44-Sec 03 20 00 Concrete Reinforcement.pdf

PDF 52 KB Posted

Attached to
Horsham Business Park Lighting - Phase II
Solicitation number
US.199180
Issued by
Montgomery County, Pennsylvania

View the file

Other files

File Type Posted
31-Sec 01 33 00-Submittals.pdf PDF
22-Doc 00 01 15-List of Drawing Sheets.pdf PDF
7-Doc 00 45 53-Agreement of Surety Company.pdf PDF
25-Doc 00 01 10-Table of Contents.pdf PDF
17-Doc 00 11 13-Advertisement for Bids.pdf PDF
24-Doc 00 61 13.13-Performance Bond.pdf PDF
29-Sec 01 56 39-Landscape Protection.pdf PDF
8-Doc 00 52 00-Agreement.pdf PDF
18-Doc 00 73 00-Supplementary Conditions.pdf PDF
4-Doc 00 62 16-Certificate of Insurance.pdf PDF
23-Doc 00 72 00-General Conditions.pdf PDF
35-Sec 01 11 13-Summary of Work.pdf PDF
33-Sec 01 70 00-Contract Closeout.pdf PDF
12-Doc 00 45 19-Non-Collusion Affidavit.pdf PDF
42-Sec 03 30 00-Cast in Place Concrete.pdf PDF
15-Doc 00 21 13.1-Instructions for Electronic Bidding.pdf PDF
5-Doc 00 73 00-Appendicies.pdf PDF
3-Doc 00 73 00 01-Appendix A - Prevailing Wage Rates.pdf PDF
14-Doc 00 45 13 - Bidder Qualification Statement.pdf PDF
45-Electrical Plans - For Permit Horsham Pedestrian Lts Elec 07312025.pdf PDF
41-Sec 01 42 13-Organization Reference Acronyms.pdf PDF
46-SITE PLAN FOR BID 2025 07 28.pdf PDF
32-Sec 01 40 00-Quality Control.pdf PDF
20-Doc 00 01 01-Cover.pdf PDF
37-Sec 01 31 00-Coordination and Meetings.pdf PDF
9-Doc 00 91 13-Addenda.pdf PDF
30-Sec 01 50 00-Construction Facilities and Temp. Controls.pdf PDF
21-Doc 00 65 19.19-Consent of Surety to Final Payment.pdf PDF
2-Doc 00 61 13.16-Payment Bond.pdf PDF
19-Doc 00 65 19.16-Contractors Release of Liens.pdf PDF
1-Doc 00 21 13-Instructions to Bidders.pdf PDF
27-Doc 00 43 13 Bid Bond (penal sum form).pdf PDF
16-Doc 00 73 00 02-Appendix B - Public Works Employment Verification.pdf PDF
38-Sec 01 29 00-Contract Considerations.pdf PDF
36-Sec 01 71 13-Mobilization.pdf PDF
43-Sec 32 92 00-Finish Grading, Seeding and Sodding.pdf PDF
11-Doc 00 45 10-Bidders Acknowledgement Form.pdf PDF
40-Sec 01 55 26-Traffic Regulation.pdf PDF
6-Doc 00 41 00-Bid Form PennBid.pdf PDF
28-Sec 01 60 00-Material and Equipment.pdf PDF
26-Doc 00 65 19.13-Contractors Affidavit.pdf PDF
13-Doc 00 41 00-Bid Form.pdf PDF
39-Sec 01 22 00-Measurement Payment.pdf PDF
10-Doc 00 61 19-Maintenance Bond.pdf PDF
34-Sec 01 57 13-Soil Erosion and Sediment Control.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONCRETE REINFORCEMENT

03 20 00-1

SECTION 03 20 00

CONCRETE REINFORCEMENT

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Reinforcing steel bars and accessories for cast-in-place concrete.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere.

1. Section 03 30 00: Cast-in-Place Concrete

1.03 REFERENCES

A. ACI 301 - Structural Concrete for Buildings.

B. ACI 318 - Building Code Requirements for Reinforced Concrete.

C. ASTM A185 - Welded Steel Wire Fabric for Concrete Reinforcement.

D. ASTM A615 - Deformed and Plain Billet Steel Bars for Concrete Reinforcement.

E. ASTM A775 - Epoxy-Coated Reinforcing Steel Bars.

F. ASTM D3963 - Epoxy-Coated Reinforcing Steel.

G. CRSI - Concrete Reinforcing Steel Institute - Manual of Practice.

H. CRSI 63 - Recommended Practice for Placing Reinforcing Bars.

I. CRSI 65 - Recommended Practice for Placing Bar Supports, Specifications and Nomenclature.

1.04 SUBMITTALS FOR REVIEW

A. Section 01 33 00 - Submittals: Procedures for submittals.

B. Shop Drawings: Indicate bar sizes, spacings, locations, and quantities of reinforcing steel, bending and cutting schedules and supporting and spacing devices.

1.05 QUALITY ASSURANCE

A. Perform Work in accordance with CRSI 63, 65 and Manual of Practice, ACI 301, and ACI

318. Maintain one copy of each document on site.

B. Provide Engineer with access to fabrication plant to facilitate inspection of reinforcement.

Provide notification of commencement and duration of shop fabrication in sufficient time to allow inspection.

C. Design reinforcement under direct supervision of a Professional Structural Engineer experienced in design of this Work and licensed in the Commonwealth of Pennsylvania.

CONCRETE REINFORCEMENT

03 20 00-2

D. Welders: Certificates: Submit under provisions of Section 01 40 00 Manufacturer’s Certificates, certifying welders employed on the Work, verifying AWS qualification within the previous 12 months.

PART 2 PRODUCTS

2.01 REINFORCEMENT

A. Reinforcing Steel: ASTM A615, 60 ksi yield grade; deformed billet steel bars, unfinished.

2.02 ACCESSORIES

A. Tie Wire: Minimum 16 gage annealed type, epoxy coated.

B. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for strength and support of reinforcement during concrete placement conditions

C. Special Chairs, Bolsters, Bar Supports, Spacers Adjacent to Weather Exposed Concrete Surfaces: Plastic coated steel type; size and shape as required.

2.03 FABRICATION

A. Fabricate concrete reinforcing in accordance with CRSI Manual of Practice.

B. Locate reinforcing splices not indicated on drawings, at point of minimum stress.

PART 3 EXECUTION

3.01 PLACEMENT

A. Place, support and secure reinforcement against displacement. Do not deviate from required position.

B. Do not displace or damage vapor barrier.

C. Accommodate placement of formed openings.

D. Conform to Act 318 code for concrete cover over reinforcement.

END OF SECTION