SUBMITTALS
01 33 00-1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Submittal procedures.
2. Construction progress schedules.
3. Product data.
4. Shop Drawings.
5. Samples.
6. Design data.
7. Test reports.
8. Certificates.
9. Manufacturer’s instructions.
10. Manufacturer’s field reports.
11. Erection drawings.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 40 00: Quality Control: Manufacturers' field services.
2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.
1.03 REFERENCES
A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.
1.04 SUBMITTAL PROCEDURES
A. Transmit each submittal to Engineer.
B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.
C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.
D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
01 33 00-2
E. Schedule submittals to expedite the Project and to coordinate submission of related items.
F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.
G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.
H. Provide space for Contractor and Engineer review stamps.
I. When revised for resubmission, identify all changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.05 CONSTRUCTION PROGRESS SCHEDULES
A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.
B. Revise and resubmit as required.
C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.
D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.
E. Submit network analysis diagram using either the critical path or PERT method, as outlined in AGC - The Use of CPM in Construction.
F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.
G. Indicate estimated percentage of completion for each item of Work at each submission.
H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.
1.06 PRODUCT DATA
A. Product Data For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.
01 33 00-3
C. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.
D. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
1.07 SHOP DRAWINGS
A. Shop Drawings For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.
1.08 CERTIFICATES
A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.
1.09 MANUFACTURER’S INSTRUCTIONS
A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.
B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION