcontractor during the start-up process. Responsibilities among parties are summarily listed in Supplement 3 to this section.

5. In general, the checkout and performance verification proceeds from simple to complex; from component level to equipment to systems and intersystem levels with construction checklists being completed before testing.

6. The Trade Subcontractor(s), under the direction of the Subcontractor’s designated Commissioning Coordinator in accordance with the OEM equipment manual/system design that they installed as part of the project, execute and document the construction checklists and perform start-up and initial checkout.

7. The Commissioning Authority documents that the checklists and start-up were completed through spot witnessing and review Trade Subcontractor's completed checklists and startup reports. Daily written/photo copy updates will be provided for commissioning status to the Commissioning Authority and University by the General Contractor and/or their designated Commissioning Coordinator of their subcontractor(s). The documents shall be signed by the representative installing Trade Subcontractor (equipment start-up (OEM) and/or Controls contractor (program point to point checklist) and submitted to the Commissioning Authority and University prior to functional performance testing.

8. The CM=GC and/or their designated Commissioning Coordinator will participate in monthly commissioning update meetings starting in April 2021 through January 2023.and then starting in February 2023 participation in weekly meetings through October 2023. Meetings are to determine all commissioning steps for all systems as part of the project. The General Contractor and/or their designated Commissioning Coordinator will provide for in advance of the meetings in direction to their subcontractors for solutions and resolutions to late material deliveries, service vendor coordination, equipment replacement/ repairs for non-compliance and/or failures, etc., to maintain schedule of commissioning.

9. The Subcontractor and/or their designated Commissioning Coordinator will provide a detailed schedule within the Master Construction Schedule that includes all equipment and systems, required tasks/activities inclusive of necessary permits, work tasks, safety compliance steps, durations associated with tasks/activities and tests, resources, etc.; a draft schedule thirty (30) days following the beginning of construction and a final schedule within sixty (60) days after beginning of construction to the University and the Commissioning Authority (examples provided upon request).

See details required per WBS-Tasks and Activities Schedule to include at end of section: 3.10 Supplements. The thirty (30) and sixty 60) days become fifteen (15) and thirty (30) respectively if project is 3 months or less in construction phase duration. All University and Commissioning Authority comments and concerns will be addressed by the General Contractor and the General Contractor will be wholly responsible for all discrepancies, missed items, etc., and shall address and rectify them immediately at their expense.

10. The Commissioning Authority performs periodic construction observation.

11. The Commissioning Authority develops specific written equipment, system and assembly test procedures for all commissioned equipment. The procedures will include the expected/desired results.

12. The test procedures are executed by the Trade Subcontractor, under the direction of the General Contractor and/or designated Commissioning Coordinator in accordance with and documented by the Commissioning Authority for most equipment. Selected testing is directed and documented by the Trade Subcontractor (refer to Supplement 3 to this Section).

13. Items of non-compliance in material, installation or setup are corrected by the Trade Subcontractor and the system is re-tested.

14. The Commissioning Authority reviews the O&M manuals for LBNL Maximo Asset identification, redlines, clarity, accessibility and completeness that are specific to the equipment installed as part of the project.

15. The Commissioning Authority reviews, pre-approves the training provided by the Trade Subcontractor and verifies that is was completed.

Last revised: 02/06/2020 Page 3 of 41 Updated August 21, 2020

16. Commissioning shall be completed before Substantial Completion inclusive of 7/24 hour test(s), except for trend log monitoring, seasonal testing, near-guarantee-end activities, verification of later controls system training sessions, and review of final red-line drawings.

17. Opposite season or deferred testing and near-guarantee-end activities are conducted, as specified.

H. Design phase reviews, not commissioning during construction, ensure that any given feature qualifies for a Leadership in Energy and Environmental Design (LEED) credit. Gathering LEED required documentation is not part of the commissioning scope of this Project, other than for the commissioning credit itself. All required documentation and procedures to comply with LEED Energy and Atmosphere commissioning prerequisite and the additional point are included in the commissioning scope.

I. LEED requires that all features in the Water Efficiency and in the Energy and Atmosphere and most of the Indoor Environmental Quality areas are appropriately commissioned. The following equipment, systems, assemblies and features will be commissioned utilizing the traditional construction phase commissioning process that includes submittal review, construction checks, testing, observation, and training and documentation verification. All general references to equipment in this document refer only to equipment that is to be commissioned. The responsibility for developing and reviewing forms, overseeing, documenting and witnessing execution and reviewing reports of checks and tests is distributed among constructors, designers and University parties and differs for different equipment types. The Check and Testing Responsibility Table (Supplement 3) included as a supplement to this Section lists these responsibilities.

1. HVAC and mechanical system and all integral equipment controls. All HVAC systems shall be commissioned, including, but not limited to:

a. Air cooled chiller system (chiller, , filtration system, piping, pumps)

b. Heating water system (boilers, piping, pumps, heat pump)

c. Air handlers

d. Hydronic piping (including air separators and expansion tanks)

e. Ductwork

f. Thermal comfort, temperature and humidity control

g. Variable frequency drives

h. Air terminal boxes

i. Fan coil units

j. Restroom exhaust system

k. Facilities Monitoring and Control System

l. TAB work including 7/24 hour test(s)

m. HVAC and envelope differential pressure relationships

n. Fire protection system (including Fire Smoke Dampers, Dampers, and Sequencing of

Smoke Shutdown)

2. Electrical Systems:

a. Scheduled lighting controls

b. Lighting occupancy sensors

c. Stand By power generator system and ATS. Standby generator located adjacent to

Building 70A and is provided by another project. Medium/Low Voltage Switchgears

d. Transformers

e. Substations

f. Uninterruptible Power Supply (UPS)

g. Panel Boards and Switchboards

h. Power and energy meters

i. Variable Frequency Drives (VFD)

j. TAB work

3. Fire and Life Safety

a. Fire protection systems

b. Fire alarm systems

c. Emergency egress lighting

d. Public Announcement

4. Building Automation Systems and Controls

a. Building Automation System

5. Metering

a. Electricity Meters, including end-use electricity sub-metering, and connection to ION enterprise

b. Water Meters, including flow and energy meters such as BTUh meters, and connection to

BMS/BAS

c. Gas Meters (if applicable) including connection to BMS/BAS

Seismic Safety and Modernization (SSM) #LBNL RFP No. GK02112

Last revised: 02/06/2020 Page 4 of 41 Updated August 21, 2020

J. The following static elements and features will be commissioned utilizing documented submittal review and observation, without testing: Details are given later in this Section.

1. Building Envelope. Testing only by the CM-GC.

2. Static LEED Water and Wastewater Efficiency Features: Low flow faucet and shower aerators.

3. Static LEED Energy Features:

a. Exterior windows and doors.

b. Envelope and pipe insulation.

4. Static LEED Indoor Environmental Quality (IEQ) Features:

a. IAQ management during construction and turnover.

b. Envelope air and moisture control design and integrity.

K. Commissioning will be directed by the CM-GC r and/or their designated Commissioning Coordinator in accordance with the Commissioning Authority under the direction of the University.

L. Related Sections

1. The General and Supplementary Conditions, applicable requirements of all Divisions of the

Contract Specifications and all Contract Drawings apply to the work of this Section. In the event of conflict between specific requirements of the various documents, the more restrictive or extensive requirement shall govern.

2. Specific commissioning requirements and related issues are given in the following Sections of the Specifications.

3. Division 01, Section 010000, General Requirements: Submittals: Alerts Subcontractor to submittal requirements for commissioning.

4. Division 01, Section 010000, General Requirements: Final Acceptance: Lists some commissioning tasks required for substantial completion and final acceptance.

5. Division 01, Section 013513.13, Cleanroom Certification and Acceptance, Commissioning requirements for lab and clean room process equipment and systems.

6. Division 23, Section 230800, Commissioning of HVAC: Special Mechanical system requirements and testing requirements by system.

7. Division 26, Section 260800, Commissioning of Electrical Systems: Electrical component testing requirements.

8. Division 01, Section 017900, Demonstration and Training: Training requirements.

9. Division 01, Section 010000, General Requirements: O&M manual requirements.

10. Division 23, Section 230500, Common Results for HVAC: Alerts Trade Subcontractor to commissioning in other sections.

11. Division 26, Section 260500, Common Work Results for Electrical: Alerts Trade Subcontractor to commissioning in other sections.

1.2 DEFINITIONS

A. Active Test: Using hand-held instruments, immediate control system readouts or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the “observation”).

B. Approval: Acceptance that a piece of equipment, system or issue related to it complies with the Contract Documents.

C. Registered Design Professional (RDP): The prime consultant (RDP) and sub-consultants who comprise the design team, generally the HVAC mechanical design engineer and the electrical designer/engineer.

D. Basis of Design: See Design Basis.

E. Certified Testing Company: An industry certified company utilizing industry certified technicians on this project who will perform inspections and testing for equipment and systems. This company is not affiliated or owned by the equipment manufacturer.

F. Commissioning: Commissioning is a systematic process of ensuring that all building systems and assemblies perform interactively according to the University’s objectives and requirements. This is achieved by beginning in the design phase and documenting the University’s Project requirements and continuing through construction, acceptance and the guarantee period with actual verification of function and performance. The commissioning process encompasses and coordinates the traditionally separate functions of system documentation, equipment start-up, control system calibration, testing and balancing, Last revised: 02/06/2020 Page 5 of 41 Updated August 21, 2020 testing and training. The commissioning process does not take away from or reduce the responsibility of the system designers or installing Trade Subcontractors to provide a finished and fully functioning product.

Commissioning during the construction phase is intended to achieve the following specific objectives:

1. Ensure that applicable equipment, systems and assemblies are installed according to the manufacturer’s recommendations and to industry accepted minimum standards and that they receive adequate operational checkout by installing Trade Subcontractors.

2. Ensure and document that equipment, systems and assemblies’ function and perform according to the Contract Documents and the University objectives and requirements.

3. Ensure that O&M manuals are complete.

4. Ensure that the University operating personnel are adequately trained.

G. Commissioning Authority: An independent party, not otherwise associated with the RDP team members, CMGC or the Trade Subcontractors. The Commissioning Authority provides assurance to the University of the General Contractor’s responsibility for compliance with the commissioning requirements per the contract documents and ensures the General Contractor and/or their designated Commissioning coordinator coordinates the day-to-day commissioning activities in concert with the CMGC’s schedule.

The Commissioning Coordinator will lead the commissioning meetings in acquiring information from the General Contractor and/or their designated Commissioning Coordinator regarding commissioning issues resolution, scheduling report status updates, status/completed checklists, status/completed test procedures, etc. The Commissioning Authority will provide recommendations for as needed and/or in accordance with the Project Manager in execution of the commissioning phase of the project.

H. Commissioning Plan: An overall plan, developed before or after bidding, that provides the structure, schedule and coordination planning for the commissioning process. The commissioning plan includes details of the commissioning scope; systems to be commissioned; rigor of commissioning; team contact information; roles and responsibilities of all players; communication and reporting protocols;

commissioning process overview as well as details of submittal activities; construction observation, construction checklist and start-up activities; the process for dealing with deficiencies; test procedure development and execution; O&M manual review and training issues; guarantee period activities;

description of summary report, description of progress and reporting logs and initial schedule including phasing, if applicable. The Commissioning Authority updates the plan as construction progresses.

I. Contract Documents: The documents binding on parties involved in the construction of this Project (Drawings, Specifications, Change Orders, Addenda, Contracts, and Requests for Information).

J. CMGC: The Construction Manager/General Contractor or authorized representative.

K. Facilities Monitoring and Control System (FMCS): The central building energy management control system.

L. Construction Checklist: A list of items to include in the installation, start-up and initial checkout of a piece of equipment or assembly. Construction checklists are primarily static inspections and procedures to prepare the equipment or system for initial operation (e.g., belt tension, oil levels, labels affixed, gauges in place, sensors calibrated, etc.). Some construction checklist items entail simple testing of the function of a component, a piece of equipment or system (such as measuring the voltage imbalance on a three phase pump motor of a chiller system). Construction checklists augment and are combined with the manufacturer’s start-up checklist. An example is provided as supplement to this Section.

M. Datalogging: Monitoring flows, currents, status, pressures, etc., of equipment using stand-alone dataloggers separate from the control system.

N. Deferred Tests: Tests that are performed later with University approval, after substantial completion, due to partial occupancy, equipment, seasonal requirements, design or other site conditions that disallow the test from being performed.

O. Deficiency: A condition in the installation or function of a component, piece of equipment or system that is not in compliance with the Contract Documents (that is, does not perform properly or is not complying with the University’s objectives).

P. Design Basis: The basis and assumptions for calculations, decisions, schemes and product selections to meet the University’s Project requirements ( OPR ) and objectives and to satisfy applicable regulatory requirements, standards and guidelines.

Last revised: 02/06/2020 Page 6 of 41 Updated August 21, 2020

Q. Design Narrative: A narrative submitted with each design submittal describing the concepts and features in the Drawings. The Design Narrative is written by the designer and is updated and increases in detail with each phase of the design. Initially, it may describe general building and space use and later should include detailed space usage and system and assembly descriptions.

R. Design Record: The compilation of the following five elements: University Project Requirements, University Objectives, Design Narrative, Design Basis and Performance Metrics.

S. Documenting Tests: The recording of what actions were taken to perform each individual test procedure, along with the results or system response of the procedure, with any deficiencies noted.

T. Emergency Power and Fire Alarm Response Matrix: A matrix listing all equipment and components (air handlers, dampers, valves, fire doors, elevators, control system, security system, lighting, etc.) with their status and action after each fire alarm initiation type, under emergency/stand by power and the requirements to bring each system back on line.

U. Factory Testing: Testing of equipment on-site or at the factory by factory personnel with the University present.

V. Indirect Indicators: Indicators of a response or condition, such as a reading from a control system screen reporting a damper to be 100 percent closed.

W. Issues Log: Ongoing record of the issues identified during the commissioning process that require or did require correction. For each entry the log includes a unique identification number, identification date, identification party, a short description of the issue, the equipment or assembly it is associated with, a long description of the issue, including cause, implications of the issue, recommendations for correction, assignment of responsibility for correction, an issue closed date and the name of the party verifying the correction. The Commissioning Authority is responsible to maintain the log.

X. Manufacture’s Service Representative (MSR): A company that is certified and trained by a manufacturer to provide startup, testing, and troubleshooting service for equipment.

Y. Monitoring: The recording of parameters (flow, current, status, pressure, etc.) of equipment operation using dataloggers or the trending capabilities of control systems.

Z. NETA: International Electrical Testing Association, Inc.

AA. Non-Compliance: See Deficiency.

BB. Non-Conformance: See Deficiency.

CC. Over-written Value: Writing over a sensor value in the control system to see the response of a system (e.g., changing the outside air temperature value from 50 degrees F to 75 degrees F to verify economizer operation). See also “Simulated Signal.”

DD. University: The representative on the Project that has the authority to act in the University’s behalf in all issues.

EE. University-Contracted Tests: Tests paid for by the University outside the CMGC’s contract and for which the Commissioning Authority does not oversee. These tests will not be repeated during tests if properly documented.

FF. University Objectives: A distillation of the most salient concepts within the University’s Project Requirements considered important to the University to have in writing and to be tracked through design and construction. The University Objectives are sometimes referred to as the design intent.

GG. University Project Requirements: Documentation of the functional requirements of the facility and the expectations of how it will be used and operated. This includes Project and design goals, measurable performance criteria, budgets and schedules and supporting information. This document is analogous to what has traditionally been referred to as the University Program.

Last revised: 02/06/2020 Page 7 of 41 Updated August 21, 2020

HH. Performance Metrics/Benchmark: Measurable indicators that allow verification that a specific University Objective or Requirement or element in the Design Narrative has been met. Performance Metrics are identified throughout the design of the Project with as many as possible being generated during the development of the University Objectives. Metrics are most applicable for those University Objectives that allow for a numerical quantitative evaluation. However, some University Objectives may have Performance Metrics that are not numerical.

II. Phased Commissioning: Commissioning that is completed in phases (by floors, for example) due to the size of the structure or other scheduling issues, in order minimize the total construction time.

JJ. Sampling: Functionally testing only a fraction of the total number of identical or near identical pieces of equipment.

KK. Seasonal Tests: Tests that are deferred until the system(s) will experience conditions closer to their design conditions.

LL. Simulated Condition: Condition that is created for the purpose of testing the response of a system (e.g., applying a hair blower to a space sensor to see the response in a VAV box).

MM. Simulated Signal: Disconnecting a sensor and using a signal generator to send an amperage, resistance or pressure to the transducer and DDC system to simulate a sensor value.

NN. Specifications: The construction Specifications of the Contract Documents.

OO. Start-up: The initial starting or activating of dynamic equipment, including executing construction checklists.

PP. Trade subcontractor: A Lower-tier Subcontractor to the CMGC.

QQ. Systems Manual: A manual providing to the immediate and future operating staff the information needed to understand and optimally operate each system. The manual is in addition to the O&M Manuals submitted by the CMGC. The systems manual focuses on operating, rather than maintaining the equipment, particularly the interactions between equipment. Some components of the manual may reside in the CMGC-submitted O&M Manuals.

RR. Test: Assessments that verify specific components, assemblies, systems, and interfaces among systems function and perform in accordance with the University’s objectives and the Contract Documents. Testing may include using manual (direct observation) or monitoring methods. Testing is the dynamic testing of specific and interacting equipment and systems in full operation. Tests are generally performed after construction checklists and start-up are complete. Some procedures in construction checklists test components, but reference to "testing" generally refers to those equipment and system tests conducted after Trade Subcontractor startup and initial checkout.

SS. Test Procedures (TP): The written procedures and documentation forms of tests used to guide and record testing. For mechanical systems, TPs are composed of repeatable, step-by-step procedures and include the test prerequisites, the test process, the expected outcomes and acceptance criteria. Forms or space for recording the results of tests may be included integrally in the written procedures or attached on separate sheets. For electrical component testing, the procedures may be less step-by-step-like than for dynamic mechanical equipment. For each piece of equipment, checks and test procedures and their documentation record forms may be different documents or combined in the same document, but checks and tests should be grouped. Responsibility for test procedure development is shared between the Commissioning Authority and the Trade Subcontractor according to the Check and Check and Testing Responsibility Table, attached as a supplement to this Section.

TT. Test Requirements: Requirements specifying what modes and functions, etc., shall be tested. The test requirements are not the detailed test procedures.

UU. Trending: Monitoring using the building control system.

VV. Vendor: Supplier of equipment.

Last revised: 02/06/2020 Page 8 of 41 Updated August 21, 2020

WW. Guarantee Period: Refer to Division 01, Section 010000, General Requirements. For commissioning purposes and where referenced in a commissioning section, Guarantee Period is defined as a minimum of one (1) year from substantial completion.

XX. Warranty Period: Refer to Division 01, Section 010000, General Requirements, for a technical definition relative to equipment.

1.3 RESPONSIBILITIES

A. Overview: The responsibilities of the non-CMGC or Trade Subcontractor parties in the commissioning process are summarized in the following articles. It is noted that the services for the University, RDP, mechanical and electrical designers/Engineers, and Commissioning Authority are not provided for in this Contract. That is, the CMGC or Trade Subcontractor is not responsible for providing their services. Their responsibilities are listed here to clarify the commissioning process. Additional responsibilities of subcontractors to the CMGC are found in this Specification and other Project specifications, including, Division 01, General Requirements.

B. Roles & Responsibilities

1. General descriptions of the commissioning roles are as follows:

a. CxA: Coordinates the Cx process, writes tests, oversees and documents performance tests, approves/rejects results on Owner’s behalf in accordance with Subcontract documents.

b. CM: Facilitates the Cx process. Reviews test plans for equipment performance and schedules.

c. GC: Subcontracted by LBNL over lower-tier subcontractors to facilitate the Cx process.

Ensures that subcontractors perform their responsibilities and integrates Cx into the construction process and schedule.

d. Subcontractors: Demonstrate proper system performance.

e. RDP: Performs construction observation, approves O&M manuals, and assists in resolving problems.

f. PM: Facilitates and supports Cx process and gives final approval of the Cx work Ensures that CM-GC and Subcontractors perform their responsibilities to assure commissioning is executed and completed in accordance with the construction and commissioning process per the schedule.

g.

h. OEM: The equipment manufacturers and vendors provide documentation to facilitate the commissioning work and perform subcontracted startup.

C. RDP and Mechanical and Electrical Engineers of Record:

1. All tasks of the designers are applicable only if it is within their contracted scope of services.

2. Construction Phase:

a. Incorporation of Functional Performance Tests (FPT’s) into the Final Bid Documents. FPT’s to be updated as required based upon subsequent input from the CM-GC or Trade Subcontractors and the approved mechanical, electrical and controls submittals.

b. Review the Commissioning Plan.

c. Attend the commissioning planning and kick-off meetings and selected commissioning team meetings.

d. The mechanical and electrical engineer attend the controls integration meetings.

e. Perform normal submittal review, construction observation, O&M manual review.

f. With the Trade Subcontractors and Commissioning Authority, actively assist in the development of the emergency power and fire alarm response matrix.

g. Review the coordination Drawings.

h. Assist (along with the ) in clarifying the operation and control of commissioned equipment in areas where the Specifications, control Drawings or equipment documentation is not sufficient for writing detailed testing procedures.

i. Witness selected testing.

j. Coordinate resolution of system deficiencies and guarantee issues identified during commissioning.

k. Provide an overview of system design and function during selected operator trainings.

Last revised: 02/06/2020 Page 9 of 41 Updated August 21, 2020

l. Provide design basis and design narratives documentation for the Systems Manual.

m. Review Systems Manual.

3. Guarantee Period: Coordinate resolution of design non-conformance and design deficiencies identified during guarantee-period commissioning activities.

D. Commissioning Authority:

1. Construction Phase:

a. The primary role of the Commissioning Authority is to develop and coordinate the execution of a process of improved equipment installation and checkout and to verify and document that systems are functioning in accordance with the documented objectives of the University and in accordance with the Contract Documents. The Commissioning Authority is not responsible for design concept, design criteria, compliance with codes, design or general construction scheduling, cost estimating, or construction management, unless specifically stated otherwise in the Contract Documents. The Commissioning Authority may assist with problem-solving non-conformance or deficiencies, but ultimately that responsibility resides with the CMGC and Trade Subcontractors.

b. Coordinate the commissioning work and with the CMGC to ensure that commissioning activities are being scheduled into the master schedule. The General Contractor and/or their designated Commissioning Coordinator will provide a detailed schedule within the Master Construction Schedule that includes all systems, required tasks/activities inclusive of necessary permits, work tasks, safety compliance steps, etc., to the University and the Commissioning Authority. . The General Contractor and/or their designated Commissioning Coordinator will provide a detailed schedule within the Master Construction Schedule that includes all systems, required tasks/activities inclusive of necessary permits, work tasks, safety compliance steps, durations associated with tasks/activities and resources etc. Submit the first draft thirty (30) days after the beginning of construction and the final after sixty (60) days of construction to the University and the Commissioning Authority. See level of details required per WBS-Tasks and Activities Schedule to include at end of section: 3.10 Supplements. The thirty (30) and sixty 60) days become fifteen (15) and thirty (30) respectively if project is 3 months or less in construction phase duration.

c. Revise, as necessary, the construction phase commissioning plan developed during design, including scope and schedule.

d. Plan and conduct commissioning meetings including the planning and kick-off meetings as needed and distribute minutes.

e. Request and review additional information required to perform commissioning tasks, including O&M materials, Trade Subcontractor start-up and checkout procedures. Before start-up, gather and review the current control sequences and interlocks and work with Trade Subcontractors and design engineers until sufficient clarity has been obtained, in writing, to be able to write detailed testing procedures.

f. Equipment List Matrix.

1) Develop an equipment list matrix of commissioned equipment in a computerized spreadsheet in an organized format and grouped by system.

2) Include:

a) Brief equipment or system name

b) Maximo Asset Number, Tag or ID number

c) Governing specification section

d) Submittal reference number

e) Installation location by room number or coordinates

g. Track status of each piece of equipment in the equipment list matrix for: receipt of documentation, submittal reviewed, construction checklist development and execution progress, startup, test form development and execution, trend log completion, O&M manual submission, training agenda development or receipt and training completion, red-line document submission, opposite season testing, and receipt of Subcontractors’ Performance Guarantee (Section 010000 Attachment A) and receipt of Manufacturers’ Product Warranties with completed Section 010000 Attachment B.

h. Develop the format for, and coordinate the completion of the emergency power and fire alarm response matrix as defined in this Section.

i. Review normal Trade Subcontractor submittals applicable to systems being commissioned concurrent with the RDP reviews for compliance with commissioning and O&M manuals and coordination issues.

j. Review requests for information and change orders for impact on commissioning and University’s objectives.

Last revised: 02/06/2020 Page 10 of 41 Updated August 21, 2020

k. Review coordination Drawings and ensure that trades are making a reasonable effort to coordinate and notify the University and CM-GC accordingly for CM-GC compliance enforcement

l. Review Trade Subcontractor’s developed start-up and initial systems checkout plans with the Trade Subcontractors for selected equipment.

m. Perform site visits, as necessary, to observe component and system installations. Attend selected planning and job-site meetings to obtain information on construction progress.

Review construction meeting minutes for revisions/substitutions relating to the commissioning process. Assist in resolving any discrepancies.

n. Coordinate with the RDP to verify that any sustainable design requirements affected by system performance or commissioning are addressed.

o. Document construction checklist completion by reviewing completed construction checklists and by selected site observation.

p. Document systems start-up by reviewing start-up reports and by selected site observation.

q. Write step-by-step test procedures and documentation formats for commissioned equipment and assemblies, as assigned in the Check and Check and Testing Responsibility Table provided as a Supplement to this Section. Test procedures will include active testing, energy management control system trending and may include stand-alone data-logger monitoring.

1) Existing written testing requirements and procedures in accepted or required standards, guidelines or Specifications will suffice as the test procedures for the following: Regulated tests such as fire alarm, fire suppression, elevators, NETA electrical equipment tests, test procedures within these specifications and common Trade Subcontractor tests such as duct and piping tests.

r. Coordinate and assist in development of test plans, execution and documentation of tests of commissioned equipment overseen by regulatory authorities and ensure that such tests meet the testing and documentation rigor desired by the University. The systems for which this applies are indicated in the Check and Testing Responsibility Table in the supplements to this Section. Testing and commissioning for these systems shall be per the requirements of those Sections of the Specifications and the governing codes and standards. The Commissioning Authority shall work with the CMGC and Trade Subcontractors and University to ensure that these tests are scheduled and coordinated with the interfaces to other systems on the Project as well as requirements of the authorities having jurisdiction.

Coordination efforts shall include but not be limited to:

1) Developing a logical test plan that flows from the component level on the various systems to the integrated testing of the systems as they interact with each other.

2) Verification that all necessary documentation requirements are met for all parties including but not limited to the authorities having jurisdiction, the University and the insurance underwriter.

3) Promoting and being proactive in the process and ensuring that all involved parties communicate effectively across the inter-discipline boundaries as required for successful integrated testing of the systems.

s. Coordinate testing for all commissioned systems and assemblies. Witness and document active tests performed by the Trade Subcontractors for all commissioned systems and assemblies, except: a) some smaller equipment may be tested and documented by the Trade Subcontractors, at the Commissioning Authority's discretion, b) electrical equipment testing and regulated testing may be directed and documented by the Trade Subcontractor with only spot witnessing and report review by the Commissioning Authority. Refer to the Check and Testing Responsibility Table provided as a supplement to this Section for more specific delineation. The testing shall include operating the system and components through each of the written sequences of operation, and other significant modes and sequences, including start-up, shutdown, unoccupied mode, manual mode, staging, miscellaneous alarms, power failure, security alarm when impacted and interlocks with other systems or equipment. Sensors and actuators shall be calibrated during construction check listing by the installing Trade Subcontractors, and spot-checked by the commissioning provider during testing. Analyze functional performance trend logs and monitoring data to verify performance. Coordinate retesting as necessary until satisfactory performance is achieved.

t. After active testing and initial trouble shooting is complete, monitor system operation and performance for selected data points for up to 2 weeks by requesting trend logs from the Trade Subcontractor from the building automation system. Analyze monitored data to verify operation and performance and issue a written report.

Last revised: 02/06/2020 Page 11 of 41 Updated August 21, 2020

u. Maintain a master Issues Log and a separate record of testing. Report all issues as they occur directly to the University. Provide directly to the University written progress reports and test results with recommended actions.

v. Review equipment manufacturers’ product warranties to ensure that the University responsibilities are clearly defined.

w. Oversee and approve the training of the University’s operating personnel.

x. Review and approve the preparation (to include labeling with Maximo Asset Numbers and redlining) of the O&M manuals for commissioned equipment.

y. Compile a Commissioning Record.

z. Compile a Systems Manual according to the definition and description in this Section for all commissioned systems.

2. HVAC and Mechanical-Specific Tasks of the Commissioning Authority

a. Controls Integration Meetings: Coordinate the approval process for the control system database and programming (point names, alarm limits, access levels, graphic details and layout, specific control strategies and sequences, etc.) via a series of meetings attended by the Trade Subcontractor, University, and Mechanical Engineer. The meetings shall occur after the software and data base drawings are issued for initial review, but prior to the development of the database and code for any piece of equipment.

b. Witness HVAC piping pressure test and flushing, sufficient to be confident that proper procedures were followed. Include documentation of all testing in the Commissioning Record.

c. Witness any ductwork testing and cleaning sufficient to be confident that proper procedures were followed. Include documentation of all testing in the Commissioning Record.

d. Approve air and water systems balancing by selected site observation, by reviewing completed reports and by spot testing.

e. Coordinate and approve the start-up of permanent equipment for temporary space conditioning during construction and review the plans for the use of temporary space conditioning equipment.

3. Process Systems Commissioning:

a. Refer to Division 01, Section 013513.13, Cleanroom Certification and Acceptance, for specific requirements.

4. Electrical System Specific Tasks of the Commissioning Authority: See Division 26, Section

260800, Commissioning of Electrical Systems, for Electrical System Requirements.

5. Static LEED Systems:

a. Refer to the Static elements commissioning article later in this Section.

6. Subcontractor’s Performance Guarantee Period:

a. Coordinate and supervise required opposite season or deferred testing and deficiency corrections and provide the final testing and sequence of operation update documentation for the Commissioning Record and O&M manuals.

b. Return to the site approximately 10 months into the 12 month performance guarantee period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal commissioning. Also interview facility staff and identify problems or concerns they have with operating the building as originally intended. Make suggestions for improvements and for recording these changes in the O&M manuals. Identify deficiencies that may come under performance guarantee or under the original construction contract. Assist facility staff in developing reports and documents and requests for services to remedy outstanding problems.

E. University:

1. Construction Phase:

a. Furnish a copy of all Construction Documents, addenda, requests for information, change orders and approved submittals and Shop Drawings related to commissioned equipment to the Commissioning Authority for their permanent retention.

b. Facilitate the coordination of the commissioning work by the Commissioning Authority.

c. With the CMGC and Commissioning Authority, ensure that commissioning activities are being scheduled into the master schedule.

d. Arrange for facility operating and maintenance personnel to attend various field commissioning activities and field training sessions according to the Commissioning Plan.

e. Participate in issue resolution as necessary.

f. Provide final approval for the completion of the commissioning work.

2. Guarantee Period: Ensure that any seasonal or deferred testing and any deficiency issues are addressed.

Last revised: 02/06/2020 Page 12 of 41 Updated August 21, 2020

F. General Contractor (GC)/CMGC

1. The GC/CMGC is fully responsible to the University for all Trade Subcontractor and CMGC listed responsibilities in the specifications.