About this file

The file is a Submittal Registry for a federal contract opportunity (Solicitation Number FTQW-17-1015-2) for renovating Building 1300 at Eielson Air Force Base in Alaska. The project scope includes converting a steam boiler to a hydronic boiler system, performing HVAC testing and balancing, repairing domestic water and fire suppression systems, replacing the roof, roof drains, and interior rain leaders. The contract is classified under NAICS code 236210 with a small business size standard of $45M, and the project magnitude is between $1,000,000 and $5,000,000.

Key dates include a mandatory site visit on 4 June 2025 at 9:00am AKDT, with questions due by 11 June 2025 at 2:00pm AKDT. Electronic bids must be submitted via email to 354CONS.PKA.MonitorConstruction@us.af.mil, with bid opening conducted at Building 2310 Central Ave. The solicitation notes that funds are not currently available, and the government reserves the right to cancel the solicitation. The submittal registry details extensive documentation requirements across multiple specification sections, including preconstruction submittals, product data, test reports, certificates, and closeout documentation for various project components such as demolition, hazardous waste management, insulation, roofing, fire protection systems, and mechanical systems.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

SUBMITTAL REGISTERCONTRACT NO.
TITLE AND LOCATION
RENO CAC B1300CONTRACTOR
A C T I V I T Y
N OT R A N S M I T T A L
N OS P E C
S E C TDESCRIPTION ITEM SUBMITTEDP A R A

G # R A P H G O V C T L A O S R S I A F / I E C A R T E I V O W

N RCONTRACTOR: SCHEDULE DATESCONTRACTOR ACTIONAPPROVING AUTHORITYMAILED TO CONTR/
DATE RCD FRM APPR AUTHREMARKS
SUBMITAPPROVAL NEEDED BYMATERIAL NEEDED BYA C T I O N
C O D EDATE OF ACTIONDATE FWD TO APPR AUTH/
DATE RCD FROM CONTRDATE FWD TO OTHER REVIEWERDATE RCD FROM OTH REVIEWERA C T I O N
C O D EDATE OF ACTION
(a)(b)(c)(d)(e)(f)(g)(h)(i)(j)(k)(l)(m)(n)(o)(p)(q)(r)
01 11 00SD-01 Preconstruction Submittals
Scope Of Work Description1.5.2G CES
Site Plan With Area Of Work1.5.2G CES
Noted
Commercial Utility Clearance1.5.2G CES
Number
Hazardous Materials Training1.5.2G CES
Certificates
Environmental Management1.5.2G CES
System (Ems) Training Certificats
Approved Sampling And Analysis1.5.2
Plan
Salvage Plan1.8G CES
Hot Work Permits1.5.5G CEF
Work Clearance Request1.5.5G CES
01 14 00SD-01 Preconstruction Submittals
List of Contact Personnel1.2.1.1
01 30 00SD-01 Preconstruction Submittals
Progress and Completion1.3
Pictures
01 32 01SD-01 Preconstruction Submittals
01 32 01Project Scheduler Qualifications1.3
Preliminary Project Schedule3.4.1G CES
Submission
Initial Project Schedule3.4.2G CES
Submission
Periodic Schedule Updates3.4.3G CES
01 33 00SD-01 Preconstruction Submittals
Submittal Register1.7G CES
01 35 26SD-01 Preconstruction Submittals
Accident Prevention Plan (APP)1.8G CES
SD-06 Test Reports
Accident Reports1.12.2G CES
LHE Inspection Reports1.12.3
Monthly Exposure Reports1.5G CES
SD-07 Certificates
Activity Hazard Analysis (AHA)1.9G CES
Certificate of Compliance1.12.4
Standard Lift Plan1.12.4G CES
01 45 00SD-01 Preconstruction Submittals
Contractor Quality Control (CQC)1.5.2G
Plan
SD-06 Test Reports
Verification Statement1.11.3
SD-07 Certificates
Certificate Of Readiness1.6.5.1G
01 50 00SD-01 Preconstruction Submittals
01 50 00Construction Site Plan1.3G CES
01 57 19SD-01 Preconstruction Submittals
Preconstruction Survey1.6.1G CEIE
Solid Waste Management Permit1.10G CEIE
Regulatory Notifications1.6.2G CEIE
ENVIRONMENTAL1.7G CEIE
PROTECTION PLAN (EPP)
Employee Training Records1.6.5G CEIE
Environmental Manager1.6.4G CEIE
Qualifications
Initial Hazardous Material3.8G CEIE
Inventory Log
01 57 19Initial Hazardous Waste1.7.8G CEIE
Accumulation Log
EMS General Awareness1.4.1
Training
SD-03 Product Data
Product Data1.7.12.3G CEIE
SD-06 Test Reports
Laboratory Analysis3.7.1.1.2
Inspection Reports3.2.1.3
Solid Waste Management Report3.7.2.1G CEIE
Laboratory Test Reports1.14.2G CEIE
SD-07 Certificates
Employee Training Records1.6.5G CEIE
Lead
Certificate Of Disposal3.7.2.1
01 57 19Hazardous Waste Accumulation1.14G CEIE
Log
SD-11 Closeout Submittals
Waste Determination3.7.1G CEIE
Documentation
Disposal Documentation for3.7.3.6G CEIE
Hazardous and Regulated Waste
Assembled Employee Training1.6.5G CEIE
Records
Solid Waste Management Permit1.10G CEIE
Solid Waste Management Report3.7.2.1G CEIE
Hazardous Waste/Debris3.7.3.1G CEIE
Management
Regulatory Notifications1.6.2G CEIE
Sales Documentation3.7.2.1G CEIE
Contractor Certification3.7.2.1
As-Built Topographic Survey3.2.1.5
Certificate of Disposal3.7.2.1
ADEC Approved Disposal Facility3.14.1G CEIE
Weight and/or Acceptance Ticket
ADEC Approved Disposal Facility3.14.1G CEIE
Certificate of Incineration or
Disposal
01 57 19Hazardous Waste Accumulation1.14G CEIE
Log
Final Hazardous Material3.8G CEIE
Inventory Log
Ammendment to the EAFB Oil3.13.2
Discharge Prevention and
Contingency Plan
Nonhazardous Solid Waste3.6.2G CEIE
Diversion Report
01 74 19SD-01 Preconstruction Submittals
Construction Waste Management1.7G CEIE
Plan
SD-06 Test Reports
Quarterly Reports1.9.2
Annual Report1.9.3
SD-11 Closeout Submittals
Final Construction Waste1.10S
Diversion Report
01 78 00SD-03 Product Data
Warranty Management Plan1.8.1G CES
Warranty Tags1.8.5
Spare Parts Data1.6
SD-08 Manufacturer’s Instructions
Instructions1.8.1
01 78 00SD-10 Operation and Maintenance
Data
Operation and Maintenance3.5G CES
Manuals
SD-11 Closeout Submittals
As-Built Drawings3.1G CES
Record Drawings3.3G CES
Record Model2.2G CES
Warranted Equipment and1.8.1
Materials
Final Approved Shop Drawings3.4G CES
Interim DD FORM 13543.7.1G CES
List Of Installed Building3.7.2
Equipment Items For DD Form
1354
01 78 23SD-10 Operation and Maintenance
Data
Facility Data Workbook1.4G
Training Plan3.1.1G
Training Outline3.1.3G
Training Content3.1.2G
Operation And Maintenance3.2.1G
Manual, Progress Submittal
Operation And Maintenance3.2.2G
Manual, Prefinal Submittal
01 78 23Operation And Maintenance3.2.3G
Manual, Final Submittal
SD-11 Closeout Submittals
Training Video Recording3.1.4G
Validation of Training Completion3.1.6G
Training Plan3.1.1G
Record Drawings And Utility1.6.6.7G
Systems
01 91 00.15SD-01 Preconstruction Submittals
Commissioning Firm1.7G
Lead Commissioning Specialist1.7.1G
Technical Commissioning1.7.2G
Specialists
SD-06 Test Reports
Interim Construction Phase3.1.2.1G
Commissioning Plan
Final Construction Phase3.1.2.2G
Commissioning Plan
Pre-Functional Checklists3.1.4.2G
Issues Log1.8G
Commissioning Report3.2G
Post-Construction Trend Log3.3.1G
Report
SD-07 Certificates
Certificate of Readiness1.9G
01 91 00.15SD-10 Operation and Maintenance
Data
Training Plan3.1.5G
Training Attendance Rosters3.1.5G
Maintenance And Service Life3.1.7G
Plans
Systems Manual3.1.6G
SD-11 Closeout Submittals
Construction Phase3.1.2.1G
Commissioning Plan
Final Commissioning Report3.2G
02 41 00SD-01 Preconstruction Submittals
Demolition Plan1.2.1G
Existing Conditions1.11G
SD-07 Certificates
Notification1.7G
SD-11 Closeout Submittals
Receipts3.3.4G
02 81 00SD-03 Product Data
Packaging Notifications2.1.1
Hazardous Waste Management3.1G
Plan
Onsite Hazardous Waste3.2G
Management
Notices of Non-Compliance and3.3
Notices of Violation
SD-06 Test Reports
Recordkeeping3.6G
Exception Report3.6G
Spill Response3.7
SD-07 Certificates
Transportation and Disposal1.4.1G
Coordinator
Training1.4.2G
Certification1.4.3
Shipping Documents and3.3.3G
Packagings Certification
02 81 00Security Plan3.3.4
Certificates of Disposal3.3.5
Waste Minimization3.5
07 22 00SD-02 Shop Drawings
Insulation Board Layout1.3G
Verification of Existing Conditions1.3G
SD-03 Product Data
Insulation2.1G
Cover Board1.4G
Fasteners2.4G
Moisture Control2.3G
Recycled Content For Insulation2.1.2S
SD-05 Design Data
Wind Resistance1.7G
SD-06 Test Reports
Flame Spread Rating1.8.1G
SD-07 Certificates
Installer Qualifications1.6G
Certificates Of Compliance For1.6G
Felt Materials
Indoor Air Quality For Insulation2.1.3S
Acceptable Foam Blowing Agents2.1.4S
SD-08 Manufacturer’s Instructions
Fasteners2.4G
Insulation2.1G
07 54 19SD-02 Shop Drawings
07 54 19Detail Drawings1.6G
Roof Plan1.6G
SD-03 Product Data
PVC Roofing Membrane3.3.2G
Bonding Adhesive2.1.2
Flashing1.5.3G
Flashing3.3.2.2G
Membrane Fasteners and Plates2.1.5
Roof Insulation2.1.7G
Protection Mat3.3.2.5
Water Cutoffs3.7.1
Information Card1.10.1G
SD-05 Design Data
Wind Uplift Resistance1.3.2G
SD-07 Certificates
Qualification of Manufacturer1.5.1
Qualifications of Applicator1.5.2
Fire Resistance1.3.1
Minimum Polymer Thickness2.1.1
Minimum Polymer Thickness2.1.4
Sample1.10G
SD-08 Manufacturer’s Instructions
Application Method3.3G
Membrane Flashing2.1.4G
Membrane Flashing3.4.2G
07 54 19Perimeter and High Wind3.3.4
Attachment
Auxiliary Fasteners2.1.5.2
Cold Weather1.8G
SD-11 Closeout Submittals
Warranty1.10G
Information Card1.10.1G
Instructions to Government3.10G
Personnel
07 60 00SD-02 Shop Drawings
Exposed Sheet Metal2.1.1G
Gravel Stops and fascia2.1.1G
Flashing for Roof Drains3.1.12G
Counterflashing3.1.9G
Flashing at Roof Penetrations3.1.15G
and Equipment Supports
Copings3.1.16G
Drip Edges3.1.11G
Eave Flashing3.1.13G
SD-08 Manufacturer’s Instructions
Instructions for Installation1.4.2G
Quality Control Plan3.5G
SD-10 Operation and Maintenance
Data
Cleaning and Maintenance1.4.2G
07 84 00SD-02 Shop Drawings
07 84 00Firestopping System2.1G
SD-03 Product Data
Firestopping Materials2.2G
SD-06 Test Reports
Inspection3.3G
SD-07 Certificates
Inspector Qualifications1.5.2G
Installer Qualifications1.5.1G
07 92 00SD-03 Product Data
Sealants2.1
Primers2.2
Bond Breakers2.3
Backstops2.4
SD-07 Certificates
Indoor Air Quality For Interior2.1.1
Sealants
Indoor Air Quality For Interior2.1.3
Floor Joint Sealants
Indoor Air Quality For Interior2.1.4
Acoustical Sealants
Indoor Air Quality For Interior2.5
Caulking
21 13 13Sprinkler System Installer1.4.2.2G
21 13 13SD-06 Test Reports
Test Procedures3.5.1G
SD-07 Certificates
Verification of Compliant3.5.2.1G
Installation
Request for Government Final3.5.2.2G
Test
SD-10 Operation and Maintenance
Data
Operating and Maintenance3.7G
(O&M) Instructions
Spare Parts1.6G
SD-11 Closeout Submittals
As-built drawings3.7G
22 00 00SD-03 Product Data
Backflow Prevention Assemblies3.6.1.1G
Relief Valves2.3.1G
Thermostatic Mixing Valves2.3.2G
Backflow Preventers2.4G
SD-06 Test Reports
Tests, Flushing and Disinfection3.6G
Test of Backflow Prevention3.6.1.1G
Assemblies
SD-07 Certificates
22 00 00Materials and Equipment1.3G
SD-10 Operation and Maintenance
Data
Plumbing System3.6.1G
23 05 48.19SD-02 Shop Drawings
Coupling and Bracing3.1G
SD-03 Product Data
SD-05 Design Data
SD-06 Test Reports
23 05 93SD-01 Preconstruction Submittals
Records of Existing Conditions1.3.3G
TAB Firm1.5.3.1G
TAB Team Assistants1.2G
TAB Team Engineer1.2G
TAB Specialist1.5.3.2G
TAB Team Field Leader1.2G
Prerequisite HVAC Work Check1.7.2G
Out List
SD-02 Shop Drawings
23 05 93TAB Schematic Drawings and1.3.3G
Report Forms
SD-03 Product Data
Equipment and Performance1.3G
Data
TAB Related HVAC Submittals1.5.3.4G
TAB Procedures1.5.2G
Calibration1.5.2G
Systems Readiness Check1.3.3G
TAB Execution1.5.4G
TAB Verification1.5.4.3G
SD-06 Test Reports
TAB Report1.5.5.2G
SD-07 Certificates
Independent TAB Agency and1.5.1G
Personnel Qualifications
TAB Submittal and Work Schedule1.7.2G
TAB Pre-Field Engineering1.7.2.3G
Report
Advanced Notice for TAB Field1.7.2G
Work
23 07 00SD-02 Shop Drawings
Pipe Insulation Systems2.3G
Duct Insulation Systems3.3G
SD-03 Product Data
Pipe Insulation Systems2.3G
recycled content for insulation2.3.1G
materials
Thermal Insulation2.2.1.3G
SD-07 Certificates
Indoor air quality for adhesives2.2.1G
SD-08 Manufacturer’s Instructions
Pipe Insulation Systems2.3G
SD-03 Product Data
SD-06 Test Reports
28 31 76Installer1.9.2.4G
Nameplates1.9.1.3G
Wiring Diagrams1.9.1.4G
Initiating devices1.9.1.7G
Alarm Wiring2.14G
Back Boxes and Conduit3.3.4G
Test Procedures3.8.1G
Verification of Compliant3.8.2.1G
Installation
Request for Government Final3.8.2.2G
Test
SD-10 Operation and Maintenance
Data
28 31 76Operation and Maintenance3.10G
(O&M) Instructions
Instruction of Government3.11G
Employees
SD-11 Closeout Submittals
As-Built Drawings1.9.1.13G