31-Sec 01 33 00-Submittals.pdf

PDF 55 KB Posted

Attached to
Horsham Business Park Lighting - Phase II
Solicitation number
US.199180
Issued by
Montgomery County, Pennsylvania

View the file

Other files

File Type Posted
22-Doc 00 01 15-List of Drawing Sheets.pdf PDF
7-Doc 00 45 53-Agreement of Surety Company.pdf PDF
25-Doc 00 01 10-Table of Contents.pdf PDF
17-Doc 00 11 13-Advertisement for Bids.pdf PDF
24-Doc 00 61 13.13-Performance Bond.pdf PDF
29-Sec 01 56 39-Landscape Protection.pdf PDF
8-Doc 00 52 00-Agreement.pdf PDF
18-Doc 00 73 00-Supplementary Conditions.pdf PDF
4-Doc 00 62 16-Certificate of Insurance.pdf PDF
23-Doc 00 72 00-General Conditions.pdf PDF
35-Sec 01 11 13-Summary of Work.pdf PDF
33-Sec 01 70 00-Contract Closeout.pdf PDF
12-Doc 00 45 19-Non-Collusion Affidavit.pdf PDF
42-Sec 03 30 00-Cast in Place Concrete.pdf PDF
15-Doc 00 21 13.1-Instructions for Electronic Bidding.pdf PDF
5-Doc 00 73 00-Appendicies.pdf PDF
3-Doc 00 73 00 01-Appendix A - Prevailing Wage Rates.pdf PDF
14-Doc 00 45 13 - Bidder Qualification Statement.pdf PDF
45-Electrical Plans - For Permit Horsham Pedestrian Lts Elec 07312025.pdf PDF
41-Sec 01 42 13-Organization Reference Acronyms.pdf PDF
46-SITE PLAN FOR BID 2025 07 28.pdf PDF
32-Sec 01 40 00-Quality Control.pdf PDF
20-Doc 00 01 01-Cover.pdf PDF
37-Sec 01 31 00-Coordination and Meetings.pdf PDF
9-Doc 00 91 13-Addenda.pdf PDF
30-Sec 01 50 00-Construction Facilities and Temp. Controls.pdf PDF
21-Doc 00 65 19.19-Consent of Surety to Final Payment.pdf PDF
2-Doc 00 61 13.16-Payment Bond.pdf PDF
19-Doc 00 65 19.16-Contractors Release of Liens.pdf PDF
1-Doc 00 21 13-Instructions to Bidders.pdf PDF
27-Doc 00 43 13 Bid Bond (penal sum form).pdf PDF
16-Doc 00 73 00 02-Appendix B - Public Works Employment Verification.pdf PDF
38-Sec 01 29 00-Contract Considerations.pdf PDF
36-Sec 01 71 13-Mobilization.pdf PDF
43-Sec 32 92 00-Finish Grading, Seeding and Sodding.pdf PDF
11-Doc 00 45 10-Bidders Acknowledgement Form.pdf PDF
40-Sec 01 55 26-Traffic Regulation.pdf PDF
6-Doc 00 41 00-Bid Form PennBid.pdf PDF
28-Sec 01 60 00-Material and Equipment.pdf PDF
26-Doc 00 65 19.13-Contractors Affidavit.pdf PDF
13-Doc 00 41 00-Bid Form.pdf PDF
39-Sec 01 22 00-Measurement Payment.pdf PDF
44-Sec 03 20 00 Concrete Reinforcement.pdf PDF
10-Doc 00 61 19-Maintenance Bond.pdf PDF
34-Sec 01 57 13-Soil Erosion and Sediment Control.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS

01 33 00-1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Submittal procedures.

2. Construction progress schedules.

3. Product data.

4. Shop Drawings.

5. Samples.

6. Design data.

7. Test reports.

8. Certificates.

9. Manufacturer’s instructions.

10. Manufacturer’s field reports.

11. Erection drawings.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 40 00: Quality Control: Manufacturers' field services.

2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.

1.03 REFERENCES

A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.

1.04 SUBMITTAL PROCEDURES

A. Transmit each submittal to Engineer.

B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.

01 33 00-2

E. Schedule submittals to expedite the Project and to coordinate submission of related items.

F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Engineer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.05 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.

B. Revise and resubmit as required.

C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.

D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.

E. Submit network analysis diagram using either the critical path or PERT method, as outlined in AGC - The Use of CPM in Construction.

F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.

G. Indicate estimated percentage of completion for each item of Work at each submission.

H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.

1.06 PRODUCT DATA

A. Product Data For Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

01 33 00-3

C. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.

D. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

1.07 SHOP DRAWINGS

A. Shop Drawings For Review:

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

1.08 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.

1.09 MANUFACTURER’S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

PART 1 GENERAL

File details come from the government source that posted it. Updated .